Resolved
[See also under Part B Minutes]
Executive decided this item on Tuesday 6 December 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
[See also under Part B Minutes]
Cabinet 6 December 2011
Report of the Cabinet Member for Leisure, Culture and Social Inclusion
Community Stadium Project
Summary 1. The purpose of this paper is to: § Set out the timetable for progression of the business case. § Set out the resources required to develop the business case to the next stage.
Background 2. An outline business case for the project was first presented to members in June 2009. It was then developed to a more detailed stage to support the decision of the Executive in July 2010 that the stadium would be at Monks Cross South and delivered as part of an enabling development at the centre of a range of community facilities.
3. The Executive of 19 October 2010 established a Community Stadium Advisory Group (CSAG) through which progress on the community stadium project has been reported. This is an advisory group to the Council Cabinet. The group’s minutes are published and are publicly accessible. The business case has been developed, amended and updated as the project and its proposals have progressed. This progression has been reported to the Advisory Group as part of regular updates.
4. A planning application has been submitted for the enabling development. It is clear from the development appraisal that has been submitted to support the scheme, that the Council’s vision is deliverable, subject to the enabling development being satisfactory in planning terms. A summary of the capital funding position is shown in the table below:
Table 1 Indicative capital costs Component Capital Cost comment (£000s)
Stadium 12,400 Potential options for value engineering to reduce this figure
External works 1,200 Based on Oakgate development appraisal / DLA plans
Community floor space 3,000 See breakdown in revenue table below
Athletics Facilities 2,500 Cost to be reduced through value engineering and inclusion in wider construction package.
Community sport facilities 750 To include interim ground sharing / training facilities / costs.
Project Costs 1,000 Estimation between £875K and £1,250K dependent on procurement route and risk transfer.
Total 21,050
Note: These figures are indicative. They include fees @12% and contingency @ 5%, but do not include VAT. A VAT assessment is underway as part of a wider financial due diligence exercise.
Table 2 Indicative Funding Sources Component Capital Cost comment (£000s)
S106 Contribution 14,040 Based on Oakgate draft development appraisal
CYC Capital 4,000 CYC approved capital programme
YCFC Capital 2,000 Contribution following Bootham Crescent disposal External Funding 1,000 Potential contributions from Sport England, UK Athletics and the Football Foundation
Total 21,040
5. This is a complex development scheme which has a number of projects forming an overall programme. It will involve the procurement of both a design and build of facilities contract, and an operation and maintenance contract. These processes require the business case to be developed in stages as the project progresses. This is an iterative process which continues all the way through the procurement and construction of the project through to delivery. The next key stage will be sign off of the core principles of the way the stadium and associated community facilities will be delivered, operated and maintained. This will set out projections of the principal costs and income streams together with a sensitivity analysis identifying the relevant risks.
6. This report will be presented to the CSAG on 14 December 2011. Following further development it will then be reported to the Council Cabinet meeting on 9 January 2012 together with a procurement and project plan including arrangements for governance and project management and a statement of the resources required to manage risk and control expenditure.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Community Stadium ProjectAppendix 1 | 31 KB | Download |
PDF |
Community Stadium UpdateReport | 120 KB | DownloadRead as text |
Follow Executive at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Nov 2026 | Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. | Approved | Open |
| 3 Nov 2026 | Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... | Noted | Open |
| 3 Nov 2026 | Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... | Noted | Open |
| 3 Nov 2026 | Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... | Noted | Open |
| 3 Nov 2026 | Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.