Highway Maintenance, Advanced Design on Programmes for 2008-2009

Noted Committee 1 paper

City Strategy and Advisory Panel noted this item on Monday 14 January 2008. Below is the council's own wording, with the papers it was decided on.

Item88

Resolved

Advice of the Advisory Panel That the Executive Member for City Strategy be advised to : (i) Note the results of the June and October 2007 condition surveys on the city’s roads and footways; (ii) Approve the split in funding between footways and roads on a 50/50 basis; (iii) Approve the provisional programme of work listed in Annexes 3 – 12 of this report. Decision of the Executive Member for City Strategy RESOLVED :That the advice of the Advisory Panel be accepted and endorsed. REASON : To ensure the Highway Maintenance budget is expended in the most cost effective way based on the Council’s assessed priorities and approved policies.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to City Strategy and Advisory Panel

Meeting of Executive Members for City 14 January 2008 Strategy and Advisory Panel Report of the Director of City Strategy

HIGHWAY MAINTENANCE, ADVANCED DESIGN ON PROGRAMMES FOR 2008-2009

Summary 1. This report discusses how the provisional highway maintenance surfaces programmes have been prepared. It recommends and seeks approval to begin advanced design for a list of schemes in each category of work.

Background 2. By Members agreeing a programme early we can begin to carry out advanced design of some of the schemes and minimise any delay at the start of the year in implementing same. This has proved very successful over the last ten years and this report proposes to continue with these arrangements.

Surveys 3. In order to produce the programmes of highway works for the next year information is drawn from a number of surveys which are carried out throughout the year.

• Visual safety survey of all our roads and footways.

• Detailed condition survey of all our roads and footways.

• United Kingdom Pavement Management System (UKPMS) visual and machine surveys of all roads and approximately 22% of the highway, footway network.

4. In June 2007 we again carried out a full coarse visual condition survey of all our roads and footways. This allows us to grade them into three categories, grade 1 (good), grade 2 (average), and grade 3 (poor). By comparing with previous year's survey results the survey tells us whether the condition of the city's infrastructure is improving or deteriorating and identifies those streets which need to be looked at more closely with regards to a future resurfacing scheme. The results of the 2007 visual survey of the highway network are shown in Annex 1. Comments on trends for each category of road and footway are shown in Annex 2 and a full copy of the survey results is available in the Members library and will also be available at the meeting. It is intended to continue this survey next year in order that we can continue to monitor trends in improvement and deterioration and as an aid to identifying which streets should be resurfaced.

5. In October and November of 2007 a detailed condition survey was undertaken of all the following highways.

• Streets listed in our Local Transport Plan (LTP) 5 year programme of structural maintenance

• Streets identified as grade 3 by June 2007 survey

• Streets where the UKPMS survey showed that sections of them breached national intervention levels

• Requests by Members

• Requests by customers

• Recommendations of the Council's Safety and Area Highway Reactive Inspectors along with other officers of the Council.

6. Each road and footway is assessed and given a condition rating (score) based on engineering criteria and experience, with a treatment solution determined. The detailed condition survey was compiled into a listing, a copy of which will be available at the meeting.

7. To compliment all those other surveys and also identify areas for treatment, machine surveys to identify the skid resistance value of all principal roads are undertaken on an annual basis to produce a three year rolling average to identify the pavement resistance to skidding.

8. With all this condition information we are in a better position to identify where we should direct our maintenance activities and develop the programmes of work.

Programme Development 9. When considering roads and footways for inclusion in the programmes we have to consider a number of issues. These are:-

• The standards to be adopted

• The priorities for selection

• The approach to take

• The choices to be made

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highway Maintenance, Advanced Design on Programmes for 2008-2009Report 88 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
SG
Councillor Steve GallowayCabinet Member, present
AR
Councillor Ann Reid MBECabinet Member, present
IG
Councillor Ian GilliesChair, present
AD
Councillor Andy D'AgorneVice-Chair, present
RC
Councillor Richard CreganCommittee Member, present
KH
Councillor Keith HymanCommittee Member, present
DS
Councillor David ScottCommittee Member, present
TS
Councillor Tracey Simpson-LaingCommittee Member, present

On this subject at York

Search all
  1. Highway Maintenance, Advanced Design on Programmes for 2008-2009This decision
  2. Highways Maintenance, Capital Programme & Major Development Highways Impacts Update, Scheduling & Planning Report [19.13]Decided
  3. Highway Maintenance Delivery Report for 2017/18Noted
  4. Highway Maintenance, Advance Programme for 2015-16Agreed
  5. Annual Highway Maintenance ReportNoted
  6. Annual Highway Maintenance ReportNoted

More from York City Strategy and Advisory Panel

All decisions
MeetingDecisionOutcome
16 Mar 2009 MinutesThat the minutes of the last meeting of the Panel held on 27 January 2009 be approved and signed by the Chair and Exe... Approved Open
16 Mar 2009 Core Funding to Voluntary Organisations 2009/10Advice of the Advisory Panel That the Executive Leader be advised to: (i) Maintain the existing grant funding agreeme... Agreed Open
16 Mar 2009 Chief Executive's Monitor 3 Finance & Performance Report 2008/09Advice of the Advisory Panel The Advisory Panel advises the Executive Leader to note the financial and performance po... Noted Open
16 Mar 2009 2008/09 Third Monitoring Report Economic Development and Partnerships - Finance & PerformanceAdvice of the Advisory Panel The Advisory Panel advises the Executive Leader to note the financial and performance po... Noted Open
16 Mar 2009 City Strategy Capital Programme - Monitor 3 ReportAdvice of the Advisory Panel That the Advisory Panel advise the Executive Member for City Strategy to: (i) Approve th... Approved Open