A19 Fulford Road Corridor Update

Noted Committee 7 papers

City Strategy and Advisory Panel noted this item on Monday 8 December 2008. Below is the council's own wording, with the papers it was decided on.

Item61

Resolved

Advice of the Advisory Panel That the Advisory Panel advise the Executive Member for City Strategy that: (i) The contents of this report and its annexes are noted; 1. (ii) The revised proposals for the section of corridor between Cemetery Road and Hospital Fields Road, as outlined in paragraph 16 and shown on Annexes A1 and A2, are agreed; 2. (iii) Agree to implement the refuge island crossing without additional waiting restrictions. If indiscriminate parking is observed in the vicinity of the island, which obstructs the flow of traffic and/or affects safety, then Officers should report through an Officer in Consultation meeting to obtain approval to implement appropriate restrictions; (iv) That the limited time parking of 60 minutes maximum, proposed on the inbound (west) side of Fulford Road on the section north of Wenlock Terrace, be amended to only operate between 8:00 am and 6:00 pm on Monday to Saturday . (v) The proposed extensions of the 30 mph zone and the associated gateway treatments and improvement measures at Naburn, as outlined in paragraphs 57 and 58 and shown on Annexes C1 and C2, are agreed and that Officers report to a future meeting on the options available for improving pedestrian facilities at the Howden Dike crossing; (iv) That, subject to consultation with local residents, an inbound bus lane on Selby Road heading north from the A64 interchange for approximately 200m should be provided ahead of other improvements to this section of the corridor; (vi) That further investigation of other proposals south of Germany Beck, as listed in paragraph 44, be deferred until potential funding to implement those improvements can be identified; (vii) That any proposed bus lanes should be 24 hour operation similar to other existing bus lanes in York. Decision of the Executive Member for City Strategy
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to City Strategy and Advisory Panel

Meeting of Executive Members for City Strategy 8th December 2008 and Advisory Panel

Report of the Director of City Strategy

A19 FULFORD ROAD CORRIDOR UPDATE

Summary 1. The purpose of this report is to advise members of progress developing the proposals to improve the corridor. The report summarises comments received when further consultation on some of the improvement schemes was carried out and the associated Traffic Orders advertised. It makes recommendations on how to progress those schemes and seeks approval to those recommendations.

2. Since the last report the council has been awarded substantial funding for the Cycle City and Access York Phase 1 projects which require match funding, principally from the LTP allocation, which means that there is unlikely to be adequate funding available to implement all the Fulford Road proposals in the timescale originally anticipated. In addition the current downturn in the housing market and the ongoing village green public enquiry has raised questions as to when the Germany Beck development would commence. The Germany Beck junction is a key element of the proposals for the southern end of the corridor and the developer would also fund some of the other major improvement measures at this end of the corridor.

3. The corridor proposals have been reviewed to assess which would provide most benefits for the funding available. With the uncertainty over Germany Beck and the ongoing study at the Fishergate end, it is considered that the best returns would come from: • Improvements to the corridor between Cemetery Road and Heslington Lane, where pedestrians, cyclists and public transport users would all benefit from the proposed improvements; • The proposed refuge island on Main Street Fulford; • A bus lane on Selby Road near the A64; and • Improved gateways and safety improvements in Naburn. Background 4. At the meeting on 29th October 2007, members considered a report outlining the results of a multi-modal transport feasibility study of the A19 Fulford Road corridor, covering the length from Skeldergate Bridge and Tower Street in the north to the Designer Outlet (just south of the A19 / A64 interchange) in the south together with the associated feeder roads.

5. That report noted that the corridor was already congested at peak periods and that air pollution in Main Street, Fulford has been monitored as breaching health based air quality objectives. Without intervention there would be a significant worsening of conditions and a need to declare a further Air Quality Management Area (AQMA). Members agreed that the package of improvement measures proposed in the report should form the basis of the improvement strategy for the corridor and be taken forward for public consultation.

6. Subsequently a wide-scale public consultation was carried out on this package of measures. There was good support for the main principles of the improvement strategy with strong support for some of the proposed measures. The responses indicated that the proposed improvements would be likely to encourage walking, cycling and use of public transport along the corridor. The consultation identified some areas of concern where the proposals would need to be reviewed and possibly revised as they are developed.

7. At the meeting on 17th March 2008, members considered a report summarising the results of the consultation and reviewing the proposals for the corridor in the light of those results. Members agreed the recommendations on how to progress the proposed improvement measures, taking account of the consultation findings.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A19 Fulford Road Corridor UpdateReport 116 KB DownloadRead as text
PDF
Appendix BAppendix B 38 KB Download
PDF
Appendix B1Appendix B1 669 KB Download
PDF
Appendix CAppendix C 43 KB Download
PDF
Appendix C1Appendix C1 204 KB Download
PDF
Appendix C2Appendix C2 202 KB Download
PDF
A1 & A2Appendix es 1.8 MB Download

At this meeting

Whole meeting

Who was there

8 of 8 attended
SG
Councillor Steve GallowayCabinet Member, present
IG
Councillor Ian GilliesChair, present
AD
Councillor Andy D'AgorneVice-Chair, present
RC
Councillor Richard CreganCommittee Member, present
RP
Councillor Ruth PotterCommittee Member, present
DS
Councillor David ScottCommittee Member, present
SS
Councillor Susan SunderlandCommittee Member, present
AW
Councillor Andrew WallerCabinet Member, present

On this subject at York

Search all
  1. A19 Fulford Road Corridor UpdateThis decision
  2. 34 Fulford Place, Hospital Fields Road, York, YO10 4FE [24/01242/FUL] (5.26 pm)Approved
  3. Fulford Flood Alleviation Scheme, Pt Fulford Ings And Pt Playing Fields, Selby Road, York [23/00283/FUL] (4.34 pm)Deferred
  4. 126 Fulford Road, York, YO10 4BE [23/00798/FUL] (5.12 pm)Approved
  5. Consideration of Objections of the extension of R63 ResPark to include properties 298-314 Fulford Road (Even only)Decided
  6. Frederick House, Fulford Road, York, YO10 4EG [19/00603/FULM]Deferred

More from York City Strategy and Advisory Panel

All decisions
MeetingDecisionOutcome
16 Mar 2009 MinutesThat the minutes of the last meeting of the Panel held on 27 January 2009 be approved and signed by the Chair and Exe... Approved Open
16 Mar 2009 Core Funding to Voluntary Organisations 2009/10Advice of the Advisory Panel That the Executive Leader be advised to: (i) Maintain the existing grant funding agreeme... Agreed Open
16 Mar 2009 Chief Executive's Monitor 3 Finance & Performance Report 2008/09Advice of the Advisory Panel The Advisory Panel advises the Executive Leader to note the financial and performance po... Noted Open
16 Mar 2009 2008/09 Third Monitoring Report Economic Development and Partnerships - Finance & PerformanceAdvice of the Advisory Panel The Advisory Panel advises the Executive Leader to note the financial and performance po... Noted Open
16 Mar 2009 City Strategy Capital Programme - Monitor 3 ReportAdvice of the Advisory Panel That the Advisory Panel advise the Executive Member for City Strategy to: (i) Approve th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies