AI summaryWrexham Planning Committee has granted permission for Kronospan's new northern access road, lorry park, weighbridges, 132kV substation and related works on land north of its Chirk site, subject to conditions and a Section 106 obligation.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSubject to conditions and a Section 106 agreement
MoneyNo specific sum stated in the papers
What happens nextComplete Section 106 agreementWithin six months of the committee resolution, or delegated refusal
Who it affectsKronospan Limited and Chirk residents
What was decided
Permission was granted, subject to a Section 106 obligation covering a final Conservation Management Plan, a final Woodland Management Plan and their long-term management, and to conditions. Report P9, P10, P11
Condition 1 was amended to require development to begin within three years of the permission, instead of the five years originally proposed. Report P147
A new Condition 29 was added requiring a scheme of noise mitigation to be approved and implemented within each phase before it is brought into use, to protect nearby residents.
Why
The application was re-assessed because the High Court quashed the Wrexham Local Development Plan on 12 June 2025 and the Welsh Government directed its withdrawal on 16 March 2026, so the 1996-2011 Unitary Development Plan is again the development plan. Report P30, P31
Officers considered the site, although outside the Chirk settlement limit and within Green Barrier and Special Landscape Area, was the only feasible location, and the development would remove most HGV traffic from Chirk town itself, supporting the existing major employer. Report P41, P43, P45, P47, P53
Statutory consultees including CADW, Natural Resources Wales, the Council's Highway Officer and the Public Protection Officer raised no objections, subject to the recommended conditions and the Section 106 obligation. Report P79, P92, P99, P114, P118
What happens next
A Section 106 agreement must be completed within six months of the committee resolution to secure the Conservation Management Plan and Woodland Management Plan; otherwise the Interim Chief Officer Economy and Planning has delegated authority to refuse. Report P11, P12, P13, P14, P29
A phasing plan has been submitted and several conditions (3, 4, 5, 13, 14, 15, 18, 20, 24 and 26) are now to be discharged on a phase-by-phase basis. Report P34
Options considered
Chosen: Grant planning permission subject to completion of a Section 106 obligation (Recommendation A). Officers concluded the development was acceptable and the obligation would secure heritage and woodland management measures Report P9, P10, P11
Chosen: If the Section 106 obligation is not completed within six months, delegate authority to refuse the application (Recommendation B). To ensure protection of the Outstanding Universal Value of the Pontcysyllte Aqueduct and Canal World Heritage Site Report P12, P13, P14
Implications
Legal: A Section 106 agreement is required under the Town and Country Planning Act 1990 to secure a Conservation Management Plan and a Woodland Management Plan, including long-term management. Report P9, P10, P99, P140, P143
Equalities: The site is in the buffer zone of the Pontcysyllte Aqueduct and Canal World Heritage Site and partly within the setting of the Clwydian Range and Dee Valley AONB; CADW and NRW raise no objections subject to conditions and the obligation. Report P98, P99, P68, P70
Environment and climate: The development would allow Kronospan to connect directly to the 132kV network, reducing reliance on on-site fossil fuel generation and the risk of failure of the local 33kV network supplying Chirk. Report P44
Environment and climate: 88 trees, six complete tree groups, two part groups, six complete hedges and six part hedgerows would be removed, with replacement native planting and net gain in woodland, hedgerow and specimen tree planting proposed. Report P122, P123, P127
Environment and climate: Officers concluded the development would not have a likely significant effect on the River Dee and Bala Lake Special Area of Conservation in relation to phosphorous, as no additional employees or foul discharges are proposed. Report P134
Risk: A new Condition 29 was added to require noise mitigation in each phase to protect occupiers of nearby properties on Holyhead Road, around 25 metres from the site. Report P76
Other: The existing access onto Holyhead Road would be retained for cars and emergencies; HGVs would use the new northern access, with a Traffic Regulation Order needed to reduce the B5070 speed limit from 50mph to 40mph. Report P91, P95
Who and where
Kronospan Limited, operator of the existing Chirk manufacturing facility, employing over 600 staff with an estimated 6,000 indirect jobs in associated supply chains Report P3, P43
Residents of Chirk, particularly those closest to the site on the opposite side of the B5070 Holyhead Road Report P76
Glandŵr Cymru, as the Woodland Management Plan covers works on its land along the Llangollen Canal cuttings Report P142, P143
Friends of Whitehurst Gardens, as the Conservation Management Plan includes a commuted sum towards restoration works at the Whitehurst Registered Historic Park and Garden Report P140
Timeline
8 April 2024: Planning Committee previously resolved to grant permission subject to completion of a Section 106 obligation Report P28
12 June 2025: High Court Order received by the Council quashing adoption of the Local Development Plan Report P30
