Capital Programme Outturn 2006/07 and Revisions to the 2007/08 Capital Programme
NotedExecutive3 papers
Executive - for meetings from 03/06/00 to 26/04/11 noted this item on Tuesday 26 June 2007. Below is the council's own wording, with the papers it was decided on.
(i) That the 2006/07 capital outturn position be noted and the requests for slippage to and from the 2007/08 capital programme be approved, with the addition that the carry forward for Neighbourhood Services be increased by £29,000; (ii) That the statutory declaration of the 2006/07 capital expenditure be approved, as required by the Local Government Act 2003 part 1. REASON:(i) To allow the continued effective management of the capital programme in 2007/08 and beyond; (ii) To fulfil its statutory function. (i) That the 2006/07 capital outturn position be noted and the requests for slippage to and from the 2007/08 capital programme be approved, with the addition that the carry forward for Neighbourhood Services be increased by £29,000; (ii) That the statutory declaration of the 2006/07 capital expenditure be approved, as required by the Local Government Act 2003 part 1. REASON:(i) To allow the continued effective management of the capital programme in 2007/08 and beyond; (ii) To fulfil its statutory function.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Executive - for meetings from 03/06/00 to 26/04/11
Executive 26th June 2007
Report of the Director of Resources
CAPITAL PROGRAMME OUTTURN 2006/07 AND REVISIONS TO THE 2007/08 PROGRAMME
Report Summary
1. The purpose of this report is to:
• Provide the Executive with the final outturn position of the capital programme for 2006/07 reflecting the capital outturn reports taken to Executive Member with Advisory Panel (EMAP) meetings for each department;
• Seek approval of the statutory declaration on the funding of the 2006/07 capital programme to show how the Councils expenditure has been financed, along with any financial implications this may result in;
• Highlight significant achievements from the Councils largest ever capital programme;
• Inform the Executive of any under or overspends and seek approval for any resulting changes to the programme;
• Inform the Executive of any slippage and seek approval for the associated funding to be slipped to or from the financial years to reflect this.
Summary of the 2006/07 Capital Programme 2. Capital expenditure in 2006/07 totalled £48.5m. This represents the largest ever capital programme delivered by the City of York Council and is a £8.3m (20.6%) increase on the 2005/06 outturn. Figure One illustrates the increase in capital programme size since 1999/00, during which time it has more than doubled from £19.5m to this years outturn of £48.5m. Capital Programme 1999/00 - 2006/07 60
City Strategy (Econ City Strategy (P&T) Devt) £19.252m £0.002m
Figure 2 Capital Outturn by Department 2006/07
4. Capital receipts raised during 2006/07 were also at a Council high of £31.5m, compared with £6.2m in 2005/06. The main contributors were the receipts from the sale of Foss Islands Depot (£10m), the sale of St Leonard’s Place (£7m) as part of a sale and lease back scheme, the sale of the Barbican (£6m), as well as the sale of Housing land and right to buy receipts (£4m). 5. The Council continues to be successful in attracting strong support from the government with funding for roads, schools, housing and leisure amounting to more than £25.3m (£22.4m in 2005/06).
6. Within the programme a number of significant schemes have been or are being delivered during 2006/07, some of the key achievements for the year are:
a. The completion of the £5.3m (£3.95m expenditure in 06/07) Huntington Secondary School extension and refurbishment scheme. A total of 8 temporary classrooms units have been replaced with the new build of 2,600 square meters of teaching and performing areas blocks. Both the teaching and performing arts blocks are now being used by both the school and the local community.
b. Works totalling £3.3m on New Deals for Schools (NDS) modernisation programmes has allowed schools to invest in buildings, grounds and ICT equipment enabling schools to improve their pupils’ educational standards. Specific schemes include:
• The £1m Canon Lee extension project is complete and operational with both the new science labs and drama studio in full use. • The £0.6m hall extension at Rufforth Primary School is complete and in full use by both the school and local community. • The £0.4m modernisation works at Scarcroft Primary are complete resulting in a new lift, refurbished toilets, entrance, reception and waiting areas and offices. • Construction of a £0.6m new classroom and community facility at Skelton Primary are complete and in full use.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Executive - for meetings from 03/06/00 to 26/04/11 at York and we tell you when its next papers are published, before the meeting rather than after it.
Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.