Worcester Play Plan Priority Projects Update Report
DecidedCommittee1 paper
AI summaryWorcester City Council's Place and Economic Development Committee has noted 2025/26 progress on the Worcester Play Plan and endorsed four s106-funded priority projects for 2026/27, with procurement authority delegated to the Corporate Director.
Moneys106 funding only from 2026/27CIL and play maintenance reserve fully used
What happens nextProcure contracts for 2026/27 projectsAfter January consultation and February procurement
Who it affectsNot stated
What was decided
The Committee noted the report and the progress made in 2025/26 on the Worcester Play Plan, including completed and in-progress play area works across the city. Report 1.1, 2.1
The Committee noted the priority projects for delivery during 2026/27 and delegated authority to the Corporate Director (Operations, Homes and Communities), with the Chair and Vice Chair, to procure all necessary contracts. Report 1.2, P28
The Committee noted the update on the Play Streets motion raised at Full Council on 25 November 2025, including planned officer actions to raise awareness and support events. Report 1.3, P47, P49
Why
The Worcester Play Plan was approved in July 2023 as a ten year commitment to invest in outdoor play spaces, mapping gaps and identifying priority locations across the city. Report 2.1, 2.2
The £400k of CIL funding has now been fully spent on a Project Support Officer and the Gheluvelt Park Splash Pad, so 2026/27 projects can only be funded from existing s106 developer contributions. Report 2.5, 2.7, P52
The play maintenance reserve is expected to be fully utilised by the end of 2026/27, after which further projects will rely on s106, Government grants or third party funding. Report 4.11, P52, P54
What happens next
Public consultation in January 2026 and procurement in February 2026 for Horizon Hub, Ronkswood Hub and Medway Road play areas, with contractors starting in April and aiming for completion by mid to late July 2026. Report 5.3, 5.9, 5.13, 5.14
St Peters Power Park to go through consultation in May or June 2026, procurement in July, works starting in September 2026, and a proposal taken to the s106 Programme Board during 2026. Report 5.17, 5.18
Officers will progress the Play Streets actions from the November 2025 motion, including social media promotion, website updates, supporting Play Worcester, and reviewing signage that discourages play. Report 6.1, P49
The money
£1,063,536 Total previously approved funding for priority play projects Report 2.3
£663,536 From s106 developer contributions within the total Report 2.3
£400k Allocated from the Community Infrastructure Levy, now fully spent Report 2.3, P52
£100,000 Budget for Horizon Hub Play Area from the s198 agreement Report 5.4
£131,000 Budget for Ronkswood Hub Play Area from the s198 agreement Report 5.10
£100,000 Budget for Medway Road Play Area from the s198 agreement Report 5.14
£307,000 Budget for St Peters Power Park from the s214 agreement Report 5.18
£60,000 Total cost of the 2025/26 Safety Surfacing Repair Programme from the play maintenance reserve Report 4.3
£70k Anticipated remaining balance of the play maintenance reserve at end of 2026/27 Report 4.11
£100,000 Annual play maintenance revenue budget for ongoing maintenance Report P52
Options considered
Chosen: Approve the report, note 2025/26 progress, endorse 2026/27 priorities and delegate procurement. Recommended by officers to progress the ten year Worcester Play Plan commitment Report P1, 1.1, 1.2
Chosen: Note the Play Streets motion update and the planned officer actions. Required by the Full Council motion of 25 November 2025 Report 1.3, P47
Implications
Financial: The £400k CIL allocation and the play maintenance reserve are now fully spent, so future projects depend on s106, Government grants or third party funding. Report 2.7, 4.11, P52, P54
Financial: Each s106-funded project must go to the s106 Programme Board for approval before a final committee decision, and only the St Peters Power Park proposal is still to be submitted. Report 5.15, 5.18, P56
Equalities: The Council's Equality, Diversity and Inclusion strategy will shape design and consultation, with facilities intended to allow children of different abilities to play together. Report P60
Staffing: Sufficient staffing resource, including a fixed term Project Support Officer, is in place to deliver the priority projects within the stated timescales. Report 2.5, P62
Climate: Environmental sustainability is a key tender criterion for each 2026/27 project and shaped site selection, with surveys to be carried out as needed. Report P66, P67
Other: The projects support the City Plan 2025 to 2030 themes of Strong and Engaged Communities and a Healthy and Active City. Report P59
Risk: Officers state there are no risk implications in respect of this report. Report P57
Who and where
Children and young people across all Worcester wards using the play areas Report P68
Users of Horizon Hub, Ronkswood Hub, Medway Road and St Peters Power Park, including the on-site nursery at Medway Road
Play Worcester and partner groups such as Action for Children, the Starting Well Partnership and SENDIASS, to be consulted on designs Report 5.20
Residents in Arboretum ward and elsewhere, in relation to the Play Streets signage review Report P49
Timeline
24 July 2023: Place and Economic Development Committee approved the Worcester Play Plan Report 2.1
November 2024: Contractor appointed for Perdiswell Pump Track Report 3.2
End of January 2026: Waverley Street Play Area safety surfacing project due for completion Report 4.8
January 2026: Public consultation on Horizon Hub, Ronkswood Hub and Medway Road projects Report 5.3, 5.9, 5.13
5 January 2026: Works commenced on the Perdiswell Pump Track, with an eleven week build Report 3.2, 3.3
Easter school holidays 2026: Targeted official opening of the Perdiswell Pump Track Report 3.3
