Executive, Thursday 6 October 2022 at 10.00am

Haxby Station – Update and Next Steps

Noted Executive 3 papers

Executive noted this item on Thursday 6 October 2022. Below is the council's own wording, with the papers it was decided on.

Item40

Resolved

( i ) That the additional £1.1m funding allocated to the project from government be noted. (ii) That the results of the public consultation undertaken earlier in 2022 be noted. (iii) That the recent application to Round 2 of the government’s Levelling Up Fund be noted. (iv) That authority be delegated to the Corporate Director of Place, in consultation with the Executive Member for Transport, to submit a planning application for the anticipated future construction of the new station. (v) That authority be delegated to the Corporate Director of Place, in consultation with the Executive Member for Transport and the Director of Governance (or his delegated Officers), to: a) Undertake such steps as are necessary to commission Network Rail, as the council’s delivery partners, to progress the next stage of development ( GRIP 4 & 5 stages), up to the point of delivery, noting that a further report will be brought to Executive to report on the actual build costs and to seek approval to proceed with construction. b) Carry out a procurement to engage a consultant to undertake the required design services to deliver all Highways aspects of the project which are outside the station site and to take such steps as are necessary to award and enter into the resulting contract. c) Carry out a procurement to engage a construction contractor to undertake the required construction works to deliver all Highways aspects of the project which are outside the station site, noting that a further report will be brought to Executive to report on the actual build costs and to seek approval to proceed with construction. Reason: To afford City of York Council the best possible opportunity to progress this project in a timely fashion and enable the full delivery of a new rail station at Haxby by early 2024, as mandated by government. (i) That the additional £1.1m funding allocated to the project from government be noted. (ii) That the results of the public consultation undertaken earlier in 2022 be noted. (iii) That the recent application to Round 2 of the government’s Levelling Up Fund be noted. (iv) That authority be delegated to the Corporate Director of Place, in consultation with the Executive Member for Transport, to submit a planning application for the anticipated future construction of the new station. (v) That authority be delegated to the Corporate Director of Place, in consultation with the Executive Member for Transport and the Director of Governance (or his delegated Officers), to: a) Undertake such steps as are necessary to commission Network Rail, as the council’s delivery partners, to progress the next stage of development ( GRIP 4 & 5 stages), up to the point of delivery, noting that a further report will be brought to Executive to report on the actual build costs and to seek approval to proceed with construction. b) Carry out a procurement to engage a consultant to undertake the required design services to deliver all Highways aspects of the project which are outside the station site and to take such steps as are necessary to award and enter into the resulting contract. c) Carry out a procurement to engage a construction contractor to undertake the required construction works to deliver all Highways aspects of the project which are outside the station site, noting that a further report will be brought to Executive to report on the actual build costs and to seek approval to proceed with construction. Reason: To afford City of York Council the best possible opportunity to progress this project in a timely fashion and enable the full delivery of a new rail station at Haxby by early 2024, as mandated by government.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 12 pages

Summary

1. This report provides an update on the progress of the Haxby Station project. To take this project forward, Members are asked to note recent developments and delegate authority for a number of matters to ensure that the project remains on target in terms of delivery timescales.

Recommendations

2. Executive is asked to:

1) Note the additional £1.1m funding allocated to the project from government.

2) Note the results of the public consultation, undertaken earlier in 2022.

3) Note the recent application to Round 2 of the government’s Levelling Up Fund.

4) Delegate authority to the Corporate Director of Place, in consultation with the Executive Member, to submit a planning application for the anticipated future construction of the new station.

5) Delegate authority to the Corporate Director of Place, in consultation with the Executive Member and the Director of Governance (or his delegated Officers), to:

i) Undertake such steps as are necessary to commission Network Rail, as our delivery partners, to progress the next stage of development (GRIP 4 & 5 stages), up to the point of delivery and note that a further report will be brought to Executive to report on the actual build costs and to ask the Executive to agree to proceed with construction.

ii) Carry out a procurement to engage a consultant to undertake the required design services to deliver all Highways aspects of the project which are outside the station site and to take such steps as are necessary to award and enter into the resulting contract.

iii) Carry out a procurement to engage a construction contractor to undertake the required construction works to deliver all Highways aspects of the project which are outside the station site and note that a further report will be brought to Executive to report on the actual build costs and to ask the Executive to agree to proceed with construction.

Reason: To afford City of York Council the best possible opportunity to progress this project in a timely fashion and enable the full delivery of a new rail station at Haxby by early 2024, as mandated by government.

Background

3. A preliminary funding decision was received in November 2020 from the Department for Transport (DfT) indicating an award of £400k of their New Stations Fund (NSF) / Restoring Your Railway Fund (RYR) towards a new station at Haxby. This was to enable further development work by delivery partners Network Rail (NwR) to develop outline designs and refine costs. DfT have continued to indicate their strong support for this project and have expressed that they expect to confirm full funding in due course (75% of costs), subject to a satisfactory business case being submitted to the Department for Transport. Upon confirmation of government funding, this will be reported to a future meeting of Executive to seek approval to add this to the budget.

4. At Executive (9 December 2021), Members approved a site at Towthorpe Road as the preferred location for the new station in Haxby, enabling the project to progress to the next stage of development (GRIP 3) and presenting the strongest case possible to government for the expected granting of funding to enable full delivery of a new station located at Towthorpe Road.

5. At Executive (7 February 2022) an allocation was agreed within the Capital budget of £4.3m over three years in anticipation of match-funding the government’s envisaged grant with a 25% local contribution (of circa £4.0m) in consultation with Chief Finance Officer and Director of Governance. Current estimates for delivery of the project are circa £16m, but this is likely to be adjusted following refinement by NwR in their Station Proposal Report, due imminently. Timescales set out by DfT mandate that construction of the new station is required by the end of March 2024.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Haxby Station Public Consultation Results 2022Appendix A 5 pages Download
PDF
Haxby Station: Update and Next StepsReport 12 pages DownloadRead as text
PDF
View item 40. as HTML 84 KBReport 84 KB Copy on its way

At this meeting

Whole meeting

On this subject at York

Search all
  1. Haxby Station – Update and Next StepsThis decision
  2. 7 Station Road, Haxby, York, YO32 3LS [24/01047/FUL] (4.37 pm)Approved
  3. Haxby Station – Site SelectionNoted
  4. Haxby Station – Update and Land AcquisitionNoted
  5. Haxby Station UpdateAgreed
  6. Haxby Rail Station Update IVNoted

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies