Members were presented with a number of amendments to the capital programme for approval, which were required to ensure that the schemes were deliverable within funding constraints whilst enabling the objectives of the approved Local Transport Plan to be met. Advice of the Advisory Panel That the Executive Member for City Strategy be advised to approve (i) The carryover schemes and adjustments set out in Annexes 1 and 2 of the report; (ii) The increase to the 2008/09 City Strategy capital budget subject to the approval of the Executive Decision of the Executive Member for City Strategy
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Meeting of Executive Members for City 14 July 2008 Strategy and Advisory Panel Report of the Director of City Strategy
CITY STRATEGY CAPITAL PROGRAMME 2008/09 – CONSOLIDATED REPORT
Summary 1. The purpose of this report is to consolidate the 2008/09 City Strategy Capital Programme to include the carryover schemes that were not completed in 2007/08, and to make adjustments to schemes and blocks to reflect individual underspends and overspends within the programme. The report asks the Executive Member for City Strategy to approve the amendments to the 2008/09 budget as set out below.
Background 2. The City Strategy Capital Programme budget for 2008/09 of £7,943k was agreed by the Executive Member in March 2008, and includes the Local Transport Plan (LTP) capital programme allocation of £5,897k, and other elements allocated funds through the Council’s budget process. These figures do not include overprogramming, which was set at £812k in the 2008/09 budget report.
3. The 2007/08 City Strategy Capital Programme contained a level of overprogramming of £353k at the consolidated report stage to give some flexibility to the programme should slippage in some schemes occur. Following minor revisions at the Monitor 1 stage, the full programme agreed by Members at the Monitor 2 report in December 2007 was £9,967k, with a budget of £9,534k. There was therefore £433k of work outstanding that could not have been funded by the LTP in 2007/08.
4. For this reason it was necessary when planning the 2008/09 programme in early 2008 to take account of schemes that were expected to slip from 2007/08.
5. As reported to Members in June, the outturn for the 2007/08 capital programme was £8,872k, an underspend of £662k against the budget. £253k of the underspend was slippage of City Council funded structural maintenance schemes which could not be completed by the end of the year. The remainder, £409k, was for schemes funded from developer contributions, which is held in a separate account for future use on the designated schemes. 6. The carryover and new schemes that have been added to the 2008/09 budget are detailed below, along with budget alterations for existing schemes where changes to the scheme cost have been identified. It is proposed to fund schemes by using the carried over funds from 2007/08 or by increasing the level of overprogramming.
7. The key changes included in this report are summarised in Annex 1, and the current and proposed budgets for each scheme are shown in Annex 2.
City Strategy Capital Programme Integrated Transport
8. Access York Park & Ride Major Scheme Bid (AY01/08). Following the approval of the council’s bid for the provision of three new Park & Ride sites and improvements to the A59/A1237 roundabout at the Regional Transport Board meeting in April, work is ongoing to prepare a Major Scheme Bid to be submitted to the Department for Transport in the autumn. The preparatory stages of Phase 1 and 2 of the Access York Bid (P&R and Outer Ring Road) are being funded from the revenue budget using £164k approved at 22 April Executive. It is proposed to allocate £400k in the capital programme in order to progress the preliminary design and planning application stages of the Park & Ride Bid. Details of the programme and resourcing for the Park & Ride Bid will be provided to Members in a report to the Executive on 29 July.
9. Fulford Road Multi-Modal Scheme (Phase 1) (PT04/06) - £850k. Following a review of the delivery programme for the works along Fulford Road, it is proposed to reduce the allocation in 2008/09 by £200k to match the extent of the works deliverable within the year.
10. P&R City Centre Bus Stop Upgrades (PR02/07) and P&R Site Upgrades (PR03/07) - £100k. It is proposed to allocate £50k of additional funds to enable additional works to be undertaken in advance of the launch of the new service.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.