City of York Council
Executive, Wednesday 9 September 2026 at 4.30pm

Capital Programme - Monitor 1 2026/27 (4:46pm)

Noted Executive 3 papers

AI summaryCity of York Council Executive recommended a £5.008k cut and noted the revised 2026/27 capital budget of £107.982m, and added a Burnholme 3G pitch with £700k from the Football Foundation and £150k from council funds. It accepted that cost overruns need council funding. [D] [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedContracts authorised, overrun risk accepted [D]
Money£107.982m [D]Revised 2026/27 budget after a £5.008k reduction [D]
What happens nextSign agreements, enter contracts [D]Director of Finance signs grant agreements; council enters contracts [D]
Who it affectsCouncil and Burnholme area [D]Pitch delivery and funding risk [D]

What was decided

The Executive recommended adjustments that reduce the 2026/27 budget by £5.008k, noted the revised budget of £107.982m, and noted the restated capital programme for 2026/27 to 2029/30 set out in Annex 1. [D] Report P3

It noted the £700k Football Foundation grant for a new 3G pitch at Burnholme and delegated the Director of Finance to sign grant agreements with the Football Foundation and GLL for their contributions. [D]

It added the scheme to the capital programme with a £150k CYC contribution from s106 / leisure sinking fund, authorised the council to enter the framework partner agreements, construction contract and other required contract documents, and accepted that cost overruns will need council funding. [D]

Why

The overall programme changes enable effective management and monitoring of the council's capital programme. [D]

The Burnholme decision allows scheme funding to be accepted and delivery to progress under the council's Constitution and Financial Regulations. [D]

What happens next

The Director of Finance will sign the grant agreements with the Football Foundation and GLL. [D]

The council is authorised to enter the framework partner agreements, construction contract and other contract documents needed for delivery. [D]

The money

  • £107.982m Revised 2026/27 capital budget
  • £700k Football Foundation grant for a new 3G pitch at Burnholme
  • £150k CYC contribution from s106 / leisure sinking fund
  • £5.008k Reduction in the 2026/27 capital budget

Implications

  • Financial: Recommended adjustments reduce the 2026/27 budget by £5.008k, with a revised budget of £107.982m. [D]
  • Financial: The Burnholme scheme has a £700k Football Foundation grant and a £150k CYC contribution. [D]
  • Risk: The council accepted that scheme cost overruns will need to be funded by it. [D]
  • Legal: The council is authorised to enter the agreements, construction contract and other required contract documents. [D]
  • Legal: The Director of Finance is delegated to sign grant agreements with the Football Foundation and GLL. [D]
  • Other: The restated programme is intended to support effective management and monitoring. [D]

Who and where

  • City of York Council
  • Burnholme area
  • Football Foundation
  • GLL

Timeline

  • 27 January 2026: Executive paper on the Capital Budget 2026/27 to 2029/30. [P1] Report P1
  • 7 July 2026: Executive paper on the Capital Programme Outturn. [P1] Report P1
  • 2026-09-09: Executive decided the capital budget and Burnholme pitch matters. [D]
  • 2026/27: Revised capital budget and Burnholme scheme recorded. [D]
  • 2026/27 to 2029/30: Restated capital programme noted in Annex 1. [D]

Plain English for the jargon

  • CYC: City of York Council [P5]
  • GLL: Contributor named in the grant agreements [D]
  • s106: One stated source of the £150k council contribution [D]
  • leisure sinking fund: One stated source of the £150k council contribution [D]
  • 3G pitch: New pitch at Burnholme included in the capital programme [D]
  • framework partner agreements: Agreements the council approved entering for scheme delivery [D]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item28

Resolved

That the Executive: i. In relation to the overall programme: · Recommended to Council the adjustments resulting in a reduction in the 2026/27 budget of £5.008k as detailed in the report. · Noted the 2026/27 revised budget of £107.982m as set out in paragraph 9 and Table 2. · Noted the restated capital programme for 2026/27 – 2029/30 as set out in Annex 1. Reason: To enable the effective management and monitoring of the Council’s capital programme. ii. In relation to the investment at Burnholme : · Noted the award of grant from the Football Foundation of £700k for a new 3G pitch at Burnholme delegating the Director of Finance to sign the grant agreements with Football Foundation and GLL for their contributions · Agreed to adding the scheme to the capital programme with £150k CYC contribution from s106 / leisure sinking fund · Approved the Council to enter into the framework partner agreements, construction contract and other contract documents required to deliver the contract. · Accepted the risk that scheme cost overruns will need to be funded by the council. Reason: To ensure that scheme funding can be accepted and the scheme delivery can progress in line with the Council’s Constitution and Financial Regulations. That Executive: i) In relation to the overall programme: · Recommended to Council the adjustments resulting in a reduction in the 2026/27 budget of £5.008k as detailed in the report. · Noted the 2026/27 revised budget of £107.982m as set out in paragraph 9 and Table 2. · Noted the restated capital programme for 2026/27 – 2029/30 as set out in Annex 1. Reason: To enable the effective management and monitoring of the Council’s capital programme. ii) In relation to the investment at Burnholme : · Noted the award of grant from the Football Foundation of £700k for a new 3G pitch at Burnholme delegating the Director of Finance to sign the grant agreements with Football Foundation and GLL for their contributions · Agreed to adding the scheme to the capital programme with £150k CYC contribution from s106 / leisure sinking fund · Approved the Council to enter into the framework partner agreements, construction contract and other contract documents required to deliver the contract. · Accepted the risk that scheme cost overruns will need to be funded by the council. Reason: To ensure that scheme funding can be accepted and the scheme delivery can progress in line with the Council’s Constitution and Financial Regulations.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 31 pages

