York Outer Ring Road Improvement Scheme

Agreed Executive 1 paper

Executive agreed this item on Tuesday 3 March 2015. Below is the council's own wording, with the papers it was decided on.

Item115

Resolved

That Cabinet agree to instruct officers to progress Option 1 to continue the delivery of the Outer Ring Road Upgrade using funds allocated in 2015/16. Reason: To maintain progress on the project pending the formalisation of the West Yorkshire plus Transport Fund. That Cabinet agree to instruct officers to progress Option 1 to continue the delivery of the Outer Ring Road Upgrade using funds allocated in 2015/16. 1. Reason: To maintain progress on the project pending the formalisation of the West Yorkshire plus Transport Fund.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 10 pages

Executive summary

1. Improvements to seven junctions on the A1237 York Outer Ring Road (YORR) is one of the York projects that make up the programme of schemes to be funded through the West Yorkshire plus Transport Fund (WY+TF). The formal establishment of the fund is to be finally approved. Subject to approval at the Full Council meeting in February an allocation is proposed to be provided within the base budget for 2015/16 to continue development of the WY+TF schemes.

2. The YORR has been identified as a quick-win project, i.e. for delivery by 2020/21 and as such work has commenced on the project. Prior to the formal establishment of the WY+TF progress on the project during 2014/15 has being funded internally via an Economic Infrastructure Fund (EIF) contribution. Until the WY+TF and local funding contribution has been formally agreed, Cabinet is asked to consider a number of options and associated risks for progressing the project.

3. This report has been written on the basis that Full Council approved an additional recurring £500k allocation in the base budget for the progression of the WY+TF. Recommendations

4. It is recommended that Cabinet

Instruct officers to progress Option 1 to continue the delivery of the Outer Ring Road Upgrade using funds allocated in 2015/16 Reason: To maintain progress on the project pending the formalisation of the West Yorkshire plus Transport Fund. Background

West Yorkshire + Transport Fund

5. The government has changed the way in which local transport major scheme funding is organised from 2015/16 onwards. Local authorities were invited to become members of Local Transport Bodies (LTB). By devolving power and funding for transport major schemes from the Department for Transport (DfT) the LTB becomes the organisation through which scheme prioritisation and funding decisions are made. 6. The Cabinet approved (9 October 2012) the proposal for York to join a West Yorkshire and York LTB subject to detailed Governance arrangements being agreed. The funding allocation for the West Yorkshire and York LTB was confirmed in 2014 as approximately £1bn over 20 years. The first six years contribution from the government is confirmed; the remaining funding is dependant on progress against delivery. 7. The West Yorkshire Combined Authority (WYCA) has still to formally agree with the DfT the programme, processes and borrowing mechanisms to deliver the WY+TF in its entirety before the fund can be formally established.

8. Subject to approval at its meeting in February 2015, it is proposed that the Council will provide a £500k allocation that will form the 2015/16 contribution to the WY+TF if the setting up of the fund is confirmed later in 2015. It is anticipated that a report will be presented to Members in late summer 2015 considering the implications of fully joining the WY+TF.

Scheme Development

9. Following initial approval from each individual district to set up the WY+TF, a number of schemes that could be brought forward in the early years of the fund were identified.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
York Outer Ring Road Improvement SchemeReport 10 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 14 attended
DW
Councillor Dafydd WilliamsChair, present
SC
Councillor Sonja CrispCommittee Member, present
LC
Councillor Linsay CunninghamCommittee Member, present
DL
Councillor David LeveneCommittee Member, present
JL
Councillor Janet LookerCommittee Member, present
TS
Councillor Tracey Simpson-LaingVice-Chair, present
AD
Councillor Andy D'AgorneAttendee, in attendance
CS
Councillor Chris StewardAttendee, in attendance
MW
Councillor Mark WartersAttendee, in attendance
JG
Councillor John GalvinAttendee, in attendance
AR
Councillor Ann ReidAttendee, in attendance
BW
Councillor Brian WatsonAttendee, in attendance

All 14 on the meeting page

On this subject at York

Search all
  1. York Outer Ring Road Improvement SchemeThis decision
  2. Major Projects (Station Gateway and York Outer Ring Road Business Case)Approved
  3. York Outer Ring Road (YORR) - Proposed A1237 (Rawcliffe to Little Hopgrove) Dualling - Update on Progress and Proposed Utility Diversions (6:32 pm)Noted
  4. York Outer Ring Road (YORR) – Phase 1 Dualling – Evaluation of the Consultation Process and Resolution to Submit a Planning ApplicationNoted
  5. York Outer Ring Road Phase 1 Dualling - Resolution in principle to promote a Compulsory Purchase Order and associated Side Roads Order.Noted
  6. York Outer Ring Road Phase 1 Dualling - Procurement Strategy, Approach to Public Engagement and LandscapingApproved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies