Haxby Station – Update and Land Acquisition

Noted Executive 2 papers

Executive noted this item on Thursday 30 September 2021. Below is the council's own wording, with the papers it was decided on.

Item41

Resolved

(i) That the progress made to date concerning a potential new rail station at Haxby be noted. (ii) That the addition of the Department for Transport grant of £400k to progress the Haxby Station project be approved, that the scheme be included in the Capital Programme 2021/22 and that authority be delegated to the Director of Place (in consultation with the Director of Governance or her delegated officers) to take such steps as are necessary to enter into the resulting agreement. (iii) That approval be given to acquire the freehold interest comprising 6.8 acres of land within the area of Haxby , as detailed in exempt Annex A, and to establish a budget of £250k to fund the purchase and associated acquisition costs. (iv) That approval be given to vire £250k from the Highways budget to fund the land purchase. (v) That authority be delegated to the Corporate Director of Place, in consultation with the Executive Member for Transport, to take such steps as are necessary to complete the purchase once all due diligence has been satisfactorily conducted on the land. Reason: To afford City of York Council the best opportunity to progress this project and present the strongest case possible to Central Government (the Department for Transport and the Treasury) for their anticipated grant of funding to enable the full delivery of a new rail station at Haxby . (i) That the progress made to date concerning a potential new rail station at Haxby be noted. (ii) That the addition of the Department for Transport grant of £400k to progress the Haxby Station project be approved, that the scheme be included in the Capital Programme 2021/22 and that authority be delegated to the Director of Place (in consultation with the Director of Governance or her delegated officers) to take such steps as are necessary to enter into the resulting agreement. (iii) That approval be given to acquire the freehold interest comprising 6.8 acres of land within the area of Haxby , as detailed in exempt Annex A, and to establish a budget of £250k to fund the purchase and associated acquisition costs. (iv) That approval be given to vire £250k from the Highways budget to fund the land purchase. (v) That authority be delegated to the Corporate Director of Place, in consultation with the Executive Member for Transport, to take such steps as are necessary to complete the purchase once all due diligence has been satisfactorily conducted on the land. Reason: To afford City of York Council the best opportunity to progress this project and present the strongest case possible to Central Government (the Department for Transport and the Treasury) for their anticipated grant of funding to enable the full delivery of a new rail station at Haxby .
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 10 pages

Summary

1. This report provides an update to Executive on progress made towards a proposed new rail station in Haxby. It seeks approval to add the Haxby Station project to the council’s Capital Programme 2021/22 and continue with development work with our delivery partners Network Rail. Additionally approval is sought from Members to acquire the freehold interest of a specific plot of land within the area of Haxby, which would either significantly de-risk the future delivery of the project or be utilised for other strategic council objectives.

Recommendations

2. The Executive is asked to:

1) Note progress made to date concerning a potential new rail station in Haxby.

2) Approve the addition of the Department for Transport grant of £400k to progress the Haxby Station project and include the scheme in the Capital Programme 2021/22 and to delegate authority to the Director of Place (in consultation with the Director of Governance or her delegated officers) to take such steps as are necessary to enter into the resulting grant agreement.

3) Subject to the approval of recommendation 2), approve the grant of the funding to Network Rail for the delivery of the development works and to delegate authority to the Director of Place (in consultation with the Director of Governance or her delegated officers) to take such steps as are necessary to enter into the resulting agreement. 4) Agree to the acquisition of the freehold interest comprising 6.8 acres of land within the area of Haxby as detailed within Confidential Annex A and agree to the establishment of a budget of £250K to fund the purchase and associated acquisition costs.

5) Agree to the virement of £250k from the Highways budget to fund the land purchase.

6) To delegate authority to the Corporate Director of Place, in consultation with the Executive Member for Transport, the council’s S151 Officer and Monitoring Officer, to take such steps as are necessary to complete the purchase once all due diligence is satisfactorily conducted on the land.

Reason: To afford City of York Council the best opportunity to progress this project and present the strongest case possible to Central Government (the Department for Transport; and Treasury) for their anticipated granting of funding to enable the full delivery of a new rail station at Haxby.

Background

3. A funding bid to Department for Transport’s (DfT) New Stations Fund (NSF) was submitted by the City of York Council (CYC) in June 2020, requesting a 75% contribution towards a new rail station at Haxby. At the time, an initial appraisal indicated an estimated cost of circa £17.6m for delivery of this project, although it should be noted that this is expected to reduce following further development.

4. A preliminary funding decision was received in November 2020 confirming that CYC had not been awarded the full award requested at this stage, however a grant allocation of £400k had been made available for CYC to fund further development work by their delivery partners Network Rail (NwR) to strengthen the strategic and business case; and refine the costs.

5. DfT have indicated their support of this project and that they would expect to make a decision within the first half of 2022 on awarding full funding for delivery of the station, subject to a satisfactory resolution of the above items, and conditional on the identification of 25% local match funding. 6. Timescales set out by DfT mandate that construction of the new station would be required by March 2024. An indicative high-level programme is included below for your information:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Haxby Station: Update and Land AcquisitionReport 10 pages DownloadRead as text
PDF
View item 41. as HTML 76 KBReport 76 KB Copy on its way

At this meeting

Whole meeting

On this subject at York

Search all
  1. Haxby Station – Update and Land AcquisitionThis decision
  2. 7 Station Road, Haxby, York, YO32 3LS [24/01047/FUL] (4.37 pm)Approved
  3. Haxby Station – Update and Next StepsNoted
  4. Haxby Station – Site SelectionNoted
  5. Haxby Station UpdateAgreed
  6. Haxby Rail Station Update IVNoted

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies