Executive 17 November 2009
Report of the Director of Resources
CAPITAL PROGRAMME – MONITOR TWO
Report Summary 1. The purpose of this report is to:
• Inform Members of the likely outturn position of 2009/10 Capital Programme based on the spend profile and information to October 2009;
• Inform the Executive of any under or overspends and seek approval for any resulting changes to the programme;
• Inform the Executive of any slippage and seek approval for the associated funding to be slipped to or from the financial years to reflect this;
• To inform Members of the funding position of the capital programme, taking account of the current capital receipts forecasts for the three year capital programme.
2. The 2009/10 – 2013/14 capital programme was approved by Council on 26th February 2009. Since then a number of amendments have taken place as reported to the Executive in the 2008/09 Capital Programme Monitor 3 report, the 2008/09 Capital Programme Outturn report and the 2009/10 Monitor 1 report. The changes made as result of the above papers have resulted in a current approved capital programme for 2009/10 of £67.034m, financed by £31.702m of external funding, and internal funding of £35.332m. Table 1 illustrates the movements from the start budget to the current approved position at monitor 2. Gross External Internal Budget Funding Funding £m £m £m Original Budget Approved by Council at 64.255 36.483 27.772 26 Feb 2009 Amendments from 2008/09 Monitor 3 0.702 0.309 0.393 report Amendments from 2008/09 outturn 4.017 (5.256) 9.273 report Amendments from 2009/10 Monitor 1 (1.940) 0.166 (2.106) report Current Approved Capital 67.034 31.702 35.332 Programme Table 1 Current Approved Capital Programme
Consultation 3. The capital programme was developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 26 February 2009. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals and associated capital receipt sales do follow a consultation process with local Councillors and residents in the locality of the individual schemes.
Summary of Key Issues 4. An increase of £0.345m is detailed in this monitor that results in a revised capital programme budget of £67.379m; £8.843m higher than the 2008/09 capital outturn of £58.536m.
5. Against the current approved budget post 2009/10 Monitor 1 of £67.034m, there is a predicted outturn of £67.379m, a net increase of £0.345m made up of: • Adjustments to schemes increasing costs by £1.078m. • The re-profiling of budgets from 2009/10 to future years of £0.733m. Table 2 outlines the variances reported against each portfolio area.
Department Current Projected Variance Paragraphs Approved Outturn Budget £m £m £m Children’s Services 32.378 33.378 1.000 9 - 10
Leisure and Culture 5.543 5.536 (0.007) 11
City Strategy 5.270 5.340 0.070 12 - 13 City Strategy (Economic 0.113 0.113 0.000 14 Development) Housing 8.732 8.734 0.002 15
Neighbourhood 6.429 5.329 (1.100) 16 - 18 Services Resources 1.761 1.761 0.000 19
Chief Executive 2.525 4.010 1.485 20 - 24
Social Services 0.711 0.711 0.000 25
City Strategy (Admin 3.212 2.107 (1.105) 26 - 29 Accom) Miscellaneous 0.360 0.360 0.000 30 - 32
Total 67.034 67.379 0.345
Table 2 Capital Programme Forecast Outturn 2009/10
6. To the end of September there was £19.623m of capital spend representing 29.6% of the projected outturn as per monitor 2 budget.
7. The 2009/10 capital programme will contribute toward the Corporate Strategy and will deliver:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Programme Monitor 2Appendix A | 118 KB | Download |
PDF |
Capital Monitor ReportAppendix B | 59 KB | Download |
PDF |
Capital Programme Monitor 2Report | 144 KB | DownloadRead as text |
Follow Executive - for meetings from 03/06/00 to 26/04/11 at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 Apr 2011 | MinutesThat the minutes of the Executive meeting held on 12 April 2011 and the Executive (Calling In) meeting held on 5 Apri... | Approved | Open |
| 26 Apr 2011 | Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas... | Agreed | Open |
| 26 Apr 2011 | Minutes of Working GroupsThat the minutes be noted and that the specific recommendations made by the Local Development Framework Working Group... | Noted | Open |
| 12 Apr 2011 | MinutesThat the minutes of the Executive meeting held on 29 March 2011 and of the Executive (Calling In) meetings held on 21... | Approved | Open |
| 12 Apr 2011 | Final Report arising from the Edible York Ad Hoc Scrutiny ReviewThat the recommendations of the Ad Hoc Scrutiny Committee be supported and approved, subject to the following amendme... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.