Resolved 1. That the progress to date and the actions of the Deputy Managing Director, Head of Environmental Services in liaison with the Portfolio Holder for the Environment and Contracted Services be noted and that a further update will be submitted during the Autumn. 2. That Authority be delegated to the Deputy Managing Director in consultation with Portfolio Holder for Environmental Contracted Services to deal with any unforeseen fluctuations providing that the overall budget of £74,000 is not exceeded.
Word for word from the decision Wychavon published for this meeting.Source: mgov.wychavon.gov.uk
1.1This report updates members on the current position regarding the Parish Flood Alleviation Support Grant Scheme which was introduced as a result of residual funds from the Government becoming available. The report also seeks delegated approval to increase the budget allocations in certain circumstances in order to facilitate progress on some projects – subject to sufficient funds being available within the scheme.
Recommendations
2.1That the Executive Board notes the progress to date and the actions of the Deputy M.D., Head of Environmental Services in liaison with the Portfolio Holder for the Environment and Contracted Services and that a further update will be submitted during the Autumn.
2.2That Authority is delegated to the Deputy Managing Director in consultation with Portfolio Holder for Environmental Contracted Services to deal with any unforeseen fluctuations providing that the overall budget of £74,000 is not exceeded.
3. IMPLICATIONS & IMPACT
3.1Council Priorities and Community Plan Themes
3.1.1 In accordance with Greener – a better environment for today and tomorrow – (5) To aid recovery from floods and reduce the impact of future floods.
Financial implications
3.2.1 Contained within the report. A total budget allocation of £74,000 has been set up for this initiative provided from residual funds from the Flood Recovery Grant and European Restoration Fund. (AW) 3.3 Staffing Implications
3.3.1 Contained within existing resources
3.4Legal
3.4.1 None at this stage
Background
4.1Members will be aware that the Parish Flood Alleviation Support Grant Scheme was approved by the Executive Board at its meeting of 6th January 2009 (min 116). Details of the scheme were circulated to all Parish Councils with a deadline for applications to be received no later than 30th April 2009.
4.2In all 21 applications were received but 5 were regarded as beyond the scope of the scheme and therefore rejected. Details of all applications are shown in the table in Appendix A. Comments on current progress of all approved schemes have been made and are also shown in the table.
4.3One Parish Council (56) Little Comberton embarked on a flood defence scheme and decided to withdraw its application as a result of the County Highways carrying out significant improvements to the highway drainage system in the vicinity of its proposals. The Parish Council confirmed in writing that it did not intend to progress its project and the allocated funds would not be claimed.
4.4As a result of a necessity to seek legal advice with regard to the Peopleton proposals, the Council has had to accommodate a legal fee of £1300. In addition to this Tenders have been received for the Flood Defence works in Abbey Park £1200 over the budget allocation of £5000. It has been agreed between the Portfolio Holder, Deputy Managing Director and Head of Environmental Services that these two additional items be taken out of the budget allocation of £74,000.
4.5In view of the uncertainty of some of the projects within the scheme it would prudent to delegate authority to the Deputy Managing Director and Portfolio Holder to deal with any unforeseen fluctuations providing that the overall budget of £74,000 is not exceeded. APPENDIX A
Parish Flood Alleviation Support Grant Scheme Progress Update for Executive Board Briefing – 12th May 2010
PARISH APPROVED/ LETTER DATE OF BUDGET PARISH NAME COMMENTS NO. REJECTED SENT MEETING ALLOC. Agreement in Assistance being provided and project 7 Beckford Principle 19 June 13th July 2009 £5K progressing. Bishampton & (A in P) Assistance being provided and project 11 A in P 19 June 9th July, 2009 £5K? Throckmorton progressing. Assistance being provided and project 12 Bredon - Kinsham A in P 19 June 13th July 2009 £5K progressing. To be used as a contribution towards the main 19 Charlton A in P £5K EA scheme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr...
Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.