That Cabinet: · Note the 2013/14 revised budget of £60.914m as set out in paragraph 5 and Table 1 of the report. · Note the restated capital programme for 2013/14 – 2017/18, totalling £205.482m as set out in paragraph 41, Table 2 and detailed in Annex A. · Approve the use of £66k of contingency to fund the York Explore Roof Replacement and note the use of contingency set out in paragraph 38. Reason: To enable the effective management and monitoring of the Council’s capital programme. That Cabinet: · Note the 2013/14 revised budget of £60.914m as set out in paragraph 5 and Table 1 of the report. · Note the restated capital programme for 2013/14 – 2017/18, totalling £205.482m as set out in paragraph 41, Table 2 and detailed in Annex A. · Approve the use of £66k of contingency to fund the York Explore Roof Replacement and note the use of contingency set out in paragraph 38. 1. Reason: To enable the effective management and monitoring of the Council’s capital programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
3. The capital programme was developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 28 February 2013. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals and associated capital receipt sales do follow a consultation process with local Councillors and residents in the locality of the individual schemes.
Summary of Key Issues
4. A decrease of £11.659m is detailed in this monitor resulting in a revised capital programme of £60.914m. This net decrease of £11.659m is made up of: • Re-profiling of schemes budgeted at £12.136m to 2014/15 • Increases of schemes budgeted at £477k funded from external funds of +£477k. 5. Table 1 outlines the variances reported against each portfolio area.
Directorate Department Current Projected Variance Approved Outturn Budget £m £m £m ACE Children’s, 7.375 6.325 (1.050) Education and Skills ACE Adult Social 1.098 0.973 (0.125) Services CES Transport 20.514 20.518 0.004
CES Highways & 4.654 4.754 0.100 Waste CES Community 1.850 1.660 (0.190) Stadium CES Economic 0.058 0.058 0.000 Development CANS Housing & 18.984 11.472 (7.512) Public Protection CANS Communities, 3.070 1.378 (1.692) Culture & Public Realm CBSS Asset 2.192 1.857 (0.335) Management CBSS Admin Accom 2.580 2.580 0.000
CBSS IT Development 0.750 0.750 0.000 Plan CBSS Contingency 0.661 0.313 (0.348)
CBSS Economic 8.787 8.276 (0.511) Infrastructure Fund Total 72.573 60.914 (11.659)
Table 1 Capital Programme Forecast Outturn 2013/14
6. To the mid point in January there was £29.615m of capital spend representing 48.6% of the revised monitor 3 budget.
Analysis 7. A summary of the key exceptions and implications on the capital programme are highlighted below.
ACE - Education and Children’s Services
8. The schemes scheduled to be carried out over summer 2013 for the DfE Maintenance programme of works are now all complete with only retentions outstanding in most cases. It is still expected that the majority of the £3.120m budget will be spent in 2013/14, although a small element (£300k) will not be required in this financial year and can be re-profiled into 2014/15 where it will be added to the funding available to be allocated to schemes in that financial year. This approach will still leave a contingency available for any urgent works which may be required before the end of the year.
9. Work on Basic Need schemes planned for 2013/14 are now complete and are projected to spend a total of £980k. It is requested that £800k be re-profiled to 2014/15 to fund the project at Fulford School and Carr Junior which are planned for summer 2014.
ACE – Adult Social Services
10.There is one re-profiling request in relation to the Elderly Peoples Homes Infrastructure works capital programme as a result of this monitor. It is requested that £145k be re-profiled from 2013/14 to 2014/15 due to the approach for the re-provision of the Councils care home needs being a joint procurement of the two sites as oppose to being developed individually.
11.It should be noted that an amount of £20k has been included at this monitor to reflect the Cabinet Approval of the Collaborative Health and Social Care Hub report on the 3rd December 2013 that recommended the use of £20k for making the new Voluntary Sector Social Care Hub more accessible.
CES – Transport
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.