That Cabinet agree to: · Note the 2013/14 revised budget of £77.184m as set out in paragraph 6 and at Table 1 of the report; · Note the restated capital programme for 2013/14 – 2017/18 as set out in paragraph 28, Table 2 and detailed in Annex A of the report. Reason: To enable the effective management and monitoring of the Council’s capital programme. That Cabinet agree to: · Note the 2013/14 revised budget of £77.184m as set out in paragraph 6 and at Table 1 of the report; · Note the restated capital programme for 2013/14 – 2017/18 as set out in paragraph 28, Table 2 and detailed in Annex A of the report. Reason: To enable the effective management and monitoring of the Council’s capital programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
3. The capital programme was developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 28 February 2013. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals and associated capital receipt sales do follow a consultation process with local Councillors and residents in the locality of the individual schemes.
Summary of Key Issues
4. An increase of £1.4 m is detailed in this monitor resulting in a revised capital programme of £77.1m. This net increase of £1.4m is made up of £1.392m external funding and £80k from HRA funds.
5. Table 1 outlines the variances reported against each portfolio area. Directorate Department Current Projected Variance Approved Outturn Budget £m £m £m ACE Children’s, 9.870 9.870 0.000 Education and Skills ACE Adult Social 1.225 1.225 0.000 Services CES Strategic 20.858 20.864 0.006 Planning & Transport CES Community 1.850 1.850 0.000 Stadium CES Economic 0.058 0.058 0.000 Development CANS Housing & 17.647 18.994 1.347 Public Protection CANS Communities, 3.294 3.420 0.126 Culture & Public Realm CANS Highways, 4.660 4.654 (0.006) Waste & Fleet CBSS Asset 3.223 3.223 0.000 Management CBSS Admin Accom 2.580 2.580 0.000
CBSS IT Development 0.983 0.983 0.000 Plan CBSS Contingency 0.676 0.676 0.000
CBSS Economic 8.787 8.787 0.000 Infrastructure Fund Total 75.711 77.184 1.473
Table 1 Capital Programme Forecast Outturn 2013/14
6. To the mid point in August there was £9.242m of capital spend representing 12% of the revised monitor 1 budget.
Analysis
7. A summary of the key exceptions and implications on the capital programme are highlighted below. ACE - Education and Children’s Services
8. There are no adjustments or re-profiling requests to the Education and Children’s Service capital programme as a result of this monitor and the forecast spend remains at £9.673m.
ACE – Adult Social Services
9. There are no adjustments or re-profiling requests to the Adult Social Care capital programme as a result of this monitor and the forecast spend is £1.225m.
City & Environmental Services - Strategic Planning and Transport + Economic Development
10. There are no significant variances to report against current approved budget. The Strategic Planning and Transport capital programme is projected to outturn at £20.864m.
11.The Economic Development capital programme is projected to outturn at £58k on budget.
City & Environmental Services – Community Stadium
12. The Community Stadium Project is expected to outturn to budget at £1.850m.
CANS – Housing & Public Protection
Adjustments
13. A number of adjustments are proposed as part of this report all of which (with the exception of the property buy back programme are externally funded)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.