16 March 2026: Welsh Government directed the Council to withdraw the Local Development Plan Report P30
11 May 2026: Planning Committee reconsidered the application and resolved to grant permission, as amended
Within six months of 11 May 2026: Section 106 obligation to be completed or delegated refusal to be issued Report P12
Plain English for the jargon
UDP: Wrexham Unitary Development Plan 1996-2011, returned to development plan status after the LDP was quashed
LDP: Wrexham Local Development Plan, quashed by the High Court in June 2025 and withdrawn in March 2026
Section 106 obligation: A legal agreement under Section 106 of the Town and Country Planning Act 1990 used to secure planning obligations
WHS: World Heritage Site, in this case the Pontcysyllte Aqueduct and Canal
AONB: Area of Outstanding Natural Beauty, in this case the Clwydian Range and Dee Valley AONB
SAC: Special Area of Conservation, a European protected ecological site
SuDS: Sustainable Drainage System, for managing surface water runoff
TAN: Technical Advice Note, Welsh Government planning guidance
PPW: Planning Policy Wales, the national land use planning policy document
NRW: Natural Resources Wales, the Welsh Government's environmental adviser
CADW: The Welsh Government's historic environment service
CEMP: Construction Environmental Management Plan
CTMP: Construction Traffic Management Plan
CMP: Conservation Management Plan
WMP: Woodland Management Plan
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item109
Resolved
RESOLVED - That permission be granted, subject to the following: Condition 01 amended as follows: The development hereby permitted shall be commenced before the expiry of three years from the date of this permission. Further added to require a scheme of noise mitigation: Condition 29 No phase shall be brought into beneficial use until a scheme of noise mitigation has been implemented within that phase in accordance with a scheme of details that shall first have been submitted to and approved in writing by the Local Planning Authority. The noise mitigation measures shall thereafter be retained in accordance with the approved details for the lifetime of the development. Reason To protect the amenities of the occupiers of nearby properties in accordance with policy GDP1 of the Wrexham Unitary Development Plan.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
Site Address KRONOSPAN LTD HOLYHEAD ROAD CHIRK WREXHAM LL14 5NT
Description of Development CREU FFORDD FYNEDIAD NEWYDD, PARC LORIS, PONT BWYSO AC ADEILAD, MAES PARCIO, BLOC CYFLEUSTRAU, ARDALOEDD STORIO COED CRWN, IS ORSAF 132 KV A GWAITH ATEGOL / CONSTRUCTION OF NEW ACCESS ROAD, LORRY PARK, WEIGHBRIDGE AND BUILDING, CAR PARK, FACILITIES BLOCK, ROUNDWOOD STORAGE AREAS ,132 KV SUBSTATION AND ANCILLARY WORKS
Ward Chirk South/De'r Waun
Community Chirk/Y Waun
Recommendation Recommendation A That planning permission is granted subject to the completion of a Planning Obligation under Section 106 of the Town and Country Planning Act 1990 to secure:
• The submission of a final Conservation Management Plan; • The implementation and long-term management of the measures contained within the final Conservation Management Plan; • The submission of a final Woodland Management Plan; and • The implementation and long-term management of the measures contained within the final Woodland Management Plan.
That the Interim Chief Officer Economy & Planning be given delegated authority to approve the final form and content of the Planning Obligation.
Recommendation B That if the Planning Obligation pursuant to Section 106 of the Town and Country Planning Act, 1990 is not completed within six months of the date of the Committee resolution, the Chief Officer Economy & Planning be given delegated authority to refuse the application for the following reason:
1. The application contains insufficient measures to protect the Outstanding Universal Value of the Pontcysyllte Aqueduct and Canal World Heritage Site Report of the Chief Officer Economy and Planning
from the adverse effects of the proposed development. The development therefore has the potential to cause a significant harmful impact upon the WHS’s Outstanding Universal Value, contrary to the requirements of policy EC11 of the Wrexham Unitary Development Plan and TAN 24.
Officer Report
Site Description The application site comprises an area of approximately 11.74 hectares of agricultural land to the north of the existing Kronospan facility. The B5070 public highway (Holyhead Road) abuts the application site’s eastern boundary, whilst the Shrewsbury – Wrexham railway line and the Llangollen Canal lie to the west of the site. The application site’s northern boundary is defined by the existing access road to Afon Bradley Farm, which is under the ownership of the Applicant.
Proposal The application, seeks full planning permission for the following:
• Construction of new northern access road, and new 4-arm roundabout access point, off the B5070 public highway; • Construction of a new lorry park to the east of the proposed northern access road, and to the west of the B5070 public highway. The lorry park would have parking spaces for up to 45 HGVs and is designed so that vehicles can enter and exit the spaces in a forward gear, without the need for reversing; Report of the Chief Officer Economy and Planning
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.