CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Wychavon District Council
Executive Board, Tuesday 12 October 2010

Capital Flood Alleviation Programme - Bishampton

Noted Executive 4 papers

Executive Board noted this item on Tuesday 12 October 2010. Below is the council's own wording, with the papers it was decided on.

Item63

Resolved

Resolved 1. That the progress to date be noted and that the Deputy Managing Director and Engineering Consultancy Manager in consultation with the Portfolio Holder progress the scheme and proceed through to construction. 2. That the Executive Board affirms its approval to enter onto the land using powers under the Land Drainage Act 1991, should the need arise, and notes that in doing so will need to compensate some of the affected landowners for appropriate losses caused by the works.
Word for word from the decision Wychavon published for this meeting. Source: mgov.wychavon.gov.uk

Follow this further

Built from Wychavon's papers

What the report saysPro

Report to Executive Board, 4 pages

Summary

1.1This report seeks permission to proceed with the Bishampton flood alleviation scheme which is being progressed in partnership with Worcestershire County Council’s Highways.

1.2The report also details the three options that have been evaluated and recommends a preferred option to proceed to detailed design, tender invitation and contract.

1.3Funding for the scheme is being provided by Defra, the County Council’s Highways, Bishampton Parish Council and Wychavon’s own funds from the Capital Flood Alleviation Programme.

Recommendations

2.1That the Executive Board notes the progress to date and authorises the Deputy Managing Director and Engineering Consultancy Manager in consultation with the Portfolio Holder to progress the scheme and proceed through to construction.

2.2That the Executive Board reaffirms its approval to enter onto the land using powers under the Land Drainage Act 1991, should the need arise, and notes in doing so will need to compensate some of the affected landowners for appropriate losses caused by the works. 3. Implications & Impact

3.1Council Priorities and Community Plan Themes

Goal: To aid recovery from flooding and reduce the impact of future floods.

3.2Resource Implications

3.2.1 Financial Implications

- Some £954,000 of the approved Capital Flood Alleviation programme has now been committed, leaving a balance of £576,000 available to complete the remaining schemes in the programme.

- Whilst the cost to the Council for this particular scheme may vary to that previously identified, they will be contained within the overall capital programme budget. (V.A)

3.2.2 Staffing implications - Apart from the hydraulic modelling carried out by Consultants this scheme is being carried out by the Engineering Consultancy Team. It is not anticipated to use any other technical resource on this scheme.

3.2.3 Risks - contained within the report.

3.2.4 Legal – Discussed in the report – s 4.7

3.2.5 Property – No property related issues for the Council. Future maintenance responsibility is expected to be taken on board by other partners and individual landowners.

3.3Diversity Impact Assessment

None carried out.

Background

4.1The Bishampton Scheme is one of the last schemes remaining in the Capital Flood Alleviation Programme. The broad brush feasibility for the scheme was carried out by the in-house team in the second tranche of possible flood alleviation projects. The scheme has been promoted on the basis that no less than five homes had been internally flooded during the Easter 1998 flooding incident. This figure increased to eighteen during July 2007. It should be noted at this stage that this scheme will not provide alleviation to all eighteen properties as several are on the outskirts of the village and did not register in the1998 event.

4.2The notional scheme for Bishampton received approval in principle from the Executive Board in November 2005. Since then a number of changes have been taken place which have had to be taken into account. The scheme has now been developed taking into account extensive investigations following the 2007 floods carried out independently by the in-house team and County Highways and also the effects of minor improvements carried out by a developer in Broad Lane.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Flood Alleviation Programme: BishamptonReport 4 pages DownloadRead as text
PDF
OPTION 1 REPORT-A4 LANDSCAPEReport 1 pages Download
PDF
OPTION 2 REPORT-A4 LANDSCAPEReport 1 pages Download
PDF
OPTION 3 REPORT-A4 LANDSCAPEReport 1 pages Download

At this meeting

Whole meeting

On this subject at Wychavon

Search all
  1. Capital Flood Alleviation Programme - BishamptonThis decision
  2. Capital Flood Alleviation Programme - Harvington and Bishampton Flood Alleviation SchemesNoted
  3. Capital Flood Alleviation ProgrammeNoted
  4. Capital Flood Alleviation SchemesNoted
  5. Capital Flood Alleviation Scheme - results of contribution requests to Parish CouncilsNoted
  6. Capital Flood Alleviation Programme - Feasibility Study - 2nd Tranche SchemesApproved

More from Wychavon Executive Board

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr... Decided Open
16 Sep 2026 Budget 2027/28Resolved That Executive Board Approves the budget timetable for the 2027/28 budget process, attached at Appendix A, i... Approved Open
16 Sep 2026 Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t... Approved Open
16 Sep 2026 Street Naming and NumberingResolved That the revised ‘ Policy’, as presented in Appendix 1, be adopted. Approved Open
16 Sep 2026 Street Naming and Numbering for Wychavon TownResolved That the street naming and numbering for the development of Wychavon Town, delineated by the allocation in t... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies