RESOLVED – ( i ) That funding from the Capital Reserve in 2015/16 be allocated as follows: · £600,000 for re-roofing works at Redwither Tower; · £500,000 to Carriageway Surface Improvements; and · £100,000 to Upgrade Town Centre Conveniences (ii) That the rolling programme for 2014/15 to 2018/19, as detailed in appendices 2 and 3 of report HF/03/15 be approved. (iii) That the capital programme be reviewed in July 2015. (iv) That the Treasury Management Activity and Prudential Indicators, as detailed in Appendix 4 of report HF/03/15 be noted. (v) That the reviews Treasury Management Practices, as detailed in Appendix 5 of report HF/03/15 be approved. Reasons for decisions ( i ) This report follows an earlier monitoring report in October in compliance with Financial Regulation 2.4 that requires that the Head of Finance monitors and reports to Members on the Capital Programme. (ii) Local Authorities are required under the Local Government Act 2003 to comply with the CIPFA Prudential Code for Capital Finance. The indicators presented in Appendix 4 fulfil the requirements of the Code. (iii) To comply with the CIPFA Code of Practice on Treasury Management and the Council’s Treasury Management Policy.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
To review the 2014/15 - 2018/19 non Housing Revenue Account Capital Programme and the Treasury Management Activity including Prudential Indicators and revised Treasury Management Practices.
Executive summary
2.1The total capital expenditure in 2014/15 is estimated to be £19,006k. This is £8,232k less than the total approved by the Executive Board at its meeting on 21 October 2014 (HF/52/14). The main reasons for the net decrease are:
• Slippage of spend on projects from 2014/15 to 2015/16 of £8,727k. • A net increase in estimated spend of £495k
2.2The Capital Programme is fully funded by borrowing supported by the Welsh Government, grants and contributions, capital receipts and prudential borrowing.
2.3The Welsh Government General Capital Funding for 2015/16 has been increased by £76k compared to the indicative allocation given in 2014/15.
2.4On 10 June 2014 the Executive Board (HF/28/14) approved the transfer of £1,214k to a capital reserve to fund new capital schemes. 3 RECOMMENDATIONS
3.1Allocate the Capital Reserve to fund; £600k for Re-roofing works at Redwither Tower, £500k to Carriageway Surface Improvements and £100k to Upgrade Town Centre Conveniences, in 2015/16.
3.2The rolling programme for 2014/15 to 2018/19 as detailed in appendices 2 and 3 is approved.
3.3The capital programme is next reviewed and reported to the Executive Board in July 2015.
3.4The Treasury Management Activity and Prudential Indicators in Appendix 4 are noted.
3.5The revised Treasury Management Practices in Appendix 5 are approved.
Reasons for recommendations
(i) This report follows an earlier monitoring report in October in compliance with Financial Regulation 2.4 that requires that the Head of Finance monitors and reports to Members on the Capital Programme.
(ii) Local Authorities are required under the Local Government Act 2003 to comply with the CIPFA Prudential Code for Capital Finance. The indicators presented in Appendix 4 fulfil the requirements of the Code.
(iii) To comply with the CIPFA Code of Practice on Treasury Management and the Council’s Treasury Management policy.
4. BACKGROUND INFORMATION
Capital Programme 2014/2015
4.1The Executive Board approved the last revision of the capital programme 2014/15 to 2018/19 on 21 October 2014 (HF/52/14). Appendix 1 provides a summary of expenditure by service, the financing of that expenditure and the variance between the revised programme and the previously approved position.
4.2The revised estimate of expenditure on all capital schemes is £19,006k, a net decrease of £8,232k compared with the projected expenditure reported to the Executive Board in October. The significant changes are as follows:-
Slippage of Expenditure to 2015/16
4.3Changes to the phasing of expenditure have resulted in £8,727k of spending originally planned in 2014/15 to be rescheduled to 2015/16. Projects where significant slippage has occurred are set out below: • Western Gateway (-£499k). The main contract tenders were received on 23 January with the contractor being appointed and work commencing March/April 2015. The project is due for completion by October 2015.
• Land based Solar Photovoltaic Project (-£2,309k). The proposed point of connection for the Solar Farm is located within an adjacent field. The scheme was delayed due to negotiations between the landowner and Scottish Power to provide legal access to the land. Installation is now ongoing with an expected completion date of May 2015.
• Redwither Biomass Boiler (-£575k). Due to new figures for Redwither gas consumption being received; all calculations were revised resulting in delays issuing tender documents. The Invitation to Tender documents to contractors were sent out in January with a return date of 2 March 2015.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.