Resolved
Resolved That a Special Meeting of the Committee, with site visits, be arranged to take place in late September 2005, to consider the Capital Flood Alleviation Programme.
Overview and Scrutiny Committee decided this item on Tuesday 19 July 2005. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved That a Special Meeting of the Committee, with site visits, be arranged to take place in late September 2005, to consider the Capital Flood Alleviation Programme.
1.1This report seeks to update members on the current position of Schemes in the original Capital Flood Alleviation Programme and progress on the second phase of feasibility studies.
2.1That the Overview and Scrutiny Committee notes the progress that has been made with Phases 1 and 2 of the Capital Flood Alleviation Programme.
3. Implications & Impact
3.1Council Priorities and Community Plan Themes The Capital Flood Alleviation Programme supports Priority 2 Healthy and Safe Communities and Priority 3 reaching out to everyone.
3.2Resource Implications
The existing CFAP Phase 1 Schemes and feasibility studies for the Phase 2 Schemes can be contained within the existing capital budget of £800,000. A further sum of £200,000 is available within the programme for works in the Phase 2 Programme. (dmt)
Staffing Implications None at this stage but dependant on the programme of works to be determined at a later date.
C:\Documents and Settings\lin\Local Settings\Temporary Internet Files\OLK337\Capital Flood Allev Programme Update.doc Legal None at this stage but may develop as any schemes progress in due course.
Property None at this stage. Any implications for future maintenance will be considered prior to carrying out any scheme.
4.1The purpose of this report is to update members of the current position of schemes in Phases 1 and 2 of the Capital Flood Alleviation Programme.
4.2The current position with schemes in Phase 1 of the Programme is shown in the table below.
Capital Flood Alleviation Programme Phase 1
Scheme Phase Status
Peopleton 1-4 All completed
Hawbridge 1-3 (originally 1-4) 1 & 2 completed apart from compensation to landowner – Phase 2. Phase 3 at tender stage now
Broadway 1-2 (Mill Lane Ditch – 1 completed 3 added) 2 abandoned 3 completed
Charlton 1-3a & 3b 1 completed 2 completed 3a completed 3b completed
Pebworth 1 Completed
Kington 1 Phase 2 – for future years
Wyre Piddle 1 Completed
Childswickham 1, option 1a section Option 1a section 1 completed 1 & 2 option 4 Section 2 completed Option 4 abandoned
East and West Side North 1 Feasibility completed. Littleton Liaison with WCC HPU and the EA commenced.
C:\Documents and Settings\lin\Local Settings\Temporary Internet Files\OLK337\Capital Flood Allev Programme Update.doc 4.3 Hawbridge Phase 3 and East/West Side North Littleton are the only schemes from the Capital Flood Alleviation Programme Phase 1 which remain to be completed.
4.4Hawbridge Phase 3 is probably the most difficult of any of the flood alleviation schemes to deliver. It is currently out to tender and the return date has been set for Friday 5th August. All consents have been obtained and we are pushing for a site start on Monday 5th September 2005. The scheme is anticipated to take 10 weeks.
4.5Road closures will be necessary and these have been applied for. The box culverts needed for this scheme have been ordered direct from the manufacturer so as not to impact on the programme for the work and create garden reinstatement problems.
4.6A customer care exhibition took place on Wednesday 13th July in the Bird in Hand to explain the scheme to all local residents who were invited to attend. This scheme will be highly disruptive to the village.
4.7The current position with the Phase 2 Schemes is shown in the table below
No Site location Parish No of internally Total HE Progress flooded properties Points
1 Post Box Corner Lower Bredon 12 15.84 Draft report Westmancote comp. March 05
2 Leys Road & Harvington Cross Harvington 9 15.2 Draft report comp. July 05
3 Plough Road & Foredraught Lane Tibberton 9 31.252 Work ongoing
4 Earls Common Road Stock 7 9.82 Draft report Green comp. June 05
5 Lower Moor Hill & Moor 6 12.84 Draft report comp. Jan 05
6 Holberrow Green Inkberrow 5 8.5 Draft report comp. Nov 04
7 Broad Lane & Main Street Bishampton 5 8.06 Draft report comp. Mar 05
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Flood Alleviation Programme: UpdateReport | 133 KB | DownloadRead as text |
Follow Overview and Scrutiny Committee at Wychavon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Minutes of Previous MeetingResolved That the Minutes of the meeting held on Wednesday 8 July 2026, be approved as a correct record and signed by... | Approved | Open |
| 8 Jul 2026 | Minutes of Previous MeetingResolved That the Minutes of the meeting held on Wednesday 8 April 2026, be approved as a correct record and signed b... | Approved | Open |
| 8 Jul 2026 | We Are Wychavon 2025/26 - Quarter 4 Performance ReportIt was agreed the future ‘We Are Wychavon’ reports would include data relating to whether developers were directing t... | Agreed | Open |
| 8 Jul 2026 | Overview and Scrutiny Committee Annual Report for 2025/26Resolved That the Overview and Scrutiny Committee Annual Report for 2025/26 be approved, and that it be sent to the C... | Approved | Open |
| 8 Jul 2026 | Overview and Scrutiny Committee Workplan for 2026/27It was agreed that this would provide a good opportunity for some productive work. Planning Enforcement Scrutiny Pane... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.