AI summaryWychavon Executive Board recommends accepting up to £1.25m of external grant funding for the Wychavon Town new settlement and adding it to the Capital Programme.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedUp to £1.25m to go into Capital Programme
MoneyUp to £1.25mExternal grant funding, no council cost
What happens nextFull Council to decideThen Deputy Chief Executive to agree allocations
Who it affectsFour rural wardsWhittington, Norton Juxta Kempsey, Stoulton, Drakes Broughton and Wadborough
What was decided
The Executive Board recommends that Council accepts the proposed funding and that up to £1.25m is added to the Capital Programme as a financial allocation for the Wychavon Town projects. Report P7
Delegated authority is recommended to be given to the Deputy Chief Executive, in consultation with the Leader and the portfolio holders for Resources, Investment and Innovation and for Planning, Infrastructure and Urban Design, to agree the increased funding allocations. Report 2.2
Why
Officers have secured grant funding from Homes England, including through the New Homes Accelerator Programme, and from the Ministry of Housing, Communities and Local Government to cover the costs of technical work, a planning application, public engagement, policy development and an education pilot for the new settlement. Report 3.2, 3.3, P12, P14, P16, P18, P20
Accepting the funding is of significant financial benefit to the Council because the work is paid for by external bodies, and a proportion of the funding has already been received and will be shown retrospectively in the budgets. Report 3.2, 3.3
The risk of funding not being received is low, as several allocations have already been received and there are formal commitments from Homes England and MHCLG. Report 4.2
What happens next
Council is asked to accept the funding and add up to £1.25m to the Capital Programme, with the money supplied by the external bodies. Report P7, 3.3
The Deputy Chief Executive will then agree the increased funding allocations in consultation with the Leader and the two named portfolio holders. Report 2.2
A planning application for strategic infrastructure at Wychavon Town, prepared by Arcadis, is due to be submitted later in 2026, with Homes England funding support capped at £750,000. Report 3.5, P14
The money
£170,000 Homes England grant for technical work on the new settlement in 2025/26, covering legal advice, transport modelling and related activity Report 3.4, P12
Up to £750,000 Homes England funding support for the strategic infrastructure planning application being prepared by Arcadis Report 3.5, P14
Up to £20,000 Homes England ATLAS Team funding for public engagement support on the Wychavon Town Draft Supplementary Planning Document consultation in January and February 2026 Report 3.6, P16
£160,000 MHCLG New Towns Unit funding for policy development work, including technical studies, financial modelling, delivery and governance models and a construction management strategy Report 3.7, P18
£150,000 MHCLG funding for an Education Digital Pilot for Wychavon Town and the surrounding area, led by 1st Planner with Wychavon District Council and Worcestershire County Council on the project team Report 3.8, P20
Options considered
Chosen: Accept the proposed external funding and add up to £1.25m to the Capital Programme. Work is paid for by external bodies and offers significant financial benefit to the Council, with low risk because funding is already secured or formally committed. Report P7, 3.2, 3.3, 4.2
Chosen: Delegate authority to the Deputy Chief Executive to agree the increased funding allocations. Allows the detailed allocations to be agreed in consultation with the Leader and the relevant portfolio holders. Report 2.2
Implications
Financial: The Capital Programme will be increased by up to £1.25m, funded externally by Homes England and MHCLG, with no cost to the Council and a proportion already received. Report 3.3, 4.2
Risk: Risk of funding not being received is low: several allocations have already been paid and Homes England and MHCLG have given formal commitments. Report 4.2
Equalities: The screening impact assessment did not identify any potential adverse impacts on any equality groups. Report P24
Other: No privacy impact assessment is needed because the funding is for investigatory and review work. Report 4.2
Who and where
Residents of the Whittington, Norton Juxta Kempsey, Stoulton and Drakes Broughton and Wadborough wards, where the new settlement is planned Report P2
Wychavon District Council, which is leading the Wychavon Town development work and the planning application Report P12, 3.5, P14
Worcestershire County Council, as a partner in the Education Digital Pilot project team Report 3.8, P20
Timeline
2025/26: Homes England provided £170,000 grant for technical work and allocated up to £20,000 via the ATLAS Team for public engagement Report 3.4, 3.6, P12, P16
End of the last financial year: MHCLG New Towns Unit provided £160,000 of policy development funding for large housing settlements Report 3.7, P18
15th October 2025: Full Council agreed the appointment of Arcadis to prepare the strategic infrastructure planning application for Wychavon Town Report 3.5, P14
January and February 2026: Public consultation on the Wychavon Town Draft Supplementary Planning Document, with engagement support from Engage Planning Report 3.6, P16
24th June 2026: Executive Board is asked to recommend that Council accepts the funding and adds up to £1.25m to the Capital Programme Report P1, P7
Later in 2026: The strategic infrastructure planning application for Wychavon Town is currently due to be submitted Report 3.5, P14
Plain English for the jargon
Capital Programme: The council's planned spending on long term projects and assets, which is set and varied by Full Council.
Homes England: The government's housing and regeneration agency, which funds and supports new housing delivery.
MHCLG: The Ministry of Housing, Communities and Local Government, a UK government department.
New Homes Accelerator Programme: A Homes England programme that supports the early delivery of large new housing settlements.
New Towns Unit: A unit within MHCLG set up to lead the government's work on new towns and large new settlements.
Section 106 agreement: A legal agreement between a local authority and a developer, used to make development proposals acceptable in planning terms, for example by requiring infrastructure or affordable housing.
Supplementary Planning Document: A local planning document that adds detail to the policies in a council's adopted planning framework.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
Resolved That Executive Board recommends that Council accepts the funding proposed and up to £1.25m is included in the Capital Programme to provide a financial allocation for the projects. And That delegated authority be given to the Deputy Chief Executive in consultation with the Leader and the Executive Board Members for Resources, Investment & Innovation and Planning, Infrastructure & Urban Design to agree the increased funding allocations.
Word for word from the decision Wychavon published for this meeting.Source: mgov.wychavon.gov.uk
Wychavon Town Funding Proposals Relevant wards: Whittington, Norton Juxta Kempsey, Stoulton and Drakes Broughton & Wadborough
Portfolio holder(s): • Cllr. Emma Stokes, Portfolio Holder for Resources, Investment and Innovation
• Cllr Emma Kersey, Portfolio Holder for Planning, Infrastructure and Urban Design
Head of Service/ Contact Officer: Doug Lee, If you have any questions about this report, please contact the portfolio holder or the contact officer.
1. Purpose and summary 1.1 To update members in relation to the funding allocations that have been progressed with Homes England and MHCLG to cover a number of costs associated with the technical work and associated support for the Wychavon Town development.
2. Recommendations 2.1. That Council accepts the funding proposed and up to £1.25m is included in the Capital Programme to provide a financial allocation for the projects.
2.2That delegated authority be given to the Deputy Chief Executive in consultation with the Leader and the Executive Board Members for Resources, Investment & Innovation and Planning, Infrastructure & Urban Design to agree the increased funding allocations. 3. Background 3.1. As Members are aware officers are working with colleagues at Homes England (HE) and MHCLG to progress more detailed modelling, investigations and reviews to enable the progression of the Wychavon Town development.
3.2Officers have been very successful in securing grant funding from HE (including through the New Homes Accelerator Programme) and MHCLG to cover the costs associated with the work to be commissioned which is of significant financial benefit to the Council.
3.3Below are the individual elements that are to be funded. Should the funding be accepted by Council the capital programme will be increased with the relevant funding to be made by the external bodies. It should be noted that a proportion of the funding has already been passed over by the funding bodies and therefore will be shown retrospectively in the financial budgets
3.4Technical Works – Homes England £170k
Homes England provided £170,000 grant funding in 2025/26 for technical work to advance the delivery of the new settlement at Wychavon Town. Within the grant funding agreement this specifically related to legal advice (including progressing a framework Section 106 agreement for Wychavon Town); transportation modelling and other such activities (subject to the discretion of Homes England) that progress the early delivery of the settlement and the objectives of the New Homes Accelerator Programme
3.5Strategic Infrastructure Planning Application Support – Up to £750k (ongoing)
Wychavon District Council (WDC) has appointed consultants, Arcadis, to prepare a planning application for the delivery of strategic infrastructure at Wychavon Town (as agreed at Full Council on the 15th October 2025). The planning application is currently being progressed and is due to be submitted later this year. Homes England have agreed to provide funding support in respect of the preparation, submission and determination of the proposed planning application. Funding from Homes England is currently capped at £750,000 and will include work directly commissioned by the Council, technical work (in kind) or work already undertaken to support the application.
3.6Public Engagement – Up to £20k 2025/26
The ATLAS Team (Advisory Team for Large Applications) within Homes England allocated up to £20k towards staffing support on public engagement. This was delivered via a consultancy, Engage Planning, who provided engagement support in terms of the public consultation undertaken on the Wychavon Town Draft Supplementary Planning Document in January / February 2026.
3.7Policy Development – New Towns Unit - £160k ongoing
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr...
Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.