Executive, Tuesday 7 January 2014 at 5.30pm

Community Stadium Update

Agreed Executive 3 papers

Executive agreed this item on Tuesday 7 January 2014. Below is the council's own wording, with the papers it was decided on.

Item88

Resolved

That Cabinet agree: (i) To note progress on the project and procurement to date, particularly that: · The project is proceeding into the final procurement stage within the existing financial parameters. · The changes made to the estimated project timetable and key milestones. · Match-day agreements and leases for the project partners will be finalised and that these will all be subject to the overall project contract. · A detailed report is presented to Cabinet prior to contract award setting out the results of the procurement and the financial implications. (ii) That tenders will be sought that encourage cost effective design solutions for the stadium that: · Meets current Football League and Rugby Football League entry requirements. · Removes any ‘built-in’ expansion requirement. · Results in a well balanced and attractive stadium bowl. · As an option, considers the use of some terracing as a means of increasing the base capacity. · Makes provision within the design to increase the capacity as an all seat solution if the Football Stadium Improvement funding can be legally secured and / or promotion to the Football League ‘Championship’ is achieved at a later date. · Demonstrates an all seat capacity of 10,000 can be achieved at a later stage, within the stadium footprint. (iii) The new Athletics track being delivered at Heslington West Campus as set out in the report, including the payment of a grant of £31,000 for the delivery of a community athletics programme . (iv) To note the risks highlighted and agree that the Project Board continue to manage the project risks. Reason: To ensure the effective delivery of this procurement exercise and that it remains within the financial parameters set. That Cabinet agree: (i) To note progress on the project and procurement to date, particularly that: · The project is proceeding into the final procurement stage within the existing financial parameters. · The changes made to the estimated project timetable and key milestones. · Match-day agreements and leases for the project partners will be finalised and that these will all be subject to the overall project contract. · A detailed report is presented to Cabinet prior to contract award setting out the results of the procurement and the financial implications. 1. (ii) That tenders will be sought that encourage cost effective design solutions for the stadium that: · Meets current Football League and Rugby Football League entry requirements. · Removes any ‘built-in’ expansion requirement. · Results in a well balanced and attractive stadium bowl. · As an option, considers the use of some terracing as a means of increasing the base capacity. · Makes provision within the design to increase the capacity as an all seat solution if the Football Stadium Improvement funding can be legally secured and / or promotion to the Football League ‘Championship’ is achieved at a later date. · Demonstrates an all seat capacity of 10,000 can be achieved at a later stage, within the stadium footprint. 2. (iii) The new Athletics track being delivered at Heslington West Campus as set out in the report, including the ... view the full minutes text for item 88.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive

Cabinet 7 January 2014

Report of Cabinet Member for Leisure, Culture &Tourism

Community Stadium Update

Summary 1. The purpose of this paper is to provide: • An update on the progress of the stadium and athletics elements of the overall project. • Options for the stadium’s design and increased base capacity. • A delivery plan for the Athletics facility at the University of York. • The procurement timetable and the stages at which key decisions will need to be made. • Risks to the delivery and ongoing operation of the project. • A more detailed paper covering all aspects of the project (including details of the leisure facilities contract) will be presented to Cabinet later in the year, once a preferred bidder has been identified.

2. Decisions are required from Cabinet to: • Note progress on the project to date and the timetable for the procurement and associated decisions. • Agree the change to the design requirements for the stadium • Agree the Athletics delivery plan and site as outlined in the report. • Note the key risks highlighted and the process in place for risk management. Background 3. The Business Case and budget for the project were noted at Cabinet on 6th March 2012 and approved at Full Council on 30th March 2012. Outline planning permission was granted on the 5th July, following confirmation from the Secretary of State that the decision should be dealt with locally. The 3 month Judicial Review period ended without challenge on the 6th October 2012.

4. At the January 2012 meeting of the Cabinet Member for Leisure, Culture & Tourism the outline procurement strategy was agreed for the project. The procurement process ongoing is to Design, Build, Operate and Maintain (DBOM) the stadium and operate and maintain the Council’s leisure facilities as one single package. An OJEU notice starting the formal procurement activity for the project was posted on the 14th September 2012. 5. A further report will be brought to Cabinet setting out the full details and cost implications of the Preferred Bidder’s final proposals. This will include proposals relating to the City’s leisure facilities. Project Progress 6. This procurement is being conducted by Competitive Dialogue which is governed by strict EU regulations that requires strict confidentiality due to commercial sensitivities. The contract is for the Design, Build, Operation and Maintenance of the Stadium, as well redevelopment and investment into the Council’s leisure facilities. This will be for a 13 year period with the option for an additional 5 years (total 18 years).

7. Formal bids were submitted in September 2013 and subsequently assessed and scored. The final two bidders have been confirmed and final proposals are being prepared. This phase will run until March when dialogue will be closed. During this period, all aspects of the detailed design, commercial and operational arrangements must be finalised, before bidders are asked to make their competitive bids. 8. A summary of the issues arising from the ITCD submissions is provided below: • All submissions were able to meet the basic minimum criteria set of 6,000 capacity all-seat stadium, community hub within the financial parameters of the project • Changes are required to the design requirements if an attractive and well balanced stadium is to be delivered. The built in expansion requirement from 6,000 to 12,000 has considerable cost and design implications for something that may never happen.

• Scope exists to increase in the base capacity of the stadium through cost efficiencies and alternative design solutions, including the consideration of the use of some terracing.

Stadium Business Case 9. The business case was approved at the March 2012 Cabinet. This is an iterative process and the business case has developed as the procurement has progressed.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Min design spec for Athletics FacilityAppendix 1 16 KB Download
PDF
Design and layout plan of Athletics FacilityAppendix 2 421 KB Download
PDF
Community Stadium UpdateReport 117 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 10 attended
JA
Councillor James AlexanderChair, present
SC
Councillor Sonja CrispCommittee Member, present
LC
Councillor Linsay Cunningham-CrossCommittee Member, present
DL
Councillor David LeveneCommittee Member, present
JL
Councillor Janet LookerCommittee Member, present
DM
Councillor Dave MerrettCommittee Member, present
TS
Councillor Tracey Simpson-LaingVice-Chair, present
DW
Councillor Dafydd WilliamsCommittee Member, present
MW
Councillor Mark WartersAttendee, in attendance
DT
Councillor Dave TaylorAttendee, in attendance

On this subject at York

Search all
  1. Community Stadium UpdateThis decision
  2. Community Stadium Project – Stadium Naming Rights SponsorshipAgreed
  3. Community Stadium Project UpdateNoted
  4. Community Stadium Project ReportNoted
  5. Community Stadium & Leisure Facilities ReportApproved
  6. Community Stadium and Leisure Facilities ReportAgreed

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies