Resolved 1. That the Better-not-Busier Annual Report and future direction of the programme be noted. 2. That the Board receives an Annual Report detailing the activities and savings of the Better-not-Busier programme. 3. That the Portfolio Holder for Leisure, Culture and Regeneration be given responsibility for the oversight of and involvement of the Member panel in the Better-not-Busier programme.
Word for word from the decision Wychavon published for this meeting.Source: mgov.wychavon.gov.uk
BY: Cllr Tom McDonald, Executive Board Member, Fiona Narburgh, Head of Strategy & Communications and Cheryl Peters, Business Improvement Manager
TITLE Annual Report on “Better not Busier” – Wychavon’s Transformation WARD No Programme
1. Executive summary and recommendations
Back in November 2008 we set up our Better not Busier programme, with 2 dedicated officers to drive the work, a Board of members to oversee and a mission to do 2 things;
1. Improve services for the customer 2. Achieve financial savings
These would happen as a result of identifying - through lean process reviews (our version of transformation/ Vanguard change programmes) - the ‘waste’ in the system i.e. the things that we are doing that overcomplicate a process and add little benefit for the customer.
Has it worked? Have we secured service improvements and cost savings through the programme? The short answer is that we have perhaps done better on the customer aspect than the financial one. This Annual Report sets out what has been achieved this year. We can show many examples of improving services to customers though shorter process times, ditching unnecessary processes and procedures etc as set out in the report. While we are less able to directly quantify financial resources saved, reviews have helped teams with focus, when posts became vacant it is easier after a BnB (Better not Busier) review not to fill the post because people were, as the saying goes “doing the right things, not doing things right”. It’s about putting in place a way of thinking and doing that is about continuous improvement. Better not busier isn’t simply a process review methodology, it’s also become part of the Wychavon culture and ethos. It is in part helping the organisation to downsize (208 full time employees now from 312 a year ago) to meet the financial challenges. It has helped identify where resources can be freed up, or moving people into more useful work.
The cultural side of BNB also links to our other strands of efficiencies too, for example the work to date to negotiate contracts and procure better. For example reducing our energy consumption - 4.4% reduction in electrical consumption compared to 2008/9 and a 13% reduction in gas consumption, saving £10,500 on our 2009/10 energy bills compared to last year. BNB has also been instrumental is demonstrating the case for good knowledge and evidence based decision making. For example a recent piece of BnB work was ‘why do customers come and see us’, analysing face to face contact at Evesham. We found that much of the contact was ‘avoidable’, people coming to see us because they didn’t understand their letters or the process or they were already in the system but didn’t know what was happening to their claim and were chasing updates. The solution was to work with revenues and benefits to reduce the backlog and improve communication and as a result we have seen a reduction of the (expensive) face to face contact overall.
Practical benefits and savings are summarised in this report, and Appendix 1 provides more detail on each. It also sets out the future programme with both specific reviews eg, into car parking and planning as well as wider reviews such as reaping the benefits of housing and planning merger and further work to reduce avoidable contact.
We have proved that reviewing processes does free up staff time and therefore resources. Given the budget challenges we face we are now using our BnB reviews to help identify savings so we can maintain our brand and customers expectations of ‘good services, good value’. This report also asks the Board whether the BnB Member Panel is still needed following successful programme establishment.
2. Recommendations for the Board
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr...
Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.