Implementing the Review of the City of York Council’s Residential Care Homes for Older People

Agreed Executive 3 papers

Executive agreed this item on Tuesday 15 May 2012. Below is the council's own wording, with the papers it was decided on.

Item142

Resolved

i ) That Cabinet agree in principle to Option 4, to provide the care on the Fordlands and Haxby Hall developments only, with care on the Lowfield site being provided by an independent operator (subject to further financial consideration and Full Council approval), that is: a) That the Council fund and operate the new residential care home to be built on the Fordlands Road site by engaging a design team and then entering a formal tender process to procure a builder. b) That the Council states its intention to operate the new residential care home to be built on the site of the existing CYC care home at Haxby subject to financial affordability in Autumn 2013 when a firm decision on that particular home is required. c) That the Council seeks to procure a partner through a tendering process to fund, build and operate a ‘community village for older people’ (including 90 residential care beds) on the Lowfield site in Acomb. The council’s own in-house service will be able to compete for this work. ii) That Cabinet receive further reports outlining the outcome of the tenders for both the Fordlands and Lowfield village developments, with updated financial implications on all areas, to assess the affordability of the proposals. REASON: The Council’s review of its existing elderly persons homes highlighted the need for changes to the current provision and how the homes could be replaced by modern facilities. There was overwhelming support in the consultation of the need for change and the vision of the new facilities in the city. After conducting a detailed analysis of a number of options both practical and financial along with considering the outcome of the public consultation Option 4 offers the best fit solution with least risk to the Council to create these modern facilities. i ) That Cabinet agree in principle to Option 4, to provide the care on the Fordlands and Haxby Hall developments only, with care on the Lowfield site being provided by an independent operator (subject to further financial consideration and Full Council approval), that is: a) That the Council fund and operate the new residential care home to be built on the Fordlands Road site by engaging a design team and then entering a formal tender process to procure a builder. 1. b) That the Council states its intention to operate the new residential care home to be built on the site of the existing CYC care home at Haxby subject to financial affordability in Autumn 2013 when a firm decision on that particular home is required. c) That the Council seeks to procure a partner through a tendering process to fund, build and operate a ‘community village for older people’ (including 90 residential care beds) on the Lowfield site in Acomb . The council’s own in-house service will be able to compete for this work. 2. ii) That Cabinet receive further reports outlining the outcome of the tenders for both the Fordlands and Lowfield village developments, with updated financial implications on all areas, to assess the affordability of the proposals. 3. REASON: The Council’s review of its existing elderly persons homes highlighted the ... view the full minutes text for item 142.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

Background

2. At its meeting on the 10 January 2012, and in the context of the positive public endorsement of the overall Elderly Persons Homes (EPH) strategy, Cabinet agreed: a) to the closure of Oliver House and Fordlands Residential Care Homes and that residents’ moves to their new homes are carefully planned and managed in line with the “Moving Homes Safely” protocol b) to the implementation of the overall programme of development for the modernisation of the council’s Residential Care Homes c) that officers undertake a soft market testing exercise for the development of the Lowfield site and report back to Cabinet the outcome along with a financial model of the operating and design options d) to receive a more detailed business case for the development of a new residential care home on the Fordlands site which shows the possible build and operating options. Progress on the closure of Oliver House and Fordlands Residential Care Homes

3. Officers from the council’s Assessment Teams and Care Home staff from Fordlands and Oliver House worked closely with residents and relatives to ensure that all residents had a carefully planned and managed move to their new home. All 25 residents moved to their ‘first preference’ home with all, except one, moving to City of York Council EPHs. All residents had been offered and mainly took up the opportunity to visit 2-3 homes before choosing their final preference. Residents without relatives were supported through the process by independent advocates. The residents moved in small numbers and by mid-March all of the residents from both homes had successfully moved and were settled in their new homes.

4. Care management staff set review dates for each of the residents that moved. The reviews were set to take place around 28 days from the date of their move. Feedback so far has been positive from both residents and their families. 5. In addition, York St John University has been commissioned to undertake an external evaluation of practice around the closures of Fordlands and Oliver House. The researcher will talk to residents, relatives and staff about the residents’ experience of the moves and the process that has been followed. The research will tell us (a) how well the council followed the process outlined in its ‘Moving Homes Safely’ protocol, (b) whether that protocol represents a ‘best practice’ model nationally, and (c) what learning lessons we can take to help inform the second round of EPH closures planned for Spring 2014. The findings of that research will be shared with the Cabinet Member who has committed to make the report public.

Elderly Persons Home Staff

6. All Fordlands and Oliver House staff have now been redeployed into either the same, or fundamentally the same posts at the other CYC EPHs and the vast majority have moved to their first preference home. Thirty two staff have been released via the council-wide voluntary redundancy programme which meant that the council was able to achieve the closure of Fordlands and Oliver House without the need to make any compulsory redundancies. Fordlands and Oliver House sites

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EPH report: Annex AAppendix 58 KB Download
PDF
EPH report: Annex CAppendix 102 KB Download
PDF
Implementing the Review of the City of York Council’s Residential Care Homes for Older PeopleReport 170 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 18 attended
JA
Councillor James AlexanderChair, present
SC
Councillor Sonja CrispCommittee Member, apologies
SF
Councillor Sandy FraserCommittee Member, present
JG
Councillor Julie GunnellCommittee Member, present
JL
Councillor Janet LookerCommittee Member, present
DM
Councillor Dave MerrettCommittee Member, present
TS
Councillor Tracey Simpson-LaingVice-Chair, present
DW
Councillor Dafydd WilliamsCommittee Member, present
CR
Councillor Carol RuncimanAttendee, in attendance
MW
Councillor Mark WartersAttendee, in attendance
KA
Councillor Keith AspdenAttendee, in attendance
IC
Councillor Ian CuthbertsonAttendee, in attendance

All 18 on the meeting page

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open