Written from the decision and the officer reportPDF Pro
OutcomeNotedBoth 2025/26 outturn and 2026/27 programme noted and approved
Money£103.1 millionProposed 2026/27 capital programme; £286.9m to 2028/29
What happens nextQuarterly monitoring continuesProgramme reviewed annually against agreed allocations
Who it affectsCouncil services and HRA schemesHighways, education, housing, social care, economy
What was decided
The Executive Board noted and approved the 2025/26 Capital Programme outturn, totalling £87,079k, which is £23,572k less than the position approved in March 2026. Report 2.1, 3.1, 4.1, 4.2
Members approved the Quarter 1 2026/27 position and the future years' programme, including a further £2.1m of support for highways maintenance, infrastructure improvements and footpaths, taking the 2026/27 highways total to just over £10m. Report 2.5, 3.2, 4.7
Why
The report complies with Financial Regulation 3.13, which requires the Chief Officer Finance & ICT to monitor and report on the Capital Programme to members. Report P10
Future year capital allocations approved in March and July 2025 were reviewed against the 2025/26 outturn, leading to reallocations and the additional highways funding. Report 2.5, 4.7
What happens next
The capital programme will be reviewed annually with monitoring of progress against agreed allocations. Report 4.8
Schemes that have been re-profiled, including Pontcysyllte Aqueduct, Welsh Medium Capital projects and decarbonisation retrofit work, are expected to be delivered in 2026/27 and future years. Report P20, P36, P57
The money
£87,079k Total 2025/26 capital expenditure including HRA Report 2.1, 4.2
£23,572k Net decrease versus March 2026 approved position Report 2.1, 4.2
£19,464k Net decrease on non-HRA projects Report P3
£4,108k Net decrease on HRA capital programme Report P3, P52
£103.1 million Total proposed capital programme for 2026/27 Report 4.6, 5.2
£286.9m Programme to 2028/29 including HRA Report 4.6, 5.2
£2.1m Additional highways, infrastructure and footpaths allocation for 2026/27 Report 2.5, 4.7
£6.6m Capital receipts funding required by proposed 3 year programme Report 4.9
£7.809m Wrexham General Capital Funding allocation for 2025/26 Report 4.4
£8.057m Wrexham General Capital Funding allocation for 2026/27 Report 4.4
Options considered
Chosen: Approve 2025/26 outturn as set out in Appendices 1 and 1a. Reflects actual 2025/26 spend and re-profiling into 2026/27 Report 3.1, 4.1
Chosen: Approve Quarter 1 2026/27 and future years' programme in Appendices 2 and 2a. Updates the programme with confirmed funding, re-profiled schemes and an extra £2.1m for highways Report 2.5, 3.2, 4.7
Implications
Financial: HRA borrowing levels reduced further than expected due to additional Welsh Government Optimised Retrofit Programme funding. Report P53, P57
Financial: A new Welsh Government capitalisation direction runs from 1 April 2025 to 31 March 2030, allowing some capital receipts to support revenue savings. Report 2.6, 4.11
Risk: Identified risks include capital receipts not being delivered to plan, reduced General Capital Funding and project overspends. Report 5.6, P80
Staffing: No direct staffing implications from this report, though HRA capital salaries show a £1,240k underspend linked to vacancies that are difficult to fill. Report 5.4, P60
Legal: Significant legal implications of individual projects are covered in separate, project specific reports.
