Wrexham County Borough Council
Planning Committee, Monday 6 July 2026 at 4.00pm

Application No: P/2026/0054 - Kronospan Limited, Holyhead Road, Chirk, Wrexham, LL14 5NT

Decided Planning 1 paper

AI summaryWrexham Planning Committee grants permission for Kronospan to install two 132kV underground circuits and fibre cables near Chirk, with conditions on construction traffic, environment and archaeology.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedPer officer recommendation, with conditions
MoneyNone statedCommunity benefit contribution requested but rejected
What happens nextConditions to dischargeDevelopment must begin within five years
Who it affectsChirk and Kronospan sitePublic highways, agricultural land, heritage sites

What was decided

Planning permission was granted in accordance with the officer recommendation, following consideration as a major application. Report P8, P13

The committee approved the cable route largely following existing highways, with two 132kV circuits, fibre cables and two cable sealing end platforms connecting to a proposed substation at the Kronospan site. Report P5, P11, P12

Why

The development would provide a significantly enhanced grid connection for Kronospan, reduce reliance on onsite fossil fuel generation and could deliver a 59% reduction in carbon emissions by 2030, without giving rise to visual, residential amenity, highway safety, ecological or historic environment concerns. Report P64, P109

The cables would be below ground for most of their length, following the route of existing roads, and the development is considered appropriate engineering operations within the Green Barrier, preserving its openness. Report P70, P80

Officers found the proposed development accords with relevant Unitary Development Plan policies and Planning Policy Wales after weighing consultation responses, including concerns from the local member and Chirk Town Council. Report P33, P34, P35, P100, P109

What happens next

Before development begins, the applicant must submit and obtain approval for a Construction Environment Management Plan, a Construction Traffic Management Plan, a highway dilapidation survey, a hedgerow planting scheme, geotechnical reporting on the A5 crossing with a contingency plan, and an archaeological written scheme of investigation. Report P111, P113, P115, P116, P117, P119, P120

The development must be commenced within five years of the permission date, and surface water must not connect to the public sewer. Report P112, P123

Within one month of completing the development, a further highway condition survey and any reinstatement scheme must be submitted. Report P117, P118

The money

  • 55% Share of total demand Kronospan is currently licensed to draw from the local grid Report P62
  • 59% reduction in carbon emissions by 2030 Potential carbon reduction if the new grid connection replaces onsite fossil fuel generation Report P64

Options considered

  • Chosen: Grant planning permission in accordance with the officer recommendation. Development accords with relevant UDP policies and PPW12; no overriding concerns on visual impact, amenity, highways, ecology or heritage subject to conditions Report P8, P109
  • Rejected: Refuse the application as submitted. The local member requested refusal, but officers concluded the scheme was acceptable with conditions and conditions were imposed to address concerns Report P34, P109
  • Rejected: Secure a community benefit contribution via planning obligation. The statutory tests in Welsh Office Circular 13/97 and the CIL Regulations 2010 are not met; the Town Council did not identify specific infrastructure lacking capacity Report P102, P103, P104, P105, P107, P108

Implications

  • Environment: A 59% reduction in carbon emissions by 2030 is forecast for Kronospan if it draws more from the grid rather than onsite fossil fuel generation, with further reductions as the grid decarbonises. Report P64
  • Risk: Part of the site lies within Flood Zone 3, but given the scale and nature of underground trenching, NRW and officers consider the development acceptable in flood risk terms. Report P41, P101
  • Legal: The grant is subject to nine planning conditions covering plan compliance, time limit, CEMP, hedgerow planting, CTMP, highway dilapidation, A5 geotechnical reporting and contingency, archaeological monitoring, and surface water drainage. Report P110, P111, P112, P113, P115, P116, P117, P119, P120, P123
  • Equalities: A public right of way (CHIRK No: 42) lies near the site; the Ramblers Association asked that it not be diverted or blocked during construction. Report P56
  • Other: Heritage assets affected include the World Heritage Site, the Grade II* Registered Park and Garden, the Grade II* listed Brynkinalt Hall, and the Grade II Telford Milestone; CADW, HENEB and the Conservation Officer raise no objections subject to conditions. Report P43, P44, P49, P91
  • Other: The site is within a Special Landscape Area, but officers and the Study underpinning the withdrawn LDP find the designation outdated for most of the area, with only a small area near the Dee and Ceiriog confluence of higher landscape value. Report P72, P75, P76

Who and where

  • Kronospan Limited, operator of the Chirk site, seeking the new grid connection Report P3, P63
  • Residents and road users in Chirk and surrounding rural areas, including farms, businesses and emergency services, during construction works on the B5070 and local roads Report P21, P23, P24, P25, P26
  • Chirk Town Council and the local member for Chirk South/De'r Waun, who raised concerns about disruption and highway safety Report P18, P21, P33
  • Users of the trunk road network, with the Welsh Government directing conditions to maintain safety and free flow on the A5 Report P36, P88, P119
  • Users of public right of way CHIRK No: 42 Report P56
  • Statutory consultees including NRW, CADW, HENEB, Welsh Water, Public Health Wales, Public Protection, Ecology, Arboricultural, Conservation and Highways officers Report P37, P38, P39, P40, P42, P43, P44, P45, P46, P47, P48, P51, P52, P53
  • Two objectors who wrote in about odour, dust, noise and highway impacts Report P59, P60

Timeline

  • Early 1970s onwards: Kronospan site has an extensive planning history Report P14
  • P/2022/1080 (pending Section 106 agreement): Application for new access roads, lorry park, weighbridge, buildings, car park, facilities block, roundwood storage areas, 132 KV substation and ancillary works Report P15
  • Within five years of the permission date: Development must be commenced Report P112
  • Within 3 months of commencement of development: Full details of proposed hedgerow planting to be submitted for written approval Report P115
  • Within one month of completion of the development: Further photographic highway condition survey and any reinstatement scheme to be submitted Report P117, P118

Plain English for the jargon

  • 132kV circuit: A high-voltage electricity line operating at 132,000 volts, in this case running underground along existing highways
  • Cable sealing end platform: An above-ground structure where an underground cable terminates and connects to an overhead line
  • CEMP: Construction Environment Management Plan, setting out how construction impacts on noise, dust, pollution and protected species will be controlled
  • CTMP: Construction Traffic Management Plan, setting out how construction vehicle movements, road closures and diversions will be managed
  • Green Barrier: A designation under the Wrexham UDP analogous to the Green Wedge in Planning Policy Wales, intended to prevent coalescence of settlements
  • Section 106 agreement: A planning obligation under Section 106 of the Town and Country Planning Act used to secure mitigation or contributions linked to a permission
  • Section 50 licence: A permit under the New Roads and Street Works Act 1991 required for works affecting a public highway
  • HDD: Horizontal Directional Drilling, a trenchless method used here to install cables beneath the A5 trunk road
  • SAC: Special Area of Conservation, a European-designated site, here the River Dee and Bala Lake SAC
  • SSSI: Site of Special Scientific Interest, here Chirk Castle and Parkland SSSI
  • SuDS: Sustainable Drainage Systems, required for surface water management and approved by a SuDS Approval Body under the Flood and Water Management Act 2010
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17

Resolved

RESOLVED - That permission be granted in accordance with the Officer recommendation.
Word for word from the decision Wrexham published for this meeting. Source: moderngov.wrexham.gov.uk

Follow this further

Built from Wrexham's papers

What the report saysPro

Report to Planning Committee

Report of the Chief Officer Economy and Planning

Application Reference P/2026/0054

Applicant [name removed] [name removed] Address KRONOSPAN LTD, HOLYHEAD ROAD, CHIRK, WREXHAM, LL14 5NT

Description of Development GOSOD DWY GYLCHED 132KV, DAU GEBL FFEIBR A DAU LWYFAN PEN SELIO CEBLAU

INSTALLATION OF TWO 132KV CIRCUITS, TWO FIBRE CABLES AND TWO CABLE SEALING END PLATFORMS

Ward Chirk South/De'r Waun

Community Chirk/Y Waun

Recommendation Grant

Officer Report

Site Description The application site comprises an area of approximately 11.34 hectares of both public highway verge and agricultural land mainly to the east of the existing Kronospan facility. The B5070 public highway (Holyhead Road) abuts the facility on the site’s eastern boundary, whilst the Shrewsbury – Wrexham railway line and the Llangollen Canal lie to the west of the site. Report of the Chief Officer Economy and Planning

Proposal The application seeking planning permission is for the installation of two 132kV circuits and two fibre cables between the existing Legacy to Oswestry 132kV overhead line and a [proposed 132kV substation at the Kronospan site. The development would follow the route of existing highways between the Kronspan site and the overhead line and comprise of: • Cable Route 1 (approximately 4.4km long) – the south and east of Chirk • Cable Route 2 (approximately 4.8km long) – to the south and east of Chirk, parallel with Cable Route 1 for most of its length. • Fibre Cable Route (approximately 3.3km long) – to the north and east of Chirk

Apart from where connections are to be made to the Legacy to Oswestry 132kV overhead line the cables would be installed in trenches that follow the route of existing highways.

