RESOLVED - ( i ) That £2m of the Capital Reserve be allocated to fund highways works, £150k towards cashless solution in schools and £100k for the purchase and installation of new car park machines. To allocate £20k for replacing gateway road signage to include reference to the canal world heritage site. (ii) That the allocation of £300k to Disabled Facilities Grants in 2017/18 as outlined in paragraph 2.5 of report HF/54/16 be approved. (iii) That the capital outturn for 2015/16 be noted. (iv) That the rolling programme for 2016/17 to 2019/20, as detailed in appendices 2 and 3 to report HF/54/16 be approved. (v) That the capital programme be reviewed and reported to the Executive Board in October 2016. Reasons for decisions (i) This report follows an earlier monitoring report in February in compliance with Financial Regulation 3.12 that requires that the Head of Finance monitors and reports to Members on the Capital Programme. (ii) Local Authorities are required under the Local Government Act 2003 to comply with the CIPFA Prudential Code for Capital Finance. The indicators presented in Appendix 4 fulfil the requirements of the Code.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
To advise Members of the 2015/16 non HRA Capital Programme out turn (the figures are subject to audit) and to review the 2016/17 - 2019/20 Capital Programme.
Executive summary
2.1The total capital expenditure in 2015/16 was £22,923k. This is £3,814k less than the total approved by the Executive Board at its meeting on 9 February 2016 (HF/09/16). The main reasons for the net decrease are:
Slippage of spend on projects from 2015/16 to 2016/17 of £4,189k A net increase in spend of £375k.
2.2The Capital Programme is fully funded by borrowing supported by the Welsh Government, grants and contributions, capital receipts and prudential borrowing and interest free loans from Welsh government and Salix.
2.3The Welsh Government General Capital Funding for 2016/17 is £5,661k, an increase of £27k from the 2015/16 allocation.
2.4On 10 May 2016 the Executive Board (HF/24/16) approved the transfer of £2,885k to the capital reserve to fund highways infrastructure and other projects. 2.5 Executive Board (HF/48/13) on 8 October 2013 recommended the need to identify an additional £300k in 2017/18 for Disabled Facilities Grants. It is proposed to increase the allocation for Disabled Facilities Grants in 2017/18 to £1.3m with the additional £300k being funded from previously unallocated Welsh Government General Capital Funding in 2015/16 (£76k) and 2016/17 (£214k) with the balance (£10k) funded from capital receipts.
Recommendations
3.1Allocate £2m of the Capital Reserve to fund highways works, £150k towards cashless solution in schools and £100k for the purchase and installation of new car park machines. To allocate £20k for replacing gateway road signage to include reference to the canal world heritage site.
3.2The allocation of £300k to Disabled Facilities Grants in 2017/18 as outlined is paragraph 2.5 is approved.
3.3The capital outturn for 2015/16 is noted.
3.4The rolling programme for 2016/17 to 2019/20 as detailed in appendices 2 and 3 is approved.
3.5The capital programme is next reviewed and reported to the Executive Board in October 2016.
Reasons for recommendations
(i) This report follows an earlier monitoring report in February in compliance with Financial Regulation 3.12 that requires that the Head of Finance monitors and reports to Members on the Capital Programme.
(ii) Local Authorities are required under the Local Government Act 2003 to comply with the CIPFA Prudential Code for Capital Finance. The indicators presented in Appendix 4 fulfil the requirements of the Code.
4. BACKGROUND INFORMATION
Capital Programme 2015/16
4.1The Executive Board approved the last revision of the capital programme 2015/16 to 2019/20 on 9 February 2016 (HF/09/16). Appendix 1 provides a summary of expenditure by service, the financing of that expenditure and the variance between the actual programme and the previously approved position.
4.2The actual expenditure on all capital schemes is £22,923k, a net decrease of £3,814k compared with the projected expenditure reported to the Executive Board in February. The significant changes are as follows;- Slippage of Expenditure to 2016/17
4.3Changes to the phasing of expenditure have resulted in £4,189k of spending originally planned in 2015/16 to be rescheduled to 2016/17. Projects where significant slippage has occurred are set out below:
ICT Infrastructure (-£140k). Due to delays in procuring the contract for the Storage Area Network system.
Land Base Solar Project (-£2,429k). Although the project is complete the payment to British Gas has been delayed until a completion certificate has been received.
ECO Arbed Projects (-£252k). Work didn’t commence until January 2016, resulting in some of the work on projects being not being completed until April. All work on the scheme has now been completed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.