2007/08 City Strategy Capital Programme: Outturn Report

Decided Committee 2 papers

City Strategy and Advisory Panel decided this item on Monday 2 June 2008. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

Consideration was given to a report which set out progress on schemes in the City Strategy Capital Programme during the 2007/08 financial year. This included the outturn report for 2007/08 and reports on budget spend to the end of March 2008. The outturn for the 2007/08 Capital Programme was £8,872k, an underspend of £662k against the budget. This represents an underspend of approximately 7% against the budget, which is principally due to the Council’s £500k contribution to the Highways Agency Hopgrove Roundabout Improvement scheme not being needed in 2007/08. It is proposed to carry over the following schemes from 2007/08 with funds into 2008/09. It was reported that proposals for the funding of the completion of other schemes would be made in the consolidated report to Members in July. Proposed Carry Overs to 2008/09 Schemes £000 A1237 Northern Bypass (Monks Cross Roundabout) - Resurfacing 60.0 Harrogate Road (part) - Resurfacing 57.0 Manor Lane (part) - Resurfacing 34.0 Hamilton Drive East/Hamilton Drive - Resurfacing 64.0 Selby Road Drainage Scheme 20.0 City Walls 18.0 Total £253
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to City Strategy and Advisory Panel

Meeting of Executive Members for City 2 June 2008 Strategy and Advisory Panel Report of the Director of City Strategy

2007/08 CITY STRATEGY CAPITAL PROGRAMME: OUTTURN REPORT

Summary 1. The purpose of this report is to set out progress on schemes in the City Strategy Capital Programme during the financial year 2007/08. It is the outturn report for 2007/08 and reports on budget spend to the end of March 2008.

Background 2. The City Strategy Capital Programme budget for 2007/08 was agreed by the Executive Member in March 2007. The programme was finalised on 16 July 2007 when the Executive Member was presented with the consolidated Capital Programme for 2007/08, which included all work that had been carried over from 2006/07.

3. Following amendments to the programme at the second monitoring report in December, the current approved budget for the City Strategy Capital Programme for 2007/08 is £9,534k.

4. The outturn for the 2007/08 Capital Programme was £8,872k, an underspend of £662k against the budget. This represents an underspend of approximately 7% against the budget, which is principally due to the Council’s £500k contribution to the Highways Agency Hopgrove Roundabout Improvement scheme not being needed in 2007/08.

5. During 2007/08, 52 schemes were completed, works were ongoing on a further 39 schemes, and feasibility work was being progressed on 21 schemes at the end of March. Over 515m of off road cycle route was constructed, 5.9km of carriageway resurfaced and 9km of footway rebuilt during the year.

6. There has been a substantial amount of work delivered in the year including the following larger schemes: A new roundabout at the junctions of Moor Lane, Askham Lane and Askham Bryan Lane with the Outer Ring Road was constructed, which will improve accessibility and reduce the likelihood of high speed collisions at that location. Improvements were made to the Strensall Road Roundabout to reduce journey times for buses travelling from Strensall. A right turn lane and cycle crossing facilities were constructed at the Murton Lane junction with the A166 to improve safety. Phase 1 of the Heslington Lane Cycle Route was opened, and a new cycle route along Hull Road to provide a safer route to Archbishop Holgate’s School was completed. Details of the many other smaller schemes which were delivered in the year are provided in the report.

7. The structural maintenance allocation was used to resurface 15 roads and reconstruct 20 footways across the city. An increased allocation for the City Walls structural maintenance was used to reconstruct the roof of Robin Hoods Tower and undertake other repairs.

City Strategy Capital Programme 8. Progress on the major elements of the programme is set out in more detail in the following sections. Schemes that are funded from the Local Transport Plan are considered first, followed by schemes funded from other sources.

9. A scheme by scheme review of the progress is set out in Annex 1, which shows the scheme status at the end of March 2008. Progress on schemes since the end of the financial year is also shown where appropriate.

Schemes Within the Local Transport Plan OUTER RING ROAD AND JAMES ST LINK ROAD Programme: £4,093k (£3,550k LTP, £543k s106) Outturn at 31 March 2008: £3,874k

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2007/08 City Strategy Capital Programme: Outturn ReportReport 116 KB DownloadRead as text
PDF
Appendix 1Appendix 1 66 KB Download

At this meeting

Whole meeting

Who was there

7 of 8 attended
SG
Councillor Steve GallowayCommittee Member, present
IG
Councillor Ian GilliesChair, present
AD
Councillor Andy D'AgorneVice-Chair, present
RC
Councillor Richard CreganCommittee Member, apologies
KH
Councillor Keith HymanCommittee Member, present
RP
Councillor Ruth PotterCommittee Member, present
DS
Councillor David ScottCommittee Member, present
AW
Councillor Andrew WallerCommittee Member, present

On this subject at York

Search all
  1. 2007/08 City Strategy Capital Programme: Outturn ReportThis decision
  2. A City that Works for All: York's All-age Autism and ADHD Strategy 2025-2030Approved
  3. North Yorkshire and City of York Domestic Abuse Strategy 2024-2028 (10:07)Approved
  4. City of York Council Actions in Response to the York Anti-Racism and Inclusion Strategy (18:03)Approved
  5. City of York Council - Human Rights City Commitment Strategy (10:26 am)Agreed
  6. A refreshed all-age Autism Strategy for the City (5:32pm)Decided

More from York City Strategy and Advisory Panel

All decisions
MeetingDecisionOutcome
16 Mar 2009 MinutesThat the minutes of the last meeting of the Panel held on 27 January 2009 be approved and signed by the Chair and Exe... Approved Open
16 Mar 2009 Core Funding to Voluntary Organisations 2009/10Advice of the Advisory Panel That the Executive Leader be advised to: (i) Maintain the existing grant funding agreeme... Agreed Open
16 Mar 2009 Chief Executive's Monitor 3 Finance & Performance Report 2008/09Advice of the Advisory Panel The Advisory Panel advises the Executive Leader to note the financial and performance po... Noted Open
16 Mar 2009 2008/09 Third Monitoring Report Economic Development and Partnerships - Finance & PerformanceAdvice of the Advisory Panel The Advisory Panel advises the Executive Leader to note the financial and performance po... Noted Open
16 Mar 2009 City Strategy Capital Programme - Monitor 3 ReportAdvice of the Advisory Panel That the Advisory Panel advise the Executive Member for City Strategy to: (i) Approve th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies