That Cabinet notes: i) The 2012/13 revised budget of £65.153m as set out in paragraph 4 and Table 2 of the report. ii) The restated capital programme for 2012/13 – 2016/17 as set out in paragraph 28, Table 3 and detailed in Annex A of the report . iii) The Better Bus Area Fund external funding received from the Department of Transport at £0.670m in 2012/13 and £1.095m in 2013/14. REASON: To enable the effective management and monitoring of the Council’s capital programme. That Cabinet notes: i) The 2012/13 revised budget of £65.153m as set out in paragraph 4 and Table 2 of the report. ii) The restated capital programme for 2012/13 – 2016/17 as set out in paragraph 28, Table 3 and detailed in Annex A of the report . iii) The Better Bus Area Fund external funding received from the Department of Transport at £0.670m in 2012/13 and £1.095m in 2013/14. REASON: To enable the effective management and monitoring of the Council’s capital programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
3. The capital programme was developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 14 February 2012. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals and associated capital receipt sales do follow a consultation process with local Councillors and residents in the locality of the individual schemes.
Summary of Key Issues
4. A decrease of £1.914m is detailed in this monitor that results in a revised capital programme budget from £67.067m to £65.153m.
5. The net decrease of £2.584m is made up of: • New schemes increasing budgeted expenditure by £0.832m. • Net re-profiling of £2.746m of schemes from the current year to future years.
6. Table 2 outlines the variances reported against each portfolio area. It should be noted that the portfolios have been aligned with the new Council Structure from 1st April 2012. Accordingly the figures presented at outturn by Directorate and portfolio will have changed due this change.
Directorate Department Current Projected Variance Approved Outturn Budget £m £m £m ACE Children’s, 9.964 10.064 0.100 Education and Skills ACE Adult Social 1.307 1.307 0.000 Services City & Env Planning & 8.342 9.012 0.670 Services Transport City & Env Community 3.864 2.864 (1.000) Services Stadium City & Env Economic 0.058 0.058 0.000 Services Development CANS Housing & 13.498 11.814 (1.684) Public Protection CANS Communities 4.238 4.238 0.000 and Culture CANS Highways, 4.549 4.342 (0.207) Waste & Fleet CBSS Property 4.016 4.223 0.207 Services CBSS Admin Accom 14.030 14.030 0.000
CBSS IT Development 1.438 1.438 0.000 Plan CBSS Miscellaneous 0.330 0.330 0.000 (Contingency etc) CBSS Economic 1.433 1.433 0.000 Infrastructure Fund Total 67.067 65.153 (1.914)
Table 2 Capital Programme Forecast Outturn 2012/13
7. To the mid point in August there was £15.990m of capital spend representing 24.75% of the revised monitor 1 budget.
Analysis
8. A summary of the key exceptions and implications on the capital programme are highlighted below.
ACE - Education and Children’s Services
Adjustments
9. At this monitor 1, the Multi-Use Games Area (MUGA) at Burnholme School for £0.1m (externally funded) has been added to the Capital programme for approval.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.