RESOLVED – ( i ) That the allocation of Welsh Government General Capital Funding in 2019/20, recommended by the Corporate Land and Buildings Strategy Group, as detailed in paragraph 4.21 of report HF/09/16 be approved. (ii) That the allocation of the Heritage and Community Well Being annual capital provision, as detailed in paragraph 4.23 of report HF/09/16 be approved. (iii) That the rolling programme for 2015/16 to 2019/20, as detailed in Appendices 2 and 3 of report HF/09/16 be approved. (iv) That the capital programme be reviewed and reported to the Executive Board in July 2016. (v) That the Treasury Management Activity and Prudential Indicators in Appendix 4 of report HF/09/16 be noted. Reasons for decisions ( i ) This report follows an earlier monitoring report in October in compliance with Financial Regulation 2.4 that requires that the Head of Finance monitors and reports to Members on the Capital Programme. (ii) Local Authorities are required under the Local Government Act 2003 to comply with the CIPFA Prudential Code for Capital Finance. The indicators presented in Appendix 4 fulfil the requirements of the Code.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
To review the 2015/16 - 2019/20 non Housing Revenue Account Capital Programme and Treasury Management Activity including Prudential Indicators.
Executive summary
2.1The total capital expenditure in 2015/16 is estimated to be £26,737k. This is £1,916k less than the total approved by the Executive Board at its meeting on 13 October 2015 (HF/53/15). The main reasons for the net decrease are:
A net increase in estimated spend of £1,994k. Slippage of spend on projects from 2015/16 to 2016/17 of £3,910k.
2.2The Capital Programme is fully funded by borrowing supported by the Welsh Government, grants and contributions, capital receipts and prudential borrowing.
2.3The Joint Member/Officer Corporate Land and Buildings Strategy Group has recommended projects to be allocated Welsh Government General Capital Funding in 2019/20. 3 RECOMMENDATIONS
3.1The allocation of Welsh Government General Capital Funding in 2019/20 recommended by the Corporate Land and Buildings Strategy Group shown in paragraph 4.21 is approved.
3.2The allocation of the Heritage and Community Well Being annual capital provision shown in paragraph 4.23 is approved.
3.3The rolling programme for 2015/16 to 2019/20 as detailed in appendices 2 and 3 is approved.
3.4The capital programme is next reviewed and reported to the Executive Board in July 2016.
3.5The Treasury Management Activity and Prudential Indicators in Appendix 4 are noted.
Reasons for recommendations
(i) This report follows an earlier monitoring report in October in compliance with Financial Regulation 2.4 that requires that the Head of Finance monitors and reports to Members on the Capital Programme.
(ii) Local Authorities are required under the Local Government Act 2003 to comply with the CIPFA Prudential Code for Capital Finance. The indicators presented in Appendix 4 fulfil the requirements of the Code.
4. BACKGROUND INFORMATION
Capital Programme 2015/16
4.1The Executive Board approved the last revision of the capital programme 2015/16 to 2018/19 on 13 October 2015 (HF/53/15). Appendix 1 provides a summary of expenditure by service, the financing of that expenditure and the variance between the revised programme and the previously approved position.
4.2The revised estimate of expenditure on all capital schemes is £26,737k, a net decrease of £1,916k compared with the projected expenditure reported to the Executive Board in October. The significant changes are as follows;-
Slippage of Expenditure to 2016/17 4.3 Changes to the phasing of expenditure have resulted in £3,910k of spending originally planned in 2015/16 to be rescheduled to 2016/17. Projects where significant slippage has occurred are set out below: Substance Misuse Action Fund (SMAF) Refurbishment Multi Agency Base (-£165k). Delays by Betsi Cadwaladr University Health Board in issuing the tender and also a longer period of negotiation with the appointed contractors.
Cefn Mawr Townscape Heritage phase 2 (-£300k). Delays in the legal transfer of Plas Kynaston Hall, and also the removal of a contractor on two schemes due to health and safety issues.
Reroofing Works Redwither Tower (-£600k). The work is to be procured by the end of March with work scheduled to take place in the summer.
Upgrade Town Centre Conveniences (-£100k). Delays due to the requirement of Listed Building Consent being obtained, which has now been forwarded to Welsh Government for determination.
21st Century Schools (-£1,620k). Issues with drainage at Hafod Y Wern resulted in a delay in planning approval being granted. Approval was granted November 2015 with work starting on site in January 2016.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.