Resolved
Resolved That the Executive Board considered the report and recommends to Council the inclusion of £80k in the Capital Programme for 2026/27 to fund the Foundational Feasibility Study to be financed from reserves
AI summaryWychavon Executive Board recommends Council adds £80k to 2026/27 Capital Programme for a Network Rail foundational feasibility study on a footbridge at Honeybourne station.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
Resolved That the Executive Board considered the report and recommends to Council the inclusion of £80k in the Capital Programme for 2026/27 to fund the Foundational Feasibility Study to be financed from reserves
EXECUTIVE BOARD 24th JUNE 2026
Honeybourne Station Footbridge Viability Study Proposal Relevant wards: Honeybourne, Pebworth & The Littletons Portfolio holder(s): • Cllr. Emma Stokes, Portfolio Holder for Resources, Investment and Innovation
Head of Service/ Contact Officer: Jayne Pickering, Deputy Chief Executive & S151 Officer If you have any questions about this report, please contact the portfolio holder or the contact officer.
1. Purpose and summary 1.1 To update members regarding work that has been ongoing in relation to the increase in car parking provision at Honeybourne station and the proposed approach in terms of a feasibility study to be undertaken by Network Rail
2. Recommendations 2.1. That the Executive Board considers the report and recommends to Council the inclusion of £80k in the Capital Programme for 2026/27 to fund the Foundational Feasibility Study (detailed at 3.7 below) to be financed from reserves
3. Background 3.1. As members are aware the Council’s Corporate Plan for 2020-2024 included an action to increase car parking provision at Honeybourne station. This was identified as a priority as the station had limited car parking available and there was a significant impact on neighbouring residents. As a result of this ambition, the Council had purchased nearby land with the aim of constructing a 200-space car park north of Honeybourne station to enhance passenger access and alleviate nuisance parking in nearby residential areas. 3.2. Honeybourne station is a two-platform station situated between Moreton-in- Marsh and Evesham. Currently, access to the station is from Station Road. Platform 1 is directly accessible from the car park at ground level, while Platform 2 is reached via the existing stepped and ramped footbridge
3.3To access Platforms 1 and 2 from the proposed new car park, passengers would need to cross several tracks, the exact number depending on the location of any bridge solution. One track serves the Honeybourne Through Siding to Long Marston, with a spur into Honeybourne Up Yard. There is another track that may be utilised by the Gloucestershire Warwickshire Steam Railway (GWSR) in the future.
3.4Over the last 4 years discussions have been ongoing between the Council, Network Rail and GWR the current rail operator on the line. Initially, the aim was to have a level crossing across the less used track, but subsequent Rail Regulator risk assessments have deemed this route to be too dangerous, with the only alternative being of a similar price to a footbridge but with a potential risk that could be challenged at any time and closed down by the Regulator.
3.5Therefore, officers have worked with Network Rail to identify alternative access arrangements. All options would result in a footbridge being delivered.
3.6Prior to any works being commissioned a feasibility study would need to be carried out. Network Rail have a framework for projects known as PACE (Project Acceleration in a Controlled Environment). PACE has a number of stages and the options below are those proposed as available to the Council in relation to the project:
3.7Price and schedule to complete PACE1 ES2 (Foundational) Feasibility study - £80k. This will be a high-level approach. It is intended to provide the Council with an entry level cost option, to procure a high-level feasibility report that will provide a ‘Foundational’ level of feasibility understanding upon which further in-depth studies can build, should they be deemed necessary.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Honeybourne Station Viability StudyReport | 153 KB | DownloadRead as text |
Follow Executive Board at Wychavon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr... | Decided | Open |
| 16 Sep 2026 | Budget 2027/28Resolved That Executive Board Approves the budget timetable for the 2027/28 budget process, attached at Appendix A, i... | Approved | Open |
| 16 Sep 2026 | Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t... | Approved | Open |
| 16 Sep 2026 | Street Naming and NumberingResolved That the revised ‘ Policy’, as presented in Appendix 1, be adopted. | Approved | Open |
| 16 Sep 2026 | Street Naming and Numbering for Wychavon TownResolved That the street naming and numbering for the development of Wychavon Town, delineated by the allocation in t... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.