That Cabinet agree to: (i) Note the 2012/13 capital outturn position of £46.476m and approve the requests for slippage totalling £10.457m from the 2012/13 programme to future years. (ii) Note the outturn position of the Economic Infrastructure Fund in 2012/13 and revisions to the profile of the £28.5m as set out in Annex B of the report. (iii) Approve the revised Economic Infrastructure Fund profile set out at Annex B of the report. REASON: To allow the continued effective financial management of the capital programme from 2013/14 to 2017/18. That Cabinet agree to: (i) Note the 2012/13 capital outturn position of £46.476m and approve the requests for slippage totalling £10.457m from the 2012/13 programme to future years. (ii) Note the outturn position of the Economic Infrastructure Fund in 2012/13 and revisions to the profile of the £28.5m as set out in Annex B of the report. (iii) Approve the revised Economic Infrastructure Fund profile set out at Annex B of the report. REASON: To allow the continued effective financial management of the capital programme from 2013/14 to 2017/18.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
3. The capital programme was developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 23 February 2012. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals and associated capital receipt sales do follow a consultation process with local Councillors and residents in the locality of the individual schemes.
Summary of the 2012/13 Capital Programme Outturn
4. The 2012/13 – 2016/17 capital programme was approved by Council on 23 February 2012. Since then amendments have taken place, as reported to Cabinet throughout the year, which have resulted in the current approved capital programme for 2012/13 of £57.281m, financed by £21.227m of external funding, and internal funding of £36.054m. 5. The 2012/13 capital outturn of £46.476m represents an overall variation against the Monitor 3 budget of -£10.805m. The variation is comprised of two components.
6. The first component is re-profiling of budget that is currently approved in the capital programme but requires moving to or from future years in line with a changing timetable of delivery for individual schemes. The second component is genuine under/over spends against the latest approved budget.
7. The net variation of -£10.805m in 2012/13 is made up as follows:
• Requests to re-profile budgets of a net -£10.457m of schemes from 2012/13 to future years, • Adjustments to schemes decreasing expenditure by a net -£0.348m.
8. Accordingly there are requests for budgets to be carried forward (re-profiled) in to future years of a net £10.805m with further details provided in the following departmental analysis paragraphs. Table 1 below shows the total variances for individual departments along with requests for re-profiling.
Table 1 – Summary of capital outturn by department
*note that the EIF spend referenced in this table is the prudential borrowing funded capital element only and excludes the revenue New Homes Bonus Funded element – see paragraphs below setting out overall EIF position for inclusion of revenue element
9. The majority of over and under spends are matched by corresponding changes in grant funding and have no impact on the overall funding available. The following paragraphs set out the main variances and the requirements for re-profiling. All the explanations are based on movement against the approved monitor 3 position.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.