CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Wychavon District Council
Executive Board, Tuesday 11 January 2011

Capital Flood Alleviation Programme - Harvington and Bishampton Flood Alleviation Schemes

Noted Executive 2 papers

Executive Board noted this item on Tuesday 11 January 2011. Below is the council's own wording, with the papers it was decided on.

Item98

Resolved

Resolved 1. That the current progress and financial position on the remaining schemes within the Capital Flood Alleviation Programme be noted. 2. That the two retention Basin Option for Harvington be abandoned due to the estimated high cost of the scheme and the results of the benefit/cost analysis carried out by Consultants WSP. 3. That the minor works as detailed below be progressed immediately subject to the Defra funding being retained: · Cattle grid and chamber on an access track currently owned by WCC – cost to implement circa £20,000; · Household level protection devices such as flood guards and airbrick covers – cost to implement circa £114,000 and limited to £6,000 per property (£4,500 plus all fees); · By pass channel around one property – cost to implement £35,000 · Upsizing some culverts under private driveways off Leys Road where appropriate. This work should only be considered if the bypass channel – item 3 – can be constructed – cost to implement £25,000. 4. That , should the Defra funding be withdrawn, the minor schemes proceed and the available finance for further schemes be reviewed on completion of the Harvington and Bishampton Schemes. 5. That the longer term option to pursue changes in land management by creating woodland areas or other features in appropriate locations at Harvington be taken out of the Capital Flood Alleviation Programme and progressed by Officers at the earliest opportunity. 6. That the results of the Tender exercise for the Bishampton Flood Alleviation Scheme be noted.
Word for word from the decision Wychavon published for this meeting. Source: mgov.wychavon.gov.uk

Follow this further

Built from Wychavon's papers

What the report saysPro

Report to Executive Board, 5 pages

Summary

1.1This report informs Members of the results of the feasibility study and cost benefit exercise on Phase 2 of the Harvington Scheme and requests permission to abandon the preferred option and proceed to examine other alternative measures to reduce flood risk and build resilience to those properties identified as being at risk.

1.2The report also informs Members of the current overall financial position and the implications for the Defra Funding allocation on the basis of not proceeding with the preferred two retention basin option.

1.3It is hoped that Defra will allow some flexibility to “mix and match” the allocated funding between their Surface Water Early Action Grant and the Property Level Flood Protection and Resilience Schemes so that the £100,000 allocation can be retained for the benefit of Harvington.

Recommendations

2.1That the Executive Board notes the current progress and financial position on the remaining schemes within the programme.

2.2That the two retention Basin Option for Harvington be abandoned due to the estimated high cost of the scheme and the results of the benefit / cost analysis carried out by Consultants WSP.

2.3That the minor works at detailed in Section 4.8 of the report be progressed immediately subject to the Defra funding being retained.

2.4That should the Defra funding be withdrawn that the minor schemes proceed and the available finance for further schemes be reviewed on completion of the Harvington and Bishampton Schemes.

2.5That the longer term option to pursue changes in land management by creating woodland areas or other features in appropriate locations at Harvington be taken out of the CFAP and progressed by Officers at the earliest opportunity.

2.6That the Board notes the results of the Tender exercise for the Bishampton Flood Alleviation Scheme.

3. Implications & Impact

3.1Council Priorities and Community Plan Themes

Greener – to aid recovery from flooding and reduce the impact from future floods.

Service goal to progress remaining schemes through all approval stages.

3.2Resource Implications

3.2.1 Financial Implications:

Some £976,000 of the approved Capital Flood Alleviation Programme (CFAP) has now been committed, leaving a balance of £223K available to complete the remaining schemes in the programme. In addition, we have contributions from the County Council and Defra totalling £360,000. (AW)

3.2.2 Staffing Implications – The works at Bishampton and Harvington must be ideally completed before the 31 March 2011 as a condition of the grant approval. To achieve this, the appointment of consultants will be necessary to complete the detailed design on the Harvington Scheme but we will seek to minimise our use of consultants. This will enable the Council’s Engineering Staff to continue to progress the Tibberton and Bishampton Schemes.

3.2.3 Legal - none at this stage dealt with in previous reports

3.2.4 Diversity Impact Assessment – not carried out

Background

Harvington

4.1Harvington Phase 2 – the final phase - is being investigated and tested in partnership with the County Council’s Highways Section. Consultant WSP has been employed jointly by WDC and WCC and all Consultant fees have been equally shared. The Consultants have been employed to carry out surface water flood route modelling which is the first time this technique has been used by the Engineering Team. The Consultants were also instructed to carry out a benefit / cost exercise as part of their brief.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Flood Alleviation Programme: Harvington and Bishampton Flood Alleviation SchemesReport 5 pages DownloadRead as text
PDF
Plan: Harvington: Capital Flood Alleviation ProgrammeReport 1 pages Download

At this meeting

Whole meeting

On this subject at Wychavon

Search all
  1. Capital Flood Alleviation Programme - Harvington and Bishampton Flood Alleviation SchemesThis decision
  2. Capital Flood Alleviation Programme - BishamptonNoted
  3. Capital Flood Alleviation ProgrammeNoted
  4. Capital Flood Alleviation SchemesNoted
  5. Capital Flood Alleviation Scheme - results of contribution requests to Parish CouncilsNoted
  6. Capital Flood Alleviation Programme - Feasibility Study - 2nd Tranche SchemesApproved

More from Wychavon Executive Board

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr... Decided Open
16 Sep 2026 Budget 2027/28Resolved That Executive Board Approves the budget timetable for the 2027/28 budget process, attached at Appendix A, i... Approved Open
16 Sep 2026 Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t... Approved Open
16 Sep 2026 Street Naming and NumberingResolved That the revised ‘ Policy’, as presented in Appendix 1, be adopted. Approved Open
16 Sep 2026 Street Naming and Numbering for Wychavon TownResolved That the street naming and numbering for the development of Wychavon Town, delineated by the allocation in t... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies