Members considered a report which provided information on how the £200k, allocated in 2008/09 for the survey and repair of drainage systems would be spent. Officers were to gather information on highway standing water problems from a variety of sources, to identify the locations most in need of treatment and to arrange for a programme of repair works to be carried out. Advice of the Advisory Panel That the Advisory Panel advise the Executive Member for City Strategy to approve the proposal in this report to enable the survey and repair works, to assist in alleviating localised highway flooding and standing water problems in 2008/09, to be completed. Decision of the Executive Member for City Strategy
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Meeting of Executive Members for 2 June 2008 City Strategy and Advisory Panel Report of the Director of City Strategy
HIGHWAY DRAINAGE – SURVEY AND REPAIR
Summary 1. This report provides information to demonstrate how the £200k, allocated in 2008/09 for the survey and repair of drainage systems, will be spent. The intention is to gather information about highway standing water problems from a variety of sources, to identify the locations most in need of treatment and to arrange for a programme of repair works to be carried out.
Background 2. Flooding events in June 2007 have highlighted the relatively poor quality of information about the extent and condition of our drainage asset. Current revenue budgets for maintaining the extensive highway surface water drainage system are not sufficient to enable the desired level of routine maintenance to be carried out with most of the work, other than gully emptying, being done on a reactive basis.
3. A comprehensive report on the Drainage in York was presented to the Meeting of the Executive Members for City Strategy and Advisory Panel on 10 December 2007. This report indicated the possibility of a growth bid of £200k to carry out highway drainage survey and repair works.
4. This bid was approved and as shown in the Annual Highway Maintenance Report in March 2008, an additional £200k has been allocated in 2008/09 to enable some of the most persistent and troublesome highway drainage problems to be dealt with. Some of the money will be spent on survey and data recording but the majority will go on repair and rectification of problems. This funding is in addition to the £139,700 being made available in the capital drainage programme for 2008/09.
Proposals Survey Initiative 2008/09
5. The way in which the survey element will be carried out, to assist in the removal of many persistent drainage problems, is as follows. Information analysis
• Analyse all relevant existing customer data • Obtain information from Ward Members about their priorities for improving standing water and flooding issues • Gather information from highway inspectors and others about persistent problems • Consolidate all the data into a single database • Use all the above information to assess the high priority drainage problems and where necessary carry out site surveys if there is also a lack of asset data • Attempt to locate as much information as possible about existing drainage information records from Yorkshire Water and various council sources and plot onto Exor for safe keeping
6. To date, information about flooding and drainage problems has been gathered from existing databases as well as from the reports from Ward Members. Ward Members have already provided a list of 70 locations where some form of action would be beneficial. A consolidated database, excluding any duplication, will soon be prepared but this is expected to have over 1,000 entries. Bearing in mind the size of this database and the amount of funding available, a desktop exercise will be used to apply prioritisation criteria to identify those locations most in need of some form of improvement. Any on- site survey works and/or design works required will then be undertaken prior to establishing a programme of works.
7. It may be that in some locations the survey work carried out identifies a need for large scale renewals of existing drainage systems or installation of new systems. This is likely to be outside the scope of the funding in this instance and any such work will have to be considered for inclusion in the capital drainage programme.
Assessment of drainage priorities
8. The proposed criteria to be used to determine priorities for more detailed investigation prior to repair are:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.