Resolved 1. That the Deputy Managing Director be authorised to submit a deemed Planning Application under Article 3 of the Town and Country Planning General Regulations 1992. 2. That the scheme be advertised for sale on the open market, with development conditions, including some social housing, the rebuilding of the church and shop. 3. That delegated authority be given to the Deputy Managing Director in consultation with the Portfolio holder for Resources to agree the final terms of disposal. 4. That a provision of up to £25,000 be added to the Capital Programme, which will be recovered from the eventual Capital Receipt.
Word for word from the decision Wychavon published for this meeting.Source: mgov.wychavon.gov.uk
1.1This report sets out the proposals for redevelopment of an area in Blake Avenue in partnership with The Emmanuel Church, and seeks approval to submit a deemed planning application, and authority to market the site in due course
Recommendations
The Committee is asked to resolve that
2.1The Deputy Managing Director be authorised to submit a deemed Planning Application under Article 3 of the Town and Country Planning General Regulations 1992.
2.2The scheme is advertised for sale on the open market, with development conditions, including some social housing, and the rebuilding of the church and shop.
2.3Authority is delegated to the Deputy Managing Director in conjunction with the Portfolio holder for Resources to agree the final terms of disposal.
2.4A provision of up to £25,000 be added to the Capital Programme which will be recovered from the eventual Capital Receipt.
3. Implications & Impact
3.1Council Priorities and Community Plan Themes
3.2Priority 1 – Safer The redevelopment will address the anti social behaviour issues currently experienced on the site, by applying the principals of “Secure by Design” and encouraging passive surveillance of the open areas 3.3. Priority 2 – Greener The new open areas within the proposed development will balance the built environment with the adjacent green space which the design of the housing will enhance by appropriate boundary treatments. The development will create a clean modern environment. The new housing will provide energy efficient accommodation.
3.4Priority 3 – Healthier The new housing will provide one single storey unit specifically designed for disabled persons.
3.5Priority 4 – Stronger The development will provide approx 29 units of residential accommodation, in a mix that responds to the local housing needs survey. Further the proposal is that approx 50% of the residential accommodation will be new affordable/ social housing some of which will be offered on a shared ownership basis. The improved community centre will improve community facilities, and a new church above the community centre will again improve these facilities for the local community with the hope to make it more inclusive. The new shop will be a modern, brighter improved facility for the local neighbourhood, with better short term parking reducing the environmental impact of poor parking provision that currently exists.
Priority 5 – Successful The proposed sale will provide the Council with a capital receipt to enhance other priorities of the Council, and address the proposal in the Asset Management Plan to use the Council resources to best effect, and dispose of surplus assets.
4.0Resource Implications
4.1Financial implications - this disposal will hopefully provide a capital receipt to the Council. The value of the capital receipt will also be dependant upon final user of supermarket and affordable housing costs. There will also be a cross subsidy to Emmanuel Church to enable the full cost of rebuilding the church to be met from the development, as they only own approx 23% of the site. There will be some development costs that will need to be reimbursed by the scheme including design and planning costs. All of these costs will be deducted from the eventual capital receipt.
4.2Staffing implications – progressing the sale and marketing will require continued staff time to produce the sale
4.3Risks - The proposed community consultation will raise expectations to improve the area and facilities, which if they can not be realised could produce negative press results
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr...
Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.