Members considered this report which presented two sets of data from the City Strategy Directorate: a) the outturn figures for revenue expenditure and capital expenditure for the City Strategy portfolio, b) outturn (2007/08) performance against target for a number of key indicators that are made up of: · Best Value Performance Indicators owned by City Strategy · Customer First targets (letter answering and telephone calls) · Staff Management Targets (sickness absence) It was reported that the overall outturn position showed a provisional £-49 underspend. A carry forward request for the waste project work that had not been completed at 31 March totalling £31k. If the request was approved the overall overspend within the City Strategy portfolio to support council reserves totalled £18k. The budget carry forward request was in order to complete projects for which funding had been set aside in 2007/08 but which were unable to be completed within the year. Waste PFI York has joined up with its neighbouring authorities to find a long-term solution to deal with waste. Slight delays in the project means that some of the work which will need to be carried out has been deferred to 2008/09. Total Requested Carry Forwards £’000 £31k Advice of the Advisory Panel That the Advisory Panel advise the Executive Member for City Strategy to approve the financial and performance position of the portfolio and the carry forward request of £31k set out in paragraph 55, subject to the approval of the Executive. Decision of the Executive Member for City Strategy
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1 This report presents two sets of data from the City Strategy Directorate
a) the outturn figures for revenue expenditure and capital expenditure for the City Strategy portfolio, b) outturn (2007/08) performance against target for a number of key indicators that are made up of: • Best Value Performance Indicators owned by City Strategy • Customer First targets (letter answering and telephone calls) • Staff Management Targets (sickness absence)
Background
2 The Executive Member has received two monitoring reports during the year and has been kept informed of expenditure and income trends for the portfolio. It should be noted that the figures reported are provisional and may be adjusted. However any changes are likely to be of a technical accounting nature and not significant in terms of impacting on the variances described in the report.
3 The performance data included is reported as part of the Council plan each year.
Management Summary
Financial Overview
4 The provisional revenue outturn for the City Strategy portfolio was £14,723k against a budget of £14,772k a gross underspend against budgets of £-49k and represents 0.1% compared to the portfolio’s gross budget. The overall position is summarised below £000 Latest Budget 14,772 Provisional Outturn 14,723 Gross Underspend -49
Carry Forward request 31
Revised Underspend -18
% Of Latest Gross Budget -0.1%
nd th 5 The 2 Monitor report was presented to Members on 10 December 2007 and showed a projected outturn of £14,481k compared to a budget of £14,428k, a net overspend of £+53k. This position assumed a supplementary estimate of £200k would be provided by the Executive to support the ongoing concessionary fares overspend.
The outturn position by service plan is shown below
Expend Income Net Projected Budget Budget Budget Outturn Var’n % of £000 £000 £000 £000 £000 gross exp City Development & Transport 25,993 12,388 13,605 13,520 -85 -0.3
Planning 3,955 2,867 1,088 1,310 +222 +5.6
Resource & Business Mgt 4,334 4,255 79 -107 -186 -4.3
TOTAL CITY STRATEGY 34,282 19,510 14,772 14,723 -49 -0.2
Note: ‘+’ indicates an increase in expenditure or shortfall in income ‘-‘ indicates a reduction in expenditure or increase in income
6 The overall outturn position shows a provisional £-49k underspend. Details of the major variances are shown in the sections below whilst overall budget summary is shown in detail in Annex 1.
7 There is a carry forward request for the waste project work that has not been completed at 31st March totalling £31k. This is detailed in paragraph 55. If this request is approved the overall underspend within the City Strategy portfolio to support council reserves totals £18k.
Performance Overview
8 There are some marked improvements in service performance compared to 2006/07, particularly in relation to:
• BVPI 106: The percentage of new homes built on previously developed land.
• BVPI 165: Percentage of pedestrian crossings with facilities for disabled people
• all enquiries at reception are dealt with within 10 minutes, and this has consistently been the case since 2002/03.
9 Key areas where the directorate did not meet the target:
• BVPI 215a: The average time taken to repair a street lighting fault where the response time is under the control of the local authority.
• BVPI 99ai: The number of people killed or seriously injured in road traffic collisions.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.