Reason for Committee Determination Major application

Site History The Kronospan site has an extensive planning history extending back to the early 1970s. The most relevant site history is:

P/2022/1080 - Construction of new access roads, lorry park, weighbridge and building, car park, facilities block, roundwood storage areas, 132 KV substation and ancillary works - pending a Section 106 agreement. Report of the Chief Officer Economy and Planning

Development Plan Wrexham Unitary Development Plan Policy: GDP1 – Development Objectives. GDP2 – Capacity of Infrastructure and Community facilities EC2 – Agricultural land EC4 - Hedgerows, trees and woodland EC5 – Special landscape areas EC6 –Biodiversity Conservation EC9 – Listed buildings of special architectural or historic interest EC11 – Archaeology EC12 - Development and flood risk. T7 – Traffic Management Local Planning Guidance Notes:

Relevant National Policy Planning Policy Wales - edition 12 Future Wales plan (2040) Future Generations of Wales Act 2015 Technical Advice Note 5 – Nature Conservation and Planning Technical Advice Note 12 – Design Technical Advice Note 18 – Transport Technical Advice Note 23 – Economic Development

Consultation Responses Chirk Town Council: Initially objected, raising concerns about the length of time the project would take and the extent of groundworks and excavations affecting the main road through the town as well as roads serving farms, homes and surrounding rural areas and the associated disruption and the adequacy of proposed mitigation.

The applicants having had dialogue with the Town Council who have subsequently responded with further comments:

The Council welcomed the engagement that has taken place and found it meeting helpful in understanding how the works are proposed to be delivered.

Notwithstanding this, the Town Council commented that it was still mindful that the project will have significant impacts on the local community, particularly in relation to traffic and access. It therefore requested the following comments be considered:

• Should the application be granted, the Council would ask that the following matters are secured by planning condition:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Application No: P/2026/0054: Kronospan Limited, Holyhead Road, Chirk, Wrexham, LL14 5NTReport 677 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 20 attended
BA
Councillor Bryan ApsleyCommittee Member, present, as expected, virtual
TB
Councillor Trevor BatesCommittee Member, present, as expected, virtual
ID
Councillor I David Bithell MBECommittee Member, present
BB
Councillor Beryl BlackmoreCommittee Member, absent
AD
Councillor Annette DaviesVice-Chair, apologies
FH
Councillor Frank HemmingsCommittee Member, present
SJ
Councillor Steve Joe JonesCommittee Member, present
JM
Councillor John McCuskerCommittee Member, present
MM
Councillor Michael MorrisChair, present
JN
Councillor Jeremy NewtonCommittee Member, present, as expected, virtual
JP
Councillor John PhillipsCommittee Member, present
RR
Councillor Rondo RobertsCommittee Member, present, as expected, virtual

All 20 on the meeting page

On this subject at Wrexham

Search all
  1. Application No: P/2026/0054 - Kronospan Limited, Holyhead Road, Chirk, Wrexham, LL14 5NTThis decision
  2. Application No: P/2022/1080 - Kronospan Limited, Holyhead Road, Chirk, Wrexham, LL14 5NTApproved
  3. Application no: p/2022/1080 - kronospan ltd, holyhead road, chirk, wrexham, ll14 5ntDecided
  4. Application no: p/2022/0765 - kronospan ltd, holyhead road, chirk wrexham, ll14 5ntApproved
  5. Application no: p/2022/0336 - kronospan ltd, holyhead road, chirk, wrexham, ll14 5ntDecided
  6. Application no: p/2019 /0505 - kronospan ltd, holyhead road, chirk wrexham, ll14 5ntDecided

More from Wrexham Planning Committee

All decisions
MeetingDecisionOutcome
7 Sep 2026 Confirmation of MinutesRESOLVED – That the Minutes of the Meeting held on 27 July 2026 be signed as a correct record. Decided Open
7 Sep 2026 Application No: P/2025/0573 - Car Park, Tesco Stores Limited, Crescent Road, Wrexham, LL13 8HFRESOLVED – That planning permission be refused. Reason for decision (i) The proposal would introduce an additional ho... Refused Open
7 Sep 2026 Variation in Order of AgendaRESOLVED – That Agenda Item 4c – P/2026/0364 – Colliers Park, Wrexham AFC Training Ground, Chester Road, Gresford, Wr... Decided Open
7 Sep 2026 Application No: P/2026/0364 - Colliers Park, Wrexham AFC Training Ground, Chester Road, Gresford, Wrexham, LL12 8PWRESOLVED – That consideration of the application be deferred. Reason for decision To request the applicant to provide... Deferred Open
7 Sep 2026 Application No: P/2026/0174 - First and Second Floor Flat, 36 Brook Street, Wrexham, LL13 7LLRESOLVED – That planning permission be refused. Reasons for decision (i) The development will result in an overconcen... Refused Open