City of York Council
Executive, Tuesday 6 November 2012 at 5.30pm

Community Stadium Update

Agreed Executive 2 papers

Executive agreed this item on Tuesday 6 November 2012. Below is the council's own wording, with the papers it was decided on.

Item52

Resolved

That Cabinet agrees to: i) Note progress on the project to date and the timetable for the procurement and associated decisions, in particular the key issues, set out in paragraph 9 of the report, relating to the financial challenges facing the future provision of the existing leisure facilities in the City. ii) Agree the key amendments to the business case and note the financial implications. iii) Note the updated risk register, the potential financial impact of any abortive costs. iv) Agree the proposed Governance arrangements for the project. v) Note the roles, responsibilities and delegated powers of the key individuals and bodies within the governance structure (set out in detail in Annex 1) and in particular the role of the Project Board set out in paragraph 14 of the report. vi) Agree Option C set out in paragraph 35 as the new interim contract arrangements for the Huntington Stadium Leisure Complex ( Waterworld ). vii) Note the financial implications of the interim arrangements for the Huntington Stadium Leisure Complex ( Waterworld ) contract. REASON: To update Cabinet on this scheme, agree key amendments and new arrangements for Waterworld in order to progress the project. That Cabinet agrees to: i) Note progress on the project to date and the timetable for the procurement and associated decisions, in particular the key issues, set out in paragraph 9 of the report, relating to the financial challenges facing the future provision of the existing leisure facilities in the City. ii) Agree the key amendments to the business case and note the financial implications. iii) Note the updated risk register, the potential financial impact of any abortive costs. iv) Agree the proposed Governance arrangements for the project. v) Note the roles, responsibilities and delegated powers of the key individuals and bodies within the governance structure (set out in detail in Annex 1) and in particular the role of the Project Board set out in paragraph 14 of the report. vi) Agree Option C set out in paragraph 35 as the new interim contract arrangements for the Huntington Stadium Leisure Complex ( Waterworld ). vii) Note the financial implications of the interim arrangements for the Huntington Stadium Leisure Complex ( Waterworld ) contract. 1. REASON: To update Cabinet on this scheme, agree key amendments and new arrangements for Waterworld in order to progress the project.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

Cabinet 6 November 2012

Report of Cabinet Member for Leisure, Culture &Tourism

Community Stadium Update Summary 1. The purpose of this paper is to: • Outline the procurement timetable and the stages at which key decisions will need to be made. • Set out the need for new Project Management / Governance arrangements. • Provide an update on the Business Plan. • Consider the updated risk register and the financial impact of potential abortive costs. • Consider new interim arrangements for the current Waterworld contract.

2. Decisions are required from Cabinet: 1) To note progress on the project to date and the timetable for the procurement and associated decisions, in particular the key issues set out in para 9 relating to the financial challenges facing the future provision of the existing leisure facilities in the City. 2) Agree the key amendments to the business case and note the financial implications. 3) Note the updated risk register, the potential financial impact of any abortive costs. 4) Agree the proposed Governance arrangements for the project. 5) Note the roles, responsibilities and delegated powers of the key individuals and bodies within the governance structure (set out in detail in Annex 1) and in particular the role of the Project Board set out in para 14. 6) Agree Option C set out in para 35 as the new interim contract arrangements for the Huntington Stadium Leisure Complex (Waterworld). 7) Note the financial implications of the interim arrangements for the Huntington Stadium Leisure Complex (Waterworld) contract.

Background 3. The Business Case and budget for the project were noted at Cabinet on 6th March 2012 and approved at Full Council on 30th March 2012. Outline planning permission was granted on the 5th July, following confirmation from the Secretary of State that the decision should be dealt with locally. The 3 month Judicial Review period ended without challenge on the 6th October 2012.

4. At the January meeting of the Cabinet Member for Leisure, Culture & Tourism the outline procurement strategy was agreed for the project. The procurement process has started to Design, Build Operate and Maintain (DBOM) the stadium and operate and maintain the Council’s leisure facilities as one single package. An OJEU notice starting the formal procurement activity for the project was posted on the 14th September 2012. 5. A bidder day was held on Friday 28th September which was very successful and attended by representatives from all sections of the construction, design and leisure operations industry. 6. The indicative timeline below outlines the key points in the procurement process: Indicative Timetable – Events and Milestones OJEU Notice September 2012 PQQ return October 2012 Invitation to submit Outline Proposals November 2012 Construction of Retail development begins October 2012 Evaluation of ISOP bids January 2013 Commence Dialogue phases January 2013 Final bids September 2013 Contract Award November 2013 Leisure Centre Contract operational January 2014 Planning Submission January 2014 Archaeological digs begin on stadium site February 2014 Construction begins June 2014 Completion July 2015

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Roles Delegations CS Goverance v1.1Appendix 1 63 KB Download
PDF
Community Stadium UpdateReport 145 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 12 attended
JA
Councillor James AlexanderChair, present
SC
Councillor Sonja CrispCommittee Member, present
JG
Councillor Julie GunnellCommittee Member, present
DL
Councillor David LeveneCommittee Member, present
JL
Councillor Janet LookerCommittee Member, present
DM
Councillor Dave MerrettCommittee Member, apologies
TS
Councillor Tracey Simpson-LaingVice-Chair, present
DW
Councillor Dafydd WilliamsCommittee Member, present
IC
Councillor Ian CuthbertsonAttendee, in attendance
PH
Councillor Paul HealeyAttendee, in attendance
PD
Councillor Paul DoughtyAttendee, in attendance
CS
Councillor Chris StewardAttendee, in attendance

On this subject at York

Search all
  1. Community Stadium UpdateThis decision
  2. Community Stadium Project – Stadium Naming Rights SponsorshipAgreed
  3. Community Stadium Project UpdateNoted
  4. Community Stadium Project ReportNoted
  5. Community Stadium & Leisure Facilities ReportApproved
  6. Community Stadium and Leisure Facilities ReportAgreed

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies