Executive Board, Tuesday 7 July 2026 at 10.30am

Relocation of Day Service

Noted Executive 5 papers

AI summaryWrexham Council's Executive Board approves transfer of Acton Resource Centre to Social Care to relocate the Cunliffe Day Service, with a phased plan to retain community use through a new building extension.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedTransfer of Acton Resource Centre and phased extension supported
Money£1m capital for 2026/27Plus £150,000 (2025-26) and £600,000 (2026-27) from WCBC General Capital Grant
What happens nextFurther engagement and design workFollowed by detailed plans, planning permission and funding confirmation
Who it affectsCunliffe users, families, Acton community groupsPlus WCBC staff in Social Care and Cleaning Services

What was decided

The Executive Board approved the transfer of Acton Resource Centre from Economy and Planning to Social Care to support the specialist Day Service. Report 3.2

Members supported a revised, phased proposal for Acton Resource Centre, including exploring an extension to allow the Day Service to co-locate with community groups. Report 3.3, 2.4, 4.11

The matter was dealt with as urgent business under Section 5 (Rule 5.8.10(m)) of the Council's Constitution, citing risks to this year's funding window and the Rhosddu Road housing timeline. Report 3.4, P14

Why

The current Cunliffe building no longer meets modern service delivery needs for adults with complex physical and learning disabilities, and the site must be released for around 57-60 new social housing units. Report 2.1, 4.1, 4.2

Acton Resource Centre was identified from an options appraisal as the most feasible site, being modern, having no sitting tenants, and adaptable for specialist use. Report 2.2, 4.3

Strong community and Local Member feedback, including a petition from over 700 local residents, prompted a revised plan to retain community use alongside the Day Service. Report 4.8, 4.9

What happens next

A structured engagement programme will run with community groups, Local Members, families, carers and staff to shape the design, layout and operational model of the extension. Report 6.3, P68, P70, P71, P72

Economy and Planning will lead engagement on the temporary relocation of community groups to alternative venues while Phase One internal works are carried out at Acton Resource Centre. Report P25, P69

A further report will return to the Executive Board once detailed extension plans are agreed, planning permission is approved, funding is secured and a joint running model is in place. Report 8.2, P91

The money

  • £150,000 WCBC General Capital Grant allocation for 2025-2026 Report P37
  • £600,000 WCBC General Capital Grant allocation for 2026-2027 Report P37
  • £1m Capital allocation for 2026/27 in the Capital Programme report for reconfiguring Acton Resource Centre Report 5.2, P39
  • £30k Previous annual funding contribution from Acton Community Council, ceased in 2022 Report 4.3

Options considered

  • Chosen: Proceed with relocation to Acton Resource Centre with phased approach and extension (Option 1). Retains community use, delivers modern fit-for-purpose Day Service, enables release of Cunliffe site for housing; requires further capital and approvals Report 7.1, P82, P83, P84
  • Rejected: Do not progress relocation to Acton Resource Centre (Option 2). Would leave unsuitable Cunliffe building in use, delay social housing delivery on the Rhosddu Road site, and increase operational and financial risks Report 7.2, P86, P87, P88

Implications

  • Financial: Capital grant of £150,000 (2025-26) and £600,000 (2026-27) approved, with a further £1m capital allocation for 2026/27; extension would require further capital and has cost implications. Report P37, P38, P39, 4.9
  • Legal: Council has statutory duties under the Social Services and Well-being (Wales) Act 2014 to promote wellbeing of adults with eligible needs; impact assessment and consultation duties apply. Report P41, 5.3, P48
  • Equalities: Integrated Impact Assessment covers Equality Act 2010, socio-economic duty, Welsh Language standards and Armed Forces Act; service supports adults with complex disabilities and young people aged 16+ transitioning from children's services. Report P48, 4.1, 4.4
  • Staffing: Day Service relocation is a base change, not a restructure; WCBC Cleaners would transfer; potential restructure at the Community Resource Centre subject to consultation; Trade Union engagement has commenced. Report P43, P44, P45, P46
  • Risk: Risks include not meeting assessed needs, reputational risk from consultation perceptions, delays to asset transfer or building works, and safeguarding/health and safety risks of co-location. Report P50, P51, P52, P53
  • Other: Carbon impact assessment has not been carried out at this stage.

Who and where

  • Adults with complex physical and learning disabilities using the Cunliffe Day Service and their families Report 2.1, 4.1, P60
  • Community groups and residents currently using Acton Resource Centre Report 2.3, 4.8, P64
  • Young people aged 16+ on Education Pathway 1 transitioning into Adult Social Care Report 4.4
  • WCBC Social Care staff and Cleaning Services staff Report P43, P45
  • Occupational Therapy Community Clinic and Betsi Cadwaladr University Health Board Physiotherapy users Report 4.5
  • Local Members, including those involved in a petition of over 700 residents in support of retaining community use

Timeline

  • March and early April 2026: Engagement activity with staff, Local Members, families, Acton community groups and residents Report 6.2, P57
  • 16th April 2026: Public engagement event held at Acton Resource Centre Report 4.8, P61
  • May 2026: WCBC Assets confirmed an extension to Acton Resource Centre is feasible, subject to planning and SAB approvals Report 4.11
  • 2025-2026: Capital allocation of £150,000 approved from WCBC General Capital Grant Report P37
  • 2026-2027: Capital allocation of £600,000 approved, plus £1m capital allocation for reconfiguring Acton Resource Centre Report P37, P39
  • 7th July 2026: Executive Board decision taken as urgent business Report 3.4
  • At least August 2026: Previous notices to community groups extended while further engagement takes place Report 4.10

Plain English for the jargon

  • Cunliffe Centre: Existing building-based Day Service for adults with complex physical and learning disabilities, located on a site earmarked for social housing redevelopment.
  • Acton Resource Centre: Council building identified as the preferred location to host the relocated Day Service, previously used for community purposes.
  • Sustainable Drainage Approval Body (SAB): Body that must approve sustainable drainage systems for new developments, referenced as a permission needed for the proposed extension.
  • Wellbeing Hub model: Approach to managing community spaces to strengthen their role as community assets, with income from room hire but not required to be fully self-financing.
  • Education Pathway 1: Programme for young people aged 16+ with additional learning needs transitioning from children's services into adulthood, intended to be co-located within the new Day Service.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item22

Resolved

RESOLVED – ( i ) That the updated position regarding the proposed relocation of the Cunliffe Day Service and the continued requirement to identify a fit for purpose facility be noted. (ii) That the transfer of Acton Resource Centre from Economy and Planning to Social Care to support the delivery and future operation of the specialist Day Service and associated provision be approved. (iii) That the development of a revised proposal for Acton Resource Centre, including the exploration of an extension and phased approach to enable relocation and co-location of community use, informed by feedback to date and further targeted engagement be supported. (iv) That this matter be dealt with as an urgent item of business in accordance with Section 5 (Rule 5.8.10(m)) of the Council’s Constitution. Reasons for Decisions ( i ) To ensure the Council can continue to meet the needs of individuals with complex needs by providing a modern, safe and suitable Day Service for those people requiring centre-based care and support. (ii) To enable the progression of a balanced and sustainable solution that considers both specialist service requirements and the needs of the local community, informed by further engagement and evidence. (iii) To enable the project to move quickly with the procurement exercise for Phase One of works at Acton Resource centre. There is a risk that any delay could impact on the ability to complete the works within this financial year, which could impact on availability of funding. In addition, any delay would have an impact on the overall project timeline for housing development scheme for Rhosddu Road.
Word for word from the decision Wrexham published for this meeting. Source: moderngov.wrexham.gov.uk

Follow this further

Built from Wrexham's papers

What the report saysPro

Report to Executive Board

Purpose of the report

The purpose of the report is to provide an updated position on the proposed relocation of the Day Service. This follows previous reports to Executive Board: Rhosddu Road Development Report COH/39/24 on 17.09.2026 and Rhosddu Road Development Proposals COH/02/25 on 21.05.2025

Executive summary

2.1The Cunliffe Centre currently provides a specialist building based Day Service for adults with complex physical and / or learning disabilities. However, the existing facility no longer meets modern service delivery requirements. There is also a long- standing corporate requirement to release the site for redevelopment to support the delivery of new social housing.

2.2Acton Resource Centre has been identified from the options appraisal attached at Appendix 1 as the preferred option.