Equalities: Equality impact assessments are carried out for specific projects as required. Report 5.5
Who and where
Wrexham County Borough Council services delivering capital schemes across highways, education, housing, social care, environment and the economy Report P18, P27, P33, P39, P47
Housing Revenue Account tenants, affected by re-profiled works on roofing, windows, doors, external wall insulation and new build schemes Report P57, P58
School pupils and families, with construction of a new school now expected to start in Autumn 2027 subject to tender Report P34
Residents in private sector housing reliant on Disabled Facilities Grants and minor adaptations, where referrals in 2025/26 were lower than budget Report P29, P55, P56
Brymbo Heritage Trust, receiving a working capital cash-flow loan funded from capital receipts to support the Stori Brymbo vision Report P25
Timeline
10 March 2026: Executive Board last revised 2025/26 capital programme (COFI/09/26) Report 4.1, P84
2025/26 financial year: Total capital expenditure of £87,079k recorded, including HRA Report 2.1, 4.2
April 2026: Start of new financial year and new Welsh Government capitalisation direction period Report 4.11
Summer 2026: Ysgol Bryn Alyn 3G Pitch Replacement project expected to complete using unspent grant carried forward Report P37
30 September 2026: Extended completion dates for Shared Prosperity Funding and Smart Car Parks schemes Report P22, P45
2026/27: Proposed capital programme of £103.1 million to be delivered Report 4.6, 5.2
March 2028: Latest date for revised Pontcysyllte Aqueduct & Canal World Heritage Site funding profile Report P20
2026/27 to 2028/29: Three year capital programme totalling £286.9m including HRA Report 4.6, 5.2
31 March 2030: End date of current Welsh Government capitalisation direction Report 4.11
Plain English for the jargon
HRA: Housing Revenue Account, the ring-fenced account for council housing income and spending
GCF: General Capital Funding, the un-hypothecated capital grant from Welsh Government
DFG: Disabled Facilities Grant, statutory funding for home adaptations assessed by an Occupational Therapist
EWI: External Wall Insulation, a decarbonisation retrofit measure for council homes
MRA: Major Repairs Allowance, Welsh Government funding for HRA capital works
GCG: General Capital Grant from Welsh Government
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item18
Resolved
RESOLVED – ( i ) That the Capital Programme outturn as detailed in Appendices 1 and 1a be noted and approved. (ii) That the Quarter 1 and future years’ programme as detailed in Appendices 2 and 2a be approved. Reason for Decisions This report follows an earlier monitoring report in March in compliance with Financial Regulation 3.13 that requires that the Chief Officer Finance & ICT monitors and reports to Members on the Capital Programme.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
To advise Members of the 2025/26 Capital Programme Outturn and to review the 2026/27 and future years’ capital programme position as at the end of Quarter 1 2026/27.
Executive summary
2.1The total capital expenditure in 2025/26 including the Housing Revenue Account (HRA) was £87,079k as detailed in Appendix 1. This is £23,572k less than the total approved by the Executive Board at its meeting on 10 March 2026 COFI/09/26. The reasons for the net decrease are:
• A net decrease in spend of £19,464k on non HRA projects including new or additional grant funding and re-phasing of spend to future years. • A net decrease in spend of £4,108k in the HRA capital programme.
2.2Each scheme within the Capital Programme is fully funded by borrowing supported by the Welsh Government, grants and contributions, capital receipts, and prudential borrowing. All schemes are reviewed as part of the quarterly monitoring exercise and the details are included in Appendices 1 and 1a.
2.3The resources available to fund the programme comprise Welsh Government un-hypothecated and hypothecated supported borrowing, grants, contributions, capital receipts and prudential system unsupported borrowing. 2.4 By their very nature, capital programmes are dynamic and during the course of the year, further funds may be made available for specific schemes. Levels of capital receipts are kept under review to ensure sufficient amounts are realised in line with planning assumptions. Therefore the current and future years within the programme are subject to changes as schemes develop and funding streams, such as specific grants, are confirmed. However, a significant part of the future programme can be determined now because of confirmed plans and funding being in place. This includes the continuation of annual capital provisions that are funded by General Capital Funding (GCF).
2.5Future year capital allocations were approved in March 2025 (COFI/05/25) and July 2025 (COFI/26/25). A review of these allocations for capital project funding has been carried out based on the outturn position and as a consequence, a further £2.1m of support for highway maintenance and infrastructure improvements and footpaths has been allocated for 2026/27. With previously agreed allocations, this means that the highways related elements of the capital programme in 2026/27 are increased to just over £10m. This is reflected in Appendix 2 and 2a.
2.6Welsh Government have confirmed that a new capitalisation direction will be in place from 1 April 2025 to 31 March 2030. This gives the option of using some capital receipts to support the delivery of revenue savings. The revised capital receipts policy approved by Executive Board in March 2025 (COFI/05/25) provides flexibility to consider how capital receipts are best applied to meet the funding requirements of the capital programme whilst recognising the benefits of having flexibility about the use of capital receipts, including in the support of the medium term revenue position.
Recommendations
3.1The Capital Programme outturn as detailed in Appendices 1 and 1a is noted and approved.
3.2The Quarter 1 and future years’ programme as detailed in Appendices 2 and 2a is approved.
Reason for recommendations
This report follows an earlier monitoring report in March in compliance with Financial Regulation 3.13 that requires that the Chief Officer Finance & ICT monitors and reports to Members on the Capital Programme.
4 BACKGROUND INFORMATION Capital Programme 2025/26
4.1The Executive Board approved the last revision of the capital programme 2025/26 on 10 March 2026 (COFI/09/26). Appendix 1 provides a summary of expenditure by service, the financing of that expenditure and the variance between the actual programme and the previously approved position.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.