February 2026: Procurement for Horizon Hub, Ronkswood Hub and Medway Road projects Report 5.3, 5.9, 5.13
March 2026: Fort Royal Park equipment refurbishment due to be completed
April 2026: Contractors due to start on Horizon Hub, Ronkswood Hub and Medway Road Report 5.3, 5.9, 5.13
May or June 2026: Public consultation planned for St Peters Power Park Report 5.17
Mid-July 2026: Targeted completion of Ronkswood Hub works before the school summer holidays Report 5.9
20 July 2026: Targeted completion of Horizon Hub and Medway Road works before the school summer holidays Report 5.3, 5.13
September 2026: St Peters Power Park works due to start, with completion targeted for March 2027 Report 5.17
Plain English for the jargon
s106: Section 106 developer contributions, paid by developers towards local infrastructure
CIL: Community Infrastructure Levy, a charge on new development used to fund local infrastructure
s198 and s214 agreements: Specific legal agreements attached to s106 funding pots, used to fund Horizon Hub, Ronkswood Hub, Medway Road and St Peters Power Park
MUGA: Multi Use Games Area, a surfaced outdoor space for sport and games
SENDIASS: Special Educational Needs and Disability Information, Advice and Support Service
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item35
Resolved
That the Committee note: 1. the contents of the report, and particularly the progress made during 2025/26 in the delivery of the Worcester Play Plan; 2. the priority projects for delivery during 2026/27, and delegates authority to the Corporate Director - Operations, Homes and Communities, in consultation with the Chair and Vice Chair of the Committee, to procure all necessary contracts and services to progress delivery; and 3. the update on the motion raised at Full Council on the 25th of November 2025, regarding the promotion of the ... view the full minutes text for item 35.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
Report to Place and Economic Development Committee, 7 pages
Recommendation
That the Committee:
1.1Notes the contents of the report, and particularly the progress made during 2025/26 in the delivery of the Worcester Play Plan;
1.2Notes the priority projects for delivery during 2026/27, and delegates authority to the Corporate Director (Operations, Homes & Communities) in consultation with the Chair and Vice Chair of this Committee, to procure all necessary contracts and services to progress delivery; and
1.3Notes the update on the motion raised at Full Council on the 25th of November 2025, regarding the promotion of the ‘Play Streets’ campaign.
Background
2.1At the Place and Economic Development Committee meeting on the 24th of July 2023, members approved the Worcester Play Plan. The Plan sets out an ambitious commitment to invest in outdoor spaces for children and young people over a ten- year period.
2.2The plan maps the gaps in provision across the city and identifies locations and needs for priority investment. It recognises that local level public consultation and community engagement with users of play facilities, as well as residents and other stakeholders, is a vital component in informing the design and feasibility stage of individual projects.
2.3Funding of up to £1,063,536 was previously approved by this committee for delivery of priority play projects, consisting of £663,536 from s106 developer contributions and £400k allocated from the Community Infrastructure Levy.
2.4It’s important to note that within the above s106 agreements, the criteria permit use of the funding for other purposes such as for the provision or enhancement of civic space or allotments in the vicinity of the development.
2.5In July 2024 this committee approved the allocation of £106k of CIL funding towards the appointment of a Project Support Officer on a fixed term contract (1st April 2025 to 30th September 2027) to facilitate the delivery of the priority projects identified within the Worcester Play Plan, in support of the Lead Commissioner for Leisure, Play, Health & Wellbeing. 2.6 In November 2024 the balance of £294k of CIL funding was allocated to the refurbishment of the Splash Pad in Gheluvelt Park. The full project costs were also covered through use of two s106 allocations totalling £72k.
2.7Therefore, given that the full CIL allocation has been utilised, priority play projects for 2026/27 can only be funded from existing s106 developer contributions.
3. Update on the delivery of Priority Projects for 2025/26
Perdiswell Pump Track 3.1 Following the opening of Worcester’s first Pump Track in Battenhall Park in November 2024, Environment Committee (June 2025) approved development of a ‘destination’ pump track at Perdiswell Park following a range of positive feedback from local public consultation.
3.2Significant interest was shown in the opportunity and following a competitive procurement process a contractor was appointed in November 2025, with works commencing on 5th January 2026.
3.3The installation is scheduled to take eleven weeks to complete (subject to delays caused by adverse weather conditions) allowing for the official opening to take place in time for the easter school holidays.
3.4A community engagement event was held at Perdiswell Leisure Centre on Wednesday 17th December 2025 to present the proposed designs, as well as the designs being advertised via traditional and social media.
3.5Having considered feedback provided by parents and children who use the track at Battenhall Park, the Perdiswell Park pump track will provide a fully inclusive beginners track for users up to the age of 8 years, as well as a separate larger intermediate/advanced track.
4. Update on other play projects delivered during 2025/26
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Place and Economic Development Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.