RESOLVED – (i) That the 2023/24 Q1 budgetary forecast position for the year be noted. (ii) That in light of the pressures forecast, immediate actions are taken to mitigate the budget forecast. Where delegation sits with Chief Officers, actions to bring the budget back in line with the approved budget will be implemented by Chief Officers, in consultation and agreement with the appropriate Lead Member and the Leader and the Deputy Leader of the Council. (iii) That the increase in charges for green waste collection to £35 from 1st August 2023 be approved. (iv) That a review of car parking charges and sickness absence management policies be approved. (v) That that formal notice be given for the cancellation of the PCSO contract provision. (vi) That the corporate budget mitigation measures attached as Appendix 5 to report COFI/14/23 be noted. (vii) That these matters be dealt with as urgent items of business in accordance with Section 5 (Rule 5.8.10(m)) of the Council’s Constitution due to the necessity to take action urgently to address the budget position. Reasons for decisions To ensure robust budget monitoring arrangements for the financial year and that action is taken to address the budget pressures forecast.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
To inform Members of the Council’s 2023/24 current budgetary position for the first quarter of the 2023/24 financial year, including the Housing Revenue Account (HRA).
Executive summary
2.1The Council’s net revenue budget for 2023/24 is £303,116,859. The net revenue budget of £302,901,187 was agreed by Council on 15 February 2023 (COFI/08/23), however following the Local Government Final Settlement, additional funding of £215,672 was received relating to the transfer of funding for the increased employer costs related to the Fire and Rescue Authority (FRA) pensions from a grant to the FRAs into the final local government settlement.
2.2This Revenue Budget Update report is the first quarterly report for the financial year 2023/24. The report forecasts the year-end position as underpinned by assumptions and estimates and taking account of actual expenditure to the end of May.
2.3Last year’s final outturn position reported a significant increase in financial pressure across statutory and demand-led services, in particular social care, school transport and Streetscene costs. Given the nature of the pressures last year, it was inevitable that this would have an impact in the current financial year and work has started immediately to address the situation. Without intervention, the current budgetary position is a gross projected pressure of £23.8m and this is summarised in Appendix 1. The ongoing impact of pay inflation and service demands continue to seriously impact the Council’s financial position. The net projected position assumes that the 2023/24 pay award is in line with the latest pay offer. The estimated impact of this is an additional cost of £4m over and above the cash limited budget allocated. The pay award has not yet been agreed and if the outcome is different from these assumptions, the forecast position will change across all services and schools.
2.4Identifying and reporting the forecast pressure early in the year allows time to adjust spending assumptions in order to bring the budget back into a balanced position. To reduce this forecast position budget mitigation measures are being identified within Social Care and the Environment and Technical departments, aiming to control pressures and supress the level of overspend. In addition to this, Council services are reviewing all spending commitments and income to identify in- year savings to a general target level of 15%. A template will be completed and agreed with Chief Officers, the Lead Member and the Leader and Deputy Leader of the Council to record all items approved. As part of identifying options, Council services will consider all areas of expenditure and income and will continue to ensure value for money is delivered in all major spending areas. A list of corporate budget mitigation measures is listed as Appendix 5 to support this. Corporate and Central expenditure will continue to be reviewed and forecasts adjusted to support the wider position.
2.5This report focuses on the latest forecast position and gives an early, detailed explanation of the scale of financial pressures. Further reports will be provided updating on the position and any policy based decisions requiring approval will be considered by the Executive Board. However, the timing of some measures and the impact in the current year means that a decision is required now on the following items:
2.5.1 Increase of charges for the collection of green waste to £35 per annum
2.5.2 Review of car parking charges
2.5.3 To give formal notice of the cancellation of the current PCSO contract provision funded by the Council
2.6Appendix 2 provides more detail on the forecast position by service with supporting narrative explaining variances.
2.7Appendix 3 details the projected outturn position for the HRA.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.