Executive decided this item on Tuesday 5 November 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
[See also Part B minute]
3. The capital programme was developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 28 February 2013. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals and associated capital receipt sales do follow a consultation process with local Councillors and residents in the locality of the individual schemes.
Summary of Key Issues
4. A decrease of £4.611m is detailed in this monitor resulting in a revised capital programme of £72.573m. This net decrease of £4.611m is made up of: • Re-profiling of schemes budgeted at £4.403m to 2014/15 • Reductions of scheme budgeted at £208k funded from external funds of +£20k and CYC resources of -£228. The reduction is comprised in the main of the reduction in the IT development plan in year spend to match available revenue resources as reported below).
5. Table 1 outlines the variances reported against each portfolio area.
Directorate Department Current Projected Variance Approved Outturn Budget £m £m £m ACE Children’s, 9.870 7.375 (2.495) Education and Skills ACE Adult Social 1.225 1.098 (0.127) Services CES Strategic 20.864 20.514 (0.350) Planning & Transport CES Community 1.850 1.850 0.000 Stadium CES Economic 0.058 0.058 0.000 Development CANS Housing & 18.994 18.984 (0.010) Public Protection CANS Communities, 3.420 3.070 (0.350) Culture & Public Realm CANS Highways, 4.654 4.654 0.000 Waste & Fleet CBSS Asset 3.223 2.192 (1.031) Management CBSS Admin Accom 2.580 2.580 0.000
CBSS IT Development 0.983 0.750 (0.233) Plan CBSS Contingency 0.676 0.661 (0.015)
CBSS Economic 8.787 8.787 0.000 Infrastructure Fund Total 77.184 72.573 (4.611)
Table 1 Capital Programme Forecast Outturn 2013/14
6. To the mid point in August there was £18.418m of capital spend representing 25% of the revised monitor 2 budget. Analysis
7. A summary of the key exceptions and implications on the capital programme are highlighted below.
ACE - Education and Children’s Services
8. There is one significant variation to report along with some minor changes reduces the budget by £2.495m in 13/14 to £7.375m.
9. A request is made to re-profile £2.500m of basic need budget from 13/14 to 14/15 and allocate £130k in year to the Knavesmire Expansion scheme. The request for re-profiling is due to a number of new schemes being planned to add pupil places at schools across the city. An expansion of Fulford School is required in order to provide sufficient places to meet rising demand from within the school's catchment area, which includes Wheldrake, Dunnington, Elvington and Naburn in addition to the school's catchment area coverage within the city.
10. The scheme, which is being developed in consultation with the school’s governing body, is planned to increase the school's capacity and will also include significant remodelling and refurbishment of the school estate. The first phase, which is planned to begin in 2014, will enable the school to meet the demand for places from within the catchment area. A second phase will be timed to accommodate additional demand for places arising from the Germany Beck development. The scheme will be funded through a combination of grant funding and S106 contributions from the developers of the Germany Beck site. Detailed design of the various phases is now underway and total budget for all phases is estimated at £3.6m.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
(3)Appendix A | 169 KB | Download |
PDF |
Capital Programme: Monitor Two 2013/14Report | 111 KB | DownloadRead as text |
Follow Executive at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Nov 2026 | Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. | Approved | Open |
| 3 Nov 2026 | Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... | Noted | Open |
| 3 Nov 2026 | Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... | Noted | Open |
| 3 Nov 2026 | Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... | Noted | Open |
| 3 Nov 2026 | Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.