2.3Engagement undertaken in March and April 2026 with staff, community groups and Local Members identified significant concern regarding the potential loss of community use at Acton Resource Centre, as the proposal considered day service use only at the building. The community groups were keen to explore co-location and in response to the concerns there is now a period of further consideration and engagement with all key stakeholders.

2.4The revised approach is to develop the building to allow for day service use and the use by the community groups, this includes the feasibility of extending the building. This would enable a phased approach, allowing the relocation of the Day Service while providing an opportunity for community use to co-locate in a timeframe determined by refurbishment and building work, within financial resources and informed by continued engagement.

2.5The continued and structured engagement, including activity led by Economy and Planning in relation to temporary relocation of community groups, will inform the development of the revised proposal and ensure that both specialist service requirements and community needs are appropriately balanced.

2.6Continued engagement with Cunliffe users, families and volunteers has been positively received, giving reassurance of an improved, more specialist environment and more flexible and modern service. Many families have expressed genuine excitement about the relocation, seeing it as a positive step towards a brighter, more supportive environment for their loved ones.

Recommendations

3.1That Executive Board notes the updated position regarding the proposed relocation of the Cunliffe Day Service and the continued requirement to identify a fit for purpose facility.

3.2That Executive Board approves the transfer of Acton Resource Centre from Economy and Planning to Social Care to support the delivery and future operation of the specialist Day Service and associated provision.

3.3That Executive Board supports the development of a revised proposal for Acton Resource Centre, including the exploration of an extension and phased approach to enable relocation and co-location of community use, informed by feedback to date and further targeted engagement.

3.4That this matter be dealt with as an urgent item of business in accordance with Section 5 (Rule 5.8.10(m)) of the Council’s Constitution.

Reasons for recommendations

(i) To ensure the Council can continue to meet the needs of individuals with complex needs by providing a modern, safe and suitable Day Service for those people requiring centre-based care and support.

(ii) To enable the progression of a balanced and sustainable solution that considers both specialist service requirements and the needs of the local community, informed by further engagement and evidence.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 77 KB Download
PDF
Appendix 2Appendix 2 2.7 MB Download
PDF
Appendix 3Appendix 3 92 KB Download
PDF
Appendix 4Appendix 4 573 KB Download
PDF
Relocation of Day ServiceReport 186 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 20 attended
DA
Councillor David A BithellVice-Chair, present
TE
Councillor Terry EvansCommittee Member, present
HJ
Councillor Hugh JonesCommittee Member, present
BP
Councillor Beverley Parry-JonesCommittee Member, present
JP
Councillor John PritchardCommittee Member, present
MP
Councillor Mark PritchardChair, present
PR
Councillor Paul RobertsCommittee Member, present
RW
Councillor Robert WalshCommittee Member, present
NW
Councillor Nigel WilliamsCommittee Member, present
PW
Councillor Phil WynnCommittee Member, present
BC
Councillor Brian CameronGuest, in attendance
AG
Councillor Andy GallandersGuest, in attendance

All 20 on the meeting page

More from Wrexham Executive Board

All decisions
MeetingDecisionOutcome
15 Sep 2026 Council Plan - Annual Performance Report 2025/26 and Year 4 Target SettingRESOLVED – ( i ) That the ‘Council Plan Annual Performance Report 2025/26’ as outlined in Appendix A of report CE/14/... Approved Open
15 Sep 2026 Brymbo Sports& Social Complex, Heritage Way, Tanyfron, Wrexham, LL11 5TGRESOLVED – ( i ) That the grant of a new lease be authorised, for a minimum term of 75 years, at a nominal rent of £1... Decided Open
15 Sep 2026 Local Development Plan Delivery AgreementRESOLVED – ( i ) That the Wrexham be approved for submission to the Welsh Government for their approval. (ii) That th... Approved Open
15 Sep 2026 Update: Wrexham UK City of Culture 2029 BidRESOLVED – That the Executive Board continue to demonstrate their full support for Wrexham's bid to become UK City of... Decided Open
15 Sep 2026 Proposal to consult on establishing a new special school for pupils with Additional Learning Needs (ALN) in Gwersyllt - Consultation FeedbackRESOLVED – ( i ) That the consultation feedback contained in the post consultation feedback report regarding the prop... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies