(i) That the £117k of adjustments made under delegated authority to the 2007/08 approved capital programme, as illustrated in Table 1, be noted; (ii) That the inclusion of £2.732m of additional funding to the 2007/08 to 2010/11 Capital Programme, as illustrated in paragraph 7 of the report, be approved; (iii) That the reprofiling of £2.360m from 2007/08 to future years, as summarised in paragraph 7 of the report, be approved; (iv) That the restated Capital Programme, summarised in Table 10 and as set out in details in Annex A of the report, be approved; (v) That the capital receipt projects for 2007/08 to 2010/11, as summarised in exempt Annex B, be noted. REASON: To enable the effective management and monitoring of the Council’s Capital Programme. (i) That the £117k of adjustments made under delegated authority to the 2007/08 approved capital programme, as illustrated in Table 1, be noted; (ii) That the inclusion of £2.732m of additional funding to the 2007/08 to 2010/11 Capital Programme, as illustrated in paragraph 7 of the report, be approved; (iii) That the reprofiling of £2.360m from 2007/08 to future years, as summarised in paragraph 7 of the report, be approved; (iv) That the restated Capital Programme, summarised in Table 10 and as set out in details in Annex A of the report, be approved; (v) That the capital receipt projects for 2007/08 to 2010/11, as summarised in exempt Annex B, be noted. REASON: To enable the effective management and monitoring of the Council’s Capital Programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Executive - for meetings from 03/06/00 to 26/04/11
Executive 9th October 2007
Report of the Director of Resources
CAPITAL PROGRAMME – MONITOR ONE
Report Summary 1. The purpose of this report is to:
• Inform Members of the likely outturn position of 2007/08 Capital Programme based on the spend profile and information to August 2007 reflecting the capital monitor one reports taken to Executive Member with Advisory Panel (EMAP) meetings for each department;
• Inform the Executive of any under or overspends and seek approval for any resulting changes to the programme;
• Inform the Executive of any slippage and seek approval for the associated funding to be slipped to or from the financial years to reflect this;
• To inform Members of the funding position of the capital programme, taking account of the current capital receipts forecasts for the four year capital programme.
2. The 2007/08 – 2010/11 capital programme was approved by Council on 21st February 2007. Since then a number of amendments have taken place as reported to the Executive in the 2006/07 Capital Outturn paper, urgency papers and under the scheme of delegation. These changes have resulted in a current approved capital programme for 2007/08 of £52.143m, financed by £38.674m of external funding, leaving a cost to the Council of £13.469m to be financed from capital receipts. Table 1 illustrates the movements from the start budget to the current approved position. Gross External Cost to Budget Funding CYC £m £m £m Original Budget Approved by Council 43.749 33.803 9.946 Slippage Carried Forward from 06/07 4.116 2.772 1.344 outturn report Additions from 06/07 outturn report 1.533 1.400 0.133 Additions as a result of Urgency 2.628 0.406 2.222 meetings / Exec Reports Adjustments made under Delegated 0.117 0.293 (0.176) Authority Current Approved Capital 52.143 38.674 13.469 Programme
Table 1 Current Approved Capital Programme
3. A number of significant changes to the 2007/08 capital programme have taken place since the 2006/07 Capital Outturn report, these briefly are: • Addition of £406k - City Strategy Capital Programme 2007/08 – Consolidated Report 16 July (see paragraph 13 for details) • Addition of £1.424m – Accommodation Project Update – Executive 24 July 07 (see paragraph 29 for details) • Addition of £798k – Children’s Centre Capital Programme Urgency Report – Urgency Committee 3 August 07 (see paragraph 12 for details)
Consultation 4. The capital programme was developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 21 February 2007. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals and associated capital receipt sales do follow a consultation process with local Councillors and residents in the locality of the individual schemes.
Summary of Key Issues 5. There is an increase of £25.7m in the 2008/09 capital programme, mainly because of the Council’s successful Building Schools for the Future pilot programme funding bid, which provides for a brand new replacement school at Joseph Rowntree Secondary School. This increases the 2008/09 programme to £73.6m, 40% more than this years anticipated outturn. 6. In year capital receipts, are forecast to be down against the target by £3.6m, although this is mainly because of timing issues with the majority of the slippage expected early in 2008/09. The impact of these delays is reduced by there being corresponding slippage on capital receipt funded schemes of £2.2m. The Council has £5.4m of capital receipt funding carried forward from the £27m raised in 2006/07. Therefore, despite the small anticipated delay in receipts the Council remains in a strong capital funding position.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Executive - for meetings from 03/06/00 to 26/04/11 at York and we tell you when its next papers are published, before the meeting rather than after it.
Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.