Meeting: Executive Meeting date: 9 September 2026 Report of: Director of Finance, Debbie Mitchell Portfolio of: Councillor Katie Lomas, Executive Member for Finance, Performance, Major Projects, Human Rights, Equalities and Inclusion

Capital Programme – Monitor 1 2026/27

Subject of Report 1. The purpose of this report is to set out the projected outturn position for 2026/27 including any under/overspends and adjustments, along with requests to re-profile budgets to/from current and future years.

2. The Capital Monitor report is one of a number of reports taken to Executive on a regular basis to provide details of expenditure and how that impacts the financial standing of the council.

Benefits and Challenges 3. The capital programme is key in delivering the Council Plan. Members are able to prioritise capital expenditure to deliver improvements across all service areas notably Schools, Housing, Transport and Regeneration as well as supporting Climate Change ambitions.

4. The programme does involve significant levels of council borrowing which impacts the level of revenue expenditure. The cost of delivering the capital programme is therefore dependent on levels of external funding, inflation levels and interests rates. Policy Basis for Decision

5. The Capital Budget is set as part of the Council’s budget setting in February 2026. The capital programme is set alongside decisions to deliver a balanced revenue position.

Financial Strategy Implications 6. The Finance and Performance Monitor 1 report elsewhere on this agenda again outlines the council’s financial position. The identification of slippage particularly in relation to Council funding will reduce council borrowing costs and support the annual revenue expenditure.

Recommendation and Reasons 7. Executive is asked to:

a) In relation to the overall programme:

 Recommend to Full Council the adjustments resulting in a reduction in the 2026/27 budget of £5.008k as detailed in the report.  Note the 2026/27 revised budget of £107.982m as set out in paragraph 9 and Table 2.  Note the restated capital programme for 2026/27 – 2029/30 as set out in Annex 1.

Reason: To enable the effective management and monitoring of the Council’s capital programme.

b) In relation to the investment at Burnholme:

 Note the award of grant from the Football Foundation of £700k for a new 3G pitch at Burnholme delegating the Director of Finance to sign the grant agreements with Football Foundation and GLL for their contributions  Agree to adding the scheme to the capital programme with £150k CYC contribution from s106 / leisure sinking fund  Approval to enter into the framework partner agreements, construction contract and other contract documents required to deliver the contract  Accept the risk that scheme cost overruns will need to be funded by the council

Reason: To ensure that scheme funding can be accepted and the scheme delivery can progress in line with the Council’s Constitution and Financial Regulations.

Background 8. The 2026/27 capital programme was approved by Council on 12 February 2026 and updated for amendments reported to Executive in the 2025/26 outturn report, which resulted in an approved capital budget for 2026/27 of £112.990m.

9. A decrease of £5.008m is detailed in this monitor resulting in a revised capital programme for 2026/27 of £107.982m. There is an increase of £2.954m due to additional funding being awarded / approved and a re-profiling of budgets to future years totalling £7.962m.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme: Monitor 1 2026/27 (4:46pm)Report 31 pages DownloadRead as text
PDF
Item 7: Capital Programme: Monitor 1 2026-27 Annex 1Appendix 3 pages Download
PDF
View item 28. as HTML 260 KBReport 260 KB Copy on its way

At this meeting

Whole meeting

Who was there

8 of 8 attended
CD
Councillor Claire DouglasChair, present
PK
Councillor Peter KilbaneCommittee Member, present
JK
Councillor Jenny KentCommittee Member, present
KL
Councillor Katie LomasCommittee Member, present
KR
Councillor Kate RaviliousCommittee Member, present
LS
Councillor Lucy Steels-WalshawCommittee Member, present
RW
Councillor Robert WebbVice-Chair, present
DM
Councillor Dave MerrettCommittee Member, present

On this subject at York

Search all
  1. Capital Programme - Monitor 1 2026/27 (4:46pm)This decision
  2. Capital Programme Monitor Update 2 Report (4:47pm)Noted
  3. Capital Programme Outturn 2025/26 and Revisions to the 2026/27 - 2029/30 ProgrammeApproved
  4. Recommendations of Executive in relation to the Capital Programme - Monitor 3 2025/26Approved
  5. Capital Programme - Monitor 3 2025/26Approved
  6. Capital Programme - Monitor Two 2025/26Approved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open