City of York Council
Executive, Tuesday 3 March 2026 at 4.30pm

Delivering More Affordable Housing in York - Castle Mills

Agreed Executive 5 papers

AI summaryYork Executive agrees preferred route for 100% affordable housing at Castle Mills, recommends £2.377m of HRA borrowing for design stages 3 and 4, and will seek Homes England and combined authority grants.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedRoute for 100% affordable housing at Castle Mills agreed
Money£2.377mHRA borrowing, for RIBA stages 3 and 4
What happens nextSubmit planning applicationAfter design updated to RIBA Stage 3
Who it affectsCastle Mills siteYork site set for 100% affordable housing

What was decided

Executive agreed the preferred delivery route of 100% affordable housing at the Castle Mills site, with procurement of a design team to update the previously approved design to RIBA Stage 3 within the proposed on-cost budget.

Executive recommended to Full Council a budget of £2.377m funded from HRA borrowing to develop the proposals through RIBA stages 3 and 4, and recommended the creation of the Castle Mills scheme within the HRA capital programme.

Executive agreed to apply to Homes England for Social and Affordable Homes Programme funding, to proceed with grant agreements with the York and North Yorkshire Combined Authority for Brownfield Fund awards, and (pending award) with One Public Estate for the Willow House project.

Why

The proposal sits within the Council's ongoing Housing Delivery Programme, with prior Executive decisions on affordable housing in York and on the Castle Gateway site referenced as background papers. Report P1, P2, P6

What happens next

Procure a design team to adapt the previously approved design to 100% affordable housing and refine it to RIBA Stage 3, then submit a planning application with the refined design.

Procure a contractor under a Pre-Contract Services Agreement or other design-only contract to collaboratively design the scheme to RIBA Stage 4 and price it.

Present an updated full business case to the Executive for approval, with the wider business case to follow at a later date.

The money

  • £2.377m HRA borrowing recommended to Full Council to develop Castle Mills proposals through RIBA stages 3 and 4

Implications

  • Financial: £2.377m of HRA borrowing recommended, with further funding to be sought from Homes England (SAHP), YNYCA Brownfield Fund and a pending OPE Brownfield Land Release Fund application.
  • Legal: Authority delegated to the Director of Housing and Communities (in consultation with the Director of Finance and Director of Governance) to procure contractors and enter contracts and grant agreements, in line with the Council's Financial Regulations, Contract Procedure Rules, the Procurement Act 2023 and the Public Contract Regulations 2015.

Who and where

  • People in need of affordable housing in York
  • The Castle Mills site
  • The Former Manor School and 68 Centre sites (covered by YNYCA Brownfield Fund grants)
  • The Willow House project (pending OPE Brownfield Land Release Fund application)

Timeline

  • RIBA Stage 3: Design team to update previously approved design to 100% affordable housing
  • After RIBA Stage 3: Planning application to be submitted with the refined design
  • RIBA Stage 4: Contractor to design and price the scheme under a Pre-Contract Services Agreement or design-only contract
  • Later date: Updated full business case to be presented to the Executive; wider business case to come forward

Plain English for the jargon

  • HDP: Housing Delivery Programme
  • OPE: One Public Estate
  • RP: Registered Provider
  • RtB: Right to Buy
  • SAHP: Social and Affordable Homes Programme
  • YNYCA: York and North Yorkshire Combined Authority
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item211

Resolved

Resolved (unanimously): That Executive a) Agrees the preferred delivery route of 100% affordable housing at the Castle Mills site with the procurement of a design team to update the design previously approved by Planning to adapt it to 100% affordable housing, and achieve a refined design to RIBA Stage 3, using the proposed on-cost budget. b) Agrees to the submission of a planning application with the refined Castle Mills design. c) Agrees to procure a contractor to operate under a Pre-Contract Services Agreement or other type of design-only contract to collaboratively design Castle Mills to RIBA Stage 4 and price the design, to enable an updated full business case to be presented to the Executive for approval. d) Recommends to Full Council the creation of the Castle Mills scheme within the HRA capital programme; the wider business case for which will come forward at a later date . e) Recommends to full Council approval of a budget of £2.377m funded from HRA borrowing, to develop the proposals through RIBA stages 3 and 4 as described in a), b) and c) above. f) Agrees to delegate authority to the Director of Housing and Communities (in consultation with the Director of Finance and the Director of Governance) to take such steps that are necessary to procure and appoint such the contractors, and to determine the provisions of and enter into the resulting contracts described in a) and c) above (and any subsequent modifications and/or extensions thereto), in accordance with the Council’s Financial Regulations set out in Appendices 10 and 10a of the Constitution (the “Finance Regs”), the Contract Procedure Rules set out in Appendix 11 of the Constitution (the “CPRs”) and (where applicable) the Procurement Act 2023 (the “Procurement Act”) and the Public Contract Regulations 2015 (the “PCRs”). g) Agrees to the preparation and submission of applications to Homes England for funding from the Social and Affordable Homes Programme (SAHP) to deliver the affordable homes at Castle Mills, and (provided that the application to Homes England is successful) to receive funding and agree to proceed with entering into a grant agreement with Homes England. h) Notes the Brownfield Fund grant awards received from the York and North Yorkshire Combined Authority (YNYCA) for the development of affordable housing at Castle Mills, Former Manor School and 68 Centre sites and agree to proceed with entering into grant agreements to receive funding. i) Notes that a Brownfield Land Release Fund grant application to the One Public Estate (OPE) has been submitted to contribute to funding of the Willow House project delivery including the necessary enabling works; and pending the grant award, agree to proceed with entering into a grant agreement to receive funding. j) Further to g), h) and i) above, agrees to delegate authority to the Director of Housing and Communities (in consultation with the Director of Finance and the Director of Governance) to determine the provisions of and enter into any resulting grant funding agreements with Homes England and YNYCA, and the provisions ...
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

Meeting: Executive Meeting date: 3 March 2026 Report of: Pauline Stuchfield, Director of Housing and Communities Portfolio of: Councillor Michael Pavlovic, Executive Member for Housing, Planning and Safer Communities

Decision Report: Delivering More Affordable Housing in York – Castle Mills

Subject of Report 1. In October 2025, a report was brought to Executive with an update of the Housing Delivery Programme in light of the Government Comprehensive Spending Review which had placed housing at its centre with a commitment to deliver the biggest increase in social and affordable housing in a generation and the new Social and Affordable Homes Programme (SAHP), which provides a decade of certainty over funding to support the delivery of new homes between 2026-2036.

2. The report sought to use the security of the national position to support the delivery of new affordable homes in York, building a strong pipeline to seize the opportunities this funding presents. Future developments through the Adopted Local Plan alongside our own housing building programme, could also include increasing Council stock through the purchase of s106 properties on private developments.

3. This paper seeks support to continue this work with a proposed delivery route for affordable housing at the Castle Mills site.

4. This report seeks decisions in respect of:

a) Continue supporting the development of a strong new build pipeline with a budget to prepare the design by adapting existing proposals to build 100% affordable housing at the Castle Mills site; submit a planning application; apply for Homes England’s Social and Affordable Homes Programme (SAHP) grant; and procure a development partner, with an updated business case to be presented to and approval sought from the Executive before entering into a construction contract.

b) Note that Brownfield Fund grants have been awarded from the York and North Yorkshire Combined Authority (YNYCA) to CYC for the development of affordable housing at Castle Mills, Former Manor School and 68 Centre sites and agree to proceed with entering into respective grant agreements to receive funding.

c) Note that a Brownfield Land Release Fund grant application to the One Public Estate (OPE) has been submitted to contribute to funding of the Willow House project delivery including the necessary enabling works; and pending the grant award, agree to proceed with entering into a grant agreement to receive funding.

Benefits and Challenges 5. Utilising Council-owned land to deliver affordable housing ensures that the maximum benefit is being achieved through our land assets. The Council has built an established and experienced team who are able to directly deliver much needed affordable homes in the city which meet the needs of our residents. All future projects are designed as 100% affordable housing, maximising both internal funding such as Right to Buy receipts and the newly announced Homes England funding combined with devolved funding through the YNYCA. The proposed developments remain mixed tenure combining social rented homes with shared ownership to provide a range of housing options for residents in various forms of housing need across the city.

6. Delivering the homes directly in the Housing Revenue Account (HRA) ensures that the Council continues to replenish housing stock lost through Right to Buy and that the income generated through rent continues to increase over the course of the 30-year business plan, supporting the ability to invest in existing homes. In the short-term, developing homes directly results in increased borrowing to support the delivery of new homes, however increasing the number of homes in the Council’s housing stock has a positive long-term impact. Policy Basis for Decision 7. One of the seven priorities outlined in the Council Plan (2023-27) is to increase the supply of good quality affordable housing.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Delivering More Affordable Housing in York: Castle MillsReport 355 KB DownloadRead as text
PDF
Item 14: Delivering More Affordable Housing in York: Castle Mills: Annex BAppendix 360 KB Download
PDF
Item 14: Delivering More Affordable Housing in York: Castle Mills: Annex CAppendix 656 KB Download
PDF
View as HTML (211./4) 103 KBAppendix 103 KB Copy on its way
PDF
View item 211. as HTML 113 KBReport 113 KB Copy on its way

At this meeting

Whole meeting

Who was there

8 of 8 attended
CD
Councillor Claire DouglasChair, present
PK
Councillor Peter KilbaneVice-Chair, present
JK
Councillor Jenny KentCommittee Member, present
KL
Councillor Katie LomasCommittee Member, present
MP
Councillor Michael PavlovicCommittee Member, present
KR
Councillor Kate RaviliousCommittee Member, present
LS
Councillor Lucy Steels-WalshawCommittee Member, present
RW
Councillor Robert WebbCommittee Member, present

On this subject at York

Search all
  1. Delivering More Affordable Housing in York - Castle MillsThis decision
  2. Delivering More Affordable Housing in York – Update on the Housing Delivery ProgrammeApproved
  3. Delivering More Affordable Housing in York – update on the Housing Delivery Programme (19:07)Decided

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open