City of York Council
Executive, Tuesday 14 February 2012 at 5.30pm

Capital Programme Budget 2012/13 - 2016/17

Agreed Executive 4 papers

Executive agreed this item on Tuesday 14 February 2012. Below is the council's own wording, with the papers it was decided on.

Item104

Resolved

RECOMMENDED: That Council: i ) Agree to the revised capital programme of £187.364m, that reflects a net overall increase of £53.641m (as set out in paragraph 32 table 9 and in Annex A ‘growth’ column). Key elements of this include: a) Extension of prudential borrowing funded Rolling Programme schemes totalling £2.105m as set out in paragraph 10 table 2 and summarised in paragraph 32 table 9; b) New schemes totalling £10.405m including increase in prudential borrowing of £2.595m as set out in paragraph 13 table 3 and summarised in paragraph 30 table 10; c) Reduction of existing prudential borrowing funded schemes totalling £4.500m as set out in paragraph 15 table 4 and summarised in paragraph 32 table 9; d) New externally funded and HRA funded schemes totalling £16.381m including HRA balances of £4.447m and including £500k of New Homes Bonus funding for Replacement of Street Lighting as set out in paragraph 18 table 5 and summarised in paragraph 32 table 9. e) Extension of the existing IT development programme totalling £750k in 16/17 funded by prudential borrowing paid for from with in existing revenue budgets as set out in paragraph 31 table 8 and summarised in paragraph 32 table 9. ii) Approve the re-profiling of £150k from future years to 12/13 in relation to replacement of unsound lighting columns scheme as shown in Annex A. iii) Approve the full restated programme as summarised in Annex A totalling £187.364m cover financial years 2012/13 to 2015/16 as set out in paragraph 34 table 10. iv) Approve the establishment of the EIF and the proposed priority themes of expenditure as follows: o Get York Moving including § Access York Park and Ride - £2.5m § Better Bus Fund - £2.0m see Annex C o Digital York o Reinvigorate York o Economic Inclusion York o Sustainable Economy York v) Approve Council funding to the EIF as follows – £20m of prudential borrowing over next 5 years, all of the New Homes Bonus funds (currently estimated at £8.5m) from 2012/13 onwards, except for £0.5m in 2012/13 which is allocated for Street Lighting replacement. vi) Agree that the Director of CBSS be authorised to take decisions on the financing of any expenditure, and profiling of any borrowing, in accordance with the overall financial framework agreed by Council vii) Agree that decisions on the actual schemes, and monitoring of such schemes will be considered through regular financial monitoring reports to Cabinet. REASON: To set a balanced capital programme as required by the Local Government Act 2003.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

Background

3. The current 2011/12 –2015/16 capital programme was approved by Council on 25th February 2011. Since then a number of amendments have taken place as reported to the Cabinet up to and including the 2011/12 Capital Monitor 3 report. The changes made as a result of the above reports have resulted in a current approved capital programme for 2011/12 – 2015/16 of £192.254m (£314.637m including HRA self financing), financed by £104.417m of external funding, and Council controlled resources of £87.837m (£210.220). Table 1 illustrates the current approved capital programme profile from 2011/12 – 2015/16 as at monitor 3.

2011/12 2012/13 2013/14 2014/15 2015/16 Total £m £m £m £m £m £m Gross Capital 180.914 71.371 29.539 21.250 11.563314.637 Programme Funded by: External Funding 26.347 33.581 21.967 15.316 7.206104.417

Council Controlled 32.184 37.790 7.572 5.934 4.357 87.837 Resources Council Controlled 122.383 0 0 0 0 122.383 Resources HRA – self financing

Total Funding 180.914 71.371 29.539 21.250 11.563 314.637 Table 1 – Capital Programme Funding and Receipts Position

Funding Position of approved 2011/12 – 2015/16 programme

4. The current economic environment continues to place pressure on the funding of the programme over the 5 year cycle based on current projections. The capital programme continues to place significant reliance on the achievement of a small number of high value asset disposals which have been affected by the economic downturn.

Developing the Capital Programme - The 2012/13 CRAM Process and Priority Investment

5. The CRAM process invited bids from the departments asking them to put forward their main capital priorities. Of the bids received, 6 are fully funded from external sources, 6 are rolling programme bids, with the remaining 12 bids seeking additional discretionary resources over and above those already approved in the Capital Programme. In total, requests that would increase the Capital Programme by £24.391m have been made. The £24.391m is comprised of £11.225m of general fund schemes and £13.166m of Housing Revenue Account (HRA) schemes. The £11.225m of general fund schemes are financed by £11.025m of external funding sources and internal funding sources of £200k. The HRA schemes are financed by £8.719m of external funding sources and £4.447m of internal funding sources (HRA balances). This results in no increase in Council funding that impact on Council Tax and has been achieved through a considered review of existing programmes and maximising match funding over the 5 year period. Tables 2,3,4 and 5 show the proposals that result in a net increase of £24.391m. Key schemes being recommended within this report include (see Annex B for full scheme details and impacts):-

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Budget 1213: 1617 v2Appendix A 167 KB Download
PDF
Capital Budget 1213 Scheme Descriptions v2Appendix B 103 KB Download
PDF
Better Bus FundAppendix C 72 KB Download
PDF
Capital Programme Budget 2012/13: 2016/17Report 190 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 15 attended
JA
Councillor James AlexanderChair, present
SC
Councillor Sonja CrispCommittee Member, present
SF
Councillor Sandy FraserCommittee Member, present
JG
Councillor Julie GunnellCommittee Member, present
JL
Councillor Janet LookerCommittee Member, apologies
DM
Councillor Dave MerrettCommittee Member, present
TS
Councillor Tracey Simpson-LaingVice-Chair, present
DW
Councillor Dafydd WilliamsCommittee Member, present
MW
Councillor Mark WartersAttendee, in attendance
AR
Councillor Ann ReidAttendee, in attendance
CF
Councillor Christina FunnellAttendee, in attendance
BB
Councillor Barbara BoyceAttendee, in attendance

All 15 on the meeting page

On this subject at York

Search all
  1. Capital Programme Budget 2012/13 - 2016/17This decision
  2. Capital Programme Monitor Update 2 Report (4:47pm)Noted
  3. Capital Programme - Monitor 1 2026/27 (4:46pm)Noted
  4. Capital Programme Outturn 2025/26 and Revisions to the 2026/27 - 2029/30 ProgrammeApproved
  5. Recommendations of Executive in relation to the Capital Programme - Monitor 3 2025/26Approved
  6. Capital Programme - Monitor 3 2025/26Approved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open