Leisure, Culture and Social Inclusion and Advisory Panel noted this item on Tuesday 2 September 2008. Below is the council's own wording, with the papers it was decided on.
Advice of the Advisory Panel That the Executive Member be advised to: (i) Note the updates to scheme as detailed in the report (ii) Agree the scheme amendments and additions reported and summarised in Annex A (iii) Approve the revised capital programme as set out in Annex A (iv) Agree to continue to seek ways to implement a scheme to refresh the landscaping of the War Memorial Gardens in the future and in the meanwhile (a) Transfer the £10k into the Parks S106 Development Fund for use on a suitable scheme within the Micklegate/Holgate area with a particular steer towards refurbishment of the toilet facilities in Westbank Park (b) Seek additional funding sources for the War Memorial Gardens scheme, including through the 2009/10 CRAM process. Decision of the Executive Member
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Leisure, Culture and Social Inclusion and Advisory Panel
Executive Member for Leisure, Culture and Social Inclusion, 2nd September 2008 and Advisory Panel
Report of the Director of Learning Culture and Children’s Services and the Director of Resources
CAPITAL PROGRAMME MONITORING 2008/09 - MONITOR 1 Summary 1 This report is to: • inform Members of the likely out-turn position of the 2008/09 Capital Programme based on the spend profile and information to the end of July 2008. • advise Members of changes to existing schemes to allow the more effective management and monitoring of the Capital Programme. • inform Members of any new schemes and seek approval for their addition to the Capital Programme.
Background 2 The original capital programme for the financial year 2008/09 was approved at Council on 21 February 2008. A number of amendments were then approved as part of the 2007/08 outturn report. This has resulted in a current approved Leisure & Culture Capital Programme for 2008/09 which shows gross capital expenditure of £5.643m, with £1.908m of other funding which gives a net capital programme cost of £3.735m. The table below details the approved changes to the 2008/09 capital programme since the original programme was approved in February 2008.
Gross Other Net Spend Funding Spend £m £m £m Original Capital Programme 2008/09 6.943 1.884 5.059 Slippage and Adjustments from the 2007/08 (1.555) 0.024 (1.579) Outturn report
Current Approved Capital Programme 2008/09 5.388 1.908 3.480
Consultation 3 Not applicable Options and Analysis
2008/09 Scheme Updates 4 Each major scheme in the capital programme has been reviewed to provide an assessment of its current status. Annex A shows the current approved capital programme and the projected outturn position for 2008/09, together with any slippage that is required into future financial years. Updates are only provided for significant schemes, with progress and variations explained in the following paragraphs.
York Pools and Indoor Sports Provision (£10.140m) 5 Work has now commenced on building the new pool on the York High site. However, the project board have identified the need to increase the contingency by £53k as there are a number of items within the programme which have been identified as at increased risk of exceeding current budget provision. It is proposed to transfer the £19k balance within the Pools Contingency to this scheme. The remaining £34k will be covered by a combination of £10k from York High School (which is being provided as a contribution towards the enhanced PE accommodation), and the remaining £24k by making a contribution from the pools repair and maintenance revenue budget (£12k in each of the years 2008/09 and 2009/10).
6 A report was presented to the EMAP meeting on 15th July 2008 setting out proposals for the use of the £200k in the capital programme which was set aside for investment in community facilities. It was agreed that a grant of £175k be given to the Melbourne Centre and a grant of £25k be given to Space 109. These amounts are currently in the programme for 2008/09.
Museum Service Heritage Lottery Bid (£1.900m) 7 There is a amount of £400k in the programme for 2008/09 to support three specific elements under the rolling programme of investment in the Museums Trust. Of this £400k, an amount of £200k has already been paid to the Trust to support work at the Art Gallery. A further £100k has been earmarked for work at the Castle Museum and is likely to be paid to the Trust shortly. The remaining £100k is set aside to fund work at the Yorkshire Museum. The release of this funding is dependent on plans for the Cultural Quarter.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Leisure, Culture and Social Inclusion and Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
Explore York - Library Learning Centre.Advice of the Advisory Panel That the Executive Member be advised to: (i) Agree to the budget subject to the approval...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.