Customers, Performance, Resources and Governance Scrutiny Committee agreed this item on Wednesday 27 April 2016. Below is the council's own wording, with the papers it was decided on.

Item77

Resolved

AGREED – ( i ) That implications of reporting of overspends to those contracts exceeding the agreed contract sum by more than 5% be established. (ii) That consideration be given as to how to bring contracts that are of concern to the attention of this Committee, as soon as possible. (iii) That the report be noted.
Word for word from the decision Wrexham published for this meeting. Source: moderngov.wrexham.gov.uk

Follow this further

Built from Wrexham's papers

What the report saysPro

Report to Customers, Performance, Resources and Governance Scrutiny Committee

Purpose of the report

To advise Members of a contract which has exceeded the agreed contract sum by more than 10%, subject to a minimum over-spend of £10,000, in accordance with Scrutiny Committee’s previous decisions.

Executive summary

2.1Financial Regulation 10.103 previously required:

“In any case where the total cost of any work carried out under a contract, including term contracts, exceeds by more than 10% the approved contract sum, subject to a minimum variation of £10,000, a report of such cost including the reasons for the variation, shall, after agreement of the final account, be submitted to the Customers, Performance & Resources Scrutiny Committee.”

2.2The Customers, Performance and Resources Scrutiny Committee also recommended:

a) That all contracts which meet the 10% or £10,000 criteria are reported every six months in a single composite report, but that any contracts where the excess sum is a minimum of 20% of the agreed contract sum subject to a minimum value of £30,000 be reported to the next available meeting of this Committee.

b) That this report also includes details of the monitoring arrangements which are in place and any areas of non-compliance with the reporting of variations to contracts which were identified through random sample checks. c) That, initially, the relevant Head of Department be required to authorise an overspend on the original contract sum, prior to any additional works being carried out.

2.3This report will enable Members to consider a contract (Appendix 1) where there was expenditure in excess of 10% of the agreed contract sum and request explanations why the overspend occurred.

2.4The contract completion date was 21 December 2012 and this pre-dated the requirement for any contract overspends to be formally approved in advance by the Head of Department. The Housing Department were notified of the overspend through a report to their budget/contract monitoring meeting.

2.5The final account was agreed early in 2016 and the protracted length of time between project completion and the agreement of the final account was due to the contractor’s failure to supply an accurate final account in a timely manner, and was exacerbated by the constant staff turnover of staff in the company. Whilst the actual work executed on site was good the process of agreeing a final account has been very difficult and time consuming.

2.6Final accounts should always be agreed as soon as possible after the contract completion date.

Recommendation

3.1That Members consider the report and comment on the issues identified in respect of this contract.

Reason for recommendation

To enable Members to challenge the reasons for expenditure in excess of 10% of the agreed contract sums subject to a minimum variation of £10,000.

4. BACKGROUND INFORMATION

4.1Contract Procedure Rules (CPR) set out the requirements for obtaining tenders for goods, works and services. Competitive tenders should be obtained unless there is an agreed reason for an exemption. This helps to ensure that value for money is obtained from the contract process.

4.2CPR 12.10 requires that “Each Head of Department is responsible for ensuring that contracts are effectively monitored and contract managed throughout the period of the contract. Evidence of this must be provided to the Head of Finance on request.”

4.3This responsibility falls upon the Client Head of Department and not the Head of Assets and Economic Development acting as agent or contract manager on their behalf although there is a need for effective and timely communication between the two parties.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Contract Which Has Exceeded the Agreed Contract Sum by More Than 10%Report 140 KB DownloadRead as text

At this meeting

Whole meeting
75Confirmation of MinutesAgreed 76Work ProgrammeAgreed
77Contract Which Has Exceeded the Agreed Contract Sum by More Than 10%This decision
78Draft Information Management Strategy 2016-2019Agreed

Who was there

11 of 14 attended
PB
Councillor Paul BlackwellCommittee Member, present
MD
Councillor Mrs Dana DaviesCommittee Member, present
RJ
Councillor R J Dutton OBEGuest, in attendance
ME
Councillor Mike EdwardsCommittee Member, present
DJ
Councillor D J GriffithsCommittee Member, present
PJ
Councillor P JeffaresCommittee Member, present
OA
Councillor O Arfon JonesCommittee Member, apologies
BM
Councillor Bernie McCannCommittee Member, present
MG
Councillor M G MorrisCommittee Member, present
PH
Councillor Paul H PembertonCommittee Member, present
CP
Councillor Colin PowellVice-Chair, present
JP
Councillor John PritchardCommittee Member, present

All 14 on the meeting page

On this subject at Wrexham

Search all
  1. Contract Which Has Exceeded the Agreed Contract Sum by More Than 10%This decision
  2. Contracts which have exceeded the Agreed Contract Sum by more than 5%Decided
  3. Contracts which have Exceeded the Agreed Contract Sum by more than 5%Agreed
  4. Contracts Which Have Exceeded the Agreed Contract Sum by More than 10%Agreed

More from Wrexham Customers, Performance, Resources and Governance Scrutiny Committee

All decisions
MeetingDecisionOutcome
3 Sep 2026 Confirmation of MinutesAGREED – That the Minutes of the Meetings held on 5 and 25 June 2026 be confirmed and signed as a correct record. Agreed Open
3 Sep 2026 Work ProgrammeAGREED – That the work programme be agreed subject to the aforementioned amendmens. Agreed Open
3 Sep 2026 ICT and Digital Strategy 2024-2027AGREED – That the Committee i. Congratulate everyone involved in achieving the national Granicus award in respect of ... Agreed Open
25 Jun 2026 Confirmation of MinutesAGREED – That the minutes of the meeting held on 14 May 2026 be confirmed and signed as a correct record. Agreed Open
25 Jun 2026 Work ProgrammeAGREED – That the work programme be agreed subject to the above amendments. Agreed Open