RESOLVED - ( i ) That the capital outturn for 2022/23 be noted. (ii) The quarter 1 rolling programme for 2023/24 to 2024/25 as detailed in appendices 2 and 3 to report COFI/15/23 be approved. Reason for decisions This report follows an earlier monitoring report in February in compliance with Financial Regulation 3.13 that requires that the Chief Officer Finance & ICT monitors and reports to Members on the Capital Programme.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
To advise Members of the 2022/23 Capital Programme outturn and to review the 2023/24 – 2024/25 Capital programme position as at the end of quarter 1 2023/24.
Executive summary
2.1The total capital expenditure in 2022/23 including the Housing Revenue Account (HRA) was £77,934k. This is £13,182k less than the total approved by the Executive Board at its meeting on 7 February 2023 (COFI/07/23). The reasons for the net decrease are:
A net decrease in spend of £12,969k on non HRA projects including rephasing of spend to future years. A net decrease in spend in the HRA capital programme of £213k.
2.2The Capital Programme is fully funded by borrowing supported by the Welsh Government, grants and contributions, capital receipts, prudential borrowing and interest free loans from Salix.
2.3Following the announcement of the final local government settlement on 28 February 2023 the Welsh Government General Capital Funding for 2023/24 is £7,046k an increase of £1,166k from the 2022/23 allocation. Indicative figures suggest a similar level of General Capital Funding will be received in 2024/25.
2.4On 15 February 2023 Council (COFI/08/23) approved the revenue budget for 2023/24. As part of the budget it was agreed that an additional annual capital provision of £700k is to be included in the Highways Structural Maintenance Capital Programme from 2023/24 onwards. 2.5 The Executive Board (COFI/13/23) on 13 June 2023 were informed of the revenue outturn for 2022/23 and the resulting position with regards to reserves, and this position is reflected in the current programme reported.
Recommendations
3.1The capital outturn for 2022/23 is noted.
3.2The quarter 1 rolling programme for 2023/24 to 2024/25 as detailed in appendices 2 and 3 is approved.
Reasons for recommendations
(i) This report follows an earlier monitoring report in February in compliance with Financial Regulation 3.13 that requires that the Chief Officer Finance & ICT monitors and reports to Members on the Capital Programme.
4. BACKGROUND INFORMATION
Capital Programme 2022/23
4.1The Executive Board approved the last revision of the capital programme 2022/23 to 2024/25 on 7 February 2023 (COFI/07/23). Appendix 1 provides a summary of expenditure by service, the financing of that expenditure and the variance between the actual programme and the previously approved position.
4.2The actual expenditure on all capital schemes was £77,934k, a net decrease of £13,182k compared with the projected expenditure reported to the Executive Board in February 2023. The significant changes are as follows;-
Rephasing of Schemes to 2023/24
4.3Changes to the phasing of expenditure have resulted in £10,900k of spending originally planned in 2022/23 to be rescheduled to 2023/24. Projects where significant slippage has occurred are set out below:
ICT Infrastructure/Modernisation (-£440k). High demand for computer hardware post Covid has resulted in delays up to six months delivery time.
Leisure Centre Solar PV Installations (-£226k). Work is ongoing to install solar panels on three leisure centres in the Borough.
Pontcysyllte Aqueduct & WHS (-£2,313k). The scheme is currently being reprofiled with the UK Government.
Wrexham City Centre Conservation Area and Markets (-£1,085k). Delays due to supply market (see paragraph 4.16).
Wrexham Gateway (-£1,627k). Updated delivery plan (see paragraph 4.17).
Crown Buildings/OAR (-£479k). Due to timing on invoices for furniture and equipment being paid early April 2023 and retentions due to be paid in 2023/24. Property Asset Improvements (-£446k). Works generated by the Schools Capital Maintenance Grant resulted in these schemes, which include a replacement roof at Wrexham Library, to be delayed until 2023/24.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.