Advice of the Advisory Panel That the Executive Member be advised to: · Note the updates to schemes as detailed in the report. · Agree the scheme reprofiling and slippage reported in the report and summarised in Annex 1. · Approve the revised capital programme as set out in Annex 1. Decision of the Executive Member
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Leisure, Culture and Social Inclusion and Advisory Panel
Executive Member for Leisure and Culture and Advisory Panel 4 December 2007
Report of the Director of Learning Culture and Children’s Services and the Director of Resources
CAPITAL PROGRAMME MONITORING 2007/08 - REPORT 2 Summary 1 This report is to: • inform Members of the likely out-turn position of the 2007/08 Capital Programme based on the spend profile and information to the end of October 2007. • advise Members of changes to existing schemes to allow the more effective management and monitoring of the Capital Programme. • inform Members of any new schemes and seek approval for their addition to the Capital Programme.
Background 2 The original capital programme for the financial year 2007/08 was approved at Council on 21 February 2007. A number of amendments were then approved as part of the 2006/07 outturn report and at the first monitor. This has resulted in a current approved Leisure & Culture Capital Programme for 2007/08 which shows gross capital expenditure of £3.001m, with £0.911m of other funding which gives a net capital programme cost of £2.090m. The table below details the approved changes to the 2007/08 capital programme since the original programme was approved in March 2007.
Gross Other Net Spend Funding Spend £m £m £m Original Capital Programme 2007/08 4.477 0.825 3.652 Slippage and Adjustments from the 2006/07 0.115 0.077 0.038 Outturn report Monitor 1 Adjustments (1.591) 0.009 (1.600)
Current Approved Capital Programme 2007/08 3.001 0.911 2.090
Consultation 3 Not applicable Options and Analysis
2007/08 Scheme Updates 4 Each major scheme in the capital programme has been reviewed to provide an assessment of its current status. Annex A shows the current approved capital programme and the projected outturn position for 2007/08, together with any slippage that is required into future financial years. Updates are only provided for significant schemes, with progress and variations explained in the following paragraphs.
York Pools and Indoor Sports Provision (Overall Scheme Cost £9.564m) 5 The separate schemes within the overall Pools programme reflect the amendments which were approved by the Executive on 23rd October 2007, with the balance of the procurement and legal fees budget, and part of the contingency budget being transferred into the Oaklands and Yearsley Pool budgets. In addition, a further £105k of prudential borrowing was approved and added to the budget for the Sports Centre on the York High site.
6 The scheme to undertake repairs at Yearsley Pool has been completed successfully and the pool has now reopened. The additional funding transferred from the procurement and contingency budgets needs to be brought forward into 2007/08 from 2008/09.
7 The new Swimming Pool development on the York High site is progressing through the detailed design stage with building work expected to be carried out in 2008. However, the estimated completion date has now been revised to June 2009, meaning that part of the budget in 2008/09 needs to be slipped back to 2009/10. In addition, fee expenditure has been incurred earlier than expected, requiring £50k of reverse slippage into 2007/08.
8 An amount of £200k was earmarked for the provision of community facilities for users displaced following the closure of the Barbican. This is currently in the 2007/08 programme but now needs to be slipped into 2008/09, as this is the earliest that this will be required.
Museum Service Heritage Lottery Bid (Scheme Cost £1.900m) 9 The amount of £600k in the programme for 2007/08 now takes account of an amendment made to the profiling of the capital scheme which was approved at Leisure and Culture EMAP on 19th October 2007. This report requested that a further £200k be brought forward into 2007/08 from later years of the scheduled programme in order to fund urgent repairs to the roof of the south gallery of the Art Gallery.
10 As reported at monitor 1 the remaining contribution of £400k will support works to the Castle Museum and the Hospitium.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Leisure, Culture and Social Inclusion and Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
Explore York - Library Learning Centre.Advice of the Advisory Panel That the Executive Member be advised to: (i) Agree to the budget subject to the approval...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.