Executive - for meetings from 03/06/00 to 26/04/11 approved this item on Tuesday 7 October 2008. Below is the council's own wording, with the papers it was decided on.
(i) That the revised 2008/09 budget of £63.930m, as set out in paragraph 6 of the report (Table 2) be approved. (ii) That the net slippage of £12.248m into future years, and the additions of £217k in 08/09, £4.424m in 09/10 and £203k in 10/11 be approved. (iii) That the re-stated capital programme for 2008/09 to 2010/11, as set out in paragraph 24 (Table 11) and detailed in Annex A, be approved. (iv) That the capital receipt projections for 2008/09 to 2010/11, as summarised in paragraph 26 (Table 12) and set out in (exempt) Annex B, be noted. (v) That the use of the re-classified PFI funds to overcome the early years shortfall in funding be noted. REASON: To enable the effective management and monitoring of the Council’s capital programme. (i) That the revised 2008/09 budget of £63.930m, as set out in paragraph 6 of the report (Table 2) be approved. 1 (ii) That the net slippage of £12.248m into future years, and the additions of £217k in 08/09, £4.424m in 09/10 and £203k in 10/11 be approved. 2 (iii) That the re-stated capital programme for 2008/09 to 2010/11, as set out in paragraph 24 (Table 11) and detailed in Annex A, be approved. 3 (iv) That the capital receipt projections for 2008/09 to 2010/11, as summarised in paragraph 26 (Table 12) and set out in (exempt) Annex B, be noted. (v) That the use of the re-classified PFI funds to overcome the early years shortfall in funding be noted. REASON: To enable the effective management and monitoring of the Council’s capital programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Executive - for meetings from 03/06/00 to 26/04/11
Executive 7 October 2008
Report of the Director of Resources
CAPITAL PROGRAMME – MONITOR ONE
Report Summary 1. The purpose of this report is to:
• Inform Members of the likely outturn position of 2008/09 Capital Programme based on the spend profile and information to August 2008 reflecting the capital monitor one reports taken to Executive Member with Advisory Panel (EMAP) meetings for each department;
• Inform the Executive of any under or overspends and seek approval for any resulting changes to the programme;
• Inform the Executive of any slippage and seek approval for the associated funding to be slipped to or from the financial years to reflect this;
• To inform Members of the funding position of the capital programme, taking account of the current capital receipts forecasts for the three year capital programme.
2. The 2008/09 – 2010/11 capital programme was approved by Council on 21st February 2008. Since then a number of amendments have taken place as reported to the Executive in the 2007/08 Capital Outturn paper. These changes have resulted in a current approved capital programme for 2008/09 of £75.942m, financed by £52.375m of external funding, leaving a cost to the Council of £23.567m to be financed from capital receipts. Table 1 illustrates the movements from the start budget to the current approved position. Gross External Cost to Budget Funding CYC £m £m £m Original Budget Approved by Council at 86.152 63.087 23.065 21 Feb 2008 Slippage Carried Forward to 09/10 & (10.997) (11.526) 0.529 10/11 from 07/08 outturn report Additions from 07/08 outturn report 0.787 0.814 (0.027)
Current Approved Capital 75.942 52.375 23.567 Programme Table 1 Current Approved Capital Programme
Consultation 3. The capital programme was developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 21 February 2008. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals and associated capital receipt sales do follow a consultation process with local Councillors and residents in the locality of the individual schemes.
Summary of Key Issues 4. There is an overall decrease of £12.012m in the 2008/09 capital programme, mainly because of the delays encountered with regard to the Administrative Accommodation project. This results in a revised capital programme budget of £63.930m, £21.905m higher than 2007/08 capital outturn.
5. In year capital receipts, are forecast to be down against the target by £3.983m, this is primarily because of timing issues with the majority of the slippage expected early in 2009/10. It should however be noted that a significant single capital receipt is currently projecting to under achieve its budgeted disposal value of £1.2m. This underachievement along with other minor variations leaves the Council in a weak capital funding position prior to applying the reclassified PFI funds.
6. Against the current approved budget of £75.942m, there is a predicted outturn of £63.930, a net decrease of £12.012m made up of: • Additional schemes costing £218k. • The re-profiling of budgets from 2008/09 to future years of £12.230m. Table 2 outlines the variances reported against each portfolio area. Department Current Projected Variance Paragraphs Approved Outturn Budget £m £m £m Children’s Services 33.347 33.217 (0.130) 10 City Strategy 8.196 8.439 0.243 11 Economic Development 0.158 0.158 0.000 12 Housing 8.953 8.817 (0.136) 13-14 Leisure and Culture 5.643 5.389 (0.254) 15-17 Neighbourhood 0.541 0.944 0.403 18-19 Services Resources 18.773 6.534 (12.239) 20-21 Social Services 0.331 0.332 0.001 22 Hazel court 0.000 0.100 0.100 23 Total 75.942 63.930 (12.012) Table 2 Capital Programme Forecast Outturn 2008/09
7. To the end of August there was £18.865m of capital spend representing 25% of the approved budget, compared to 23% for the same period in 2007/08.
8. The main highlights of this report are:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Executive - for meetings from 03/06/00 to 26/04/11 at York and we tell you when its next papers are published, before the meeting rather than after it.
Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.