Capital Programme - Monitor 2 2015/16

Agreed Executive 2 papers

Executive agreed this item on Thursday 26 November 2015. Below is the council's own wording, with the papers it was decided on.

Item80

Resolved

That Executive agree to: (i) Note the 2015/16 revised budget of £94.389m, as set out in paragraph 6 and Table 1 of the report. (ii) Note the restated capital programme for 2015/16 – 2019/20 as set out in paragraph 33, Table 2 and detailed in Annex A of the report. 1. Reason: To enable the effective management and monitoring of the Council’s capital programme. That Executive agree to: (i) Note the 2015/16 revised budget of £94.389m as set out in paragraph 6 and Table 1 of the report. (ii) Note the restated capital programme for 2015/16 – 2019/20 as set out in paragraph 33, Table 2 and detailed in Annex A of the report. 1. Reason: To enable the effective management and monitoring of the Council’s capital programme.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 10 pages

Summary

1. The purpose of this report is to set out the projected outturn position for 2015/16 including any adjustments and requests to re-profile budgets between years.

2. The 2015/16 capital programme as approved by Council on 26 February 2015 and updated for amendments reported to Executive and Council is £95.290m.

Recommendations

3. Executive is asked to:

 Recommend to Council a decrease in the 2015/16 programme of £901k as detailed in the report and contained in Annex A.

 Note the 2015/16 revised budget of £94.389m as set out in paragraph 6 and Table 1.

 Note the restated capital programme for 2015/16 – 2019/20 as set out in paragraph 33, Table 2 and detailed in Annex A. Reason: To enable the effective management and monitoring of the Council’s capital programme.

Consultation

4. The capital programme was developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 26 February 2015. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals and associated capital receipt sales do follow a consultation process with local Councillors and residents in the locality of the individual schemes. Summary of Key Issues

5. A decrease of £901k is detailed in this monitor resulting in a revised capital programme of £94.389m. £961k of the decrease is due to re- profiling to budgets to future years. Offsetting this is a net increase of £60k due to an increase in external contributions.

6. Table 1 outlines the variances reported against each portfolio area.

Directorate Department Current Projected Variance Approved Outturn Budget £m £m £m CSES Children’s 13.361 13.361 0.000 Services, Education & Skills ASC Adult Social 1.464 1.464 0.000 Services CANS Communities 3.127 2.660 (0.467) Culture & Public Realm CANS Housing & 19.193 19.133 (0.060) Community Safety

CES Highways & Waste 6.226 6.226 0.000

CES Transport 8.619 8.619 0.000

CES Econ Development 0.058 0.000 (0.058) (trfrd to Asst Mgt) CES Community 20.714 20.714 0.000 Stadium CBSS Asset Management 3.559 3.576 0.017

CBSS West Offices - 0.512 0.512 0.000 Admin Accom CBSS IT Development 2.696 2.383 (0.313) Plan CBSS Misc(Contingency ) 0.443 0.423 (0.020)

CBSS Corporate 15.318 15.318 0.000 Schemes (former EIF) Total 95.290 94.389 (0.901)

Table 1 Capital Programme Forecast Outturn 2015/16 Analysis

7. A summary of the key exceptions, and their implications on the capital programme, are highlighted below.

CSES – Children Services, Education and Skills

8. There are no variations to report and the forecast spend inclusive of the above for 15/16 is £13.361m.

Adult Social Services

9. No variations are proposed as part of this report and the forecast spend inclusive of the above for 15/16 is £1.464m.

Communities and Neighbourhood Services – Communities, Culture and Public Realm

10. Two schemes require re-profiling of budgets over £100k to future years. Better Play Areas requires budget of £290k to be moved to 16/17 from 15/16. This is to allow time for planning permissions to be obtained. Secondly the Knavesmire Culverts schemes requires £270k to be re- profiled from 15/16 to 16/17 as the CCTV surveys to assess the condition of specific culverts have not yet been undertaken and remediation work will not start until next financial year.

11. Programmed work will still be completed at the Leeman Road War Memorial and Triangle Gardens. However, it has been identified that landscaping works can be funded from revenue using section 106 funds allocated to open spaces.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme: Monitor 2 2015/16Report 10 pages DownloadRead as text
PDF
Monitor 2 Annex A v4Appendix 3 pages Download

At this meeting

Whole meeting

Who was there

8 of 11 attended
CS
Councillor Chris StewardChair, present
KA
Councillor Keith AspdenVice-Chair, present
NA
Councillor Nigel AyreCommittee Member, present
JB
Councillor Jenny BrooksCommittee Member, present
DC
Councillor David CarrCommittee Member, present
IG
Councillor Ian GilliesCommittee Member, present
CR
Councillor Carol RuncimanCommittee Member, present
AW
Councillor Andrew WallerCommittee Member, present
IC
Councillor Ian CuthbertsonAttendee, in attendance
JH
Councillor Johnny HayesAttendee, in attendance
DC
Councillor Denise CraghillAttendee, in attendance

On this subject at York

Search all
  1. Capital Programme - Monitor 2 2015/16This decision
  2. Capital Programme Monitor Update 2 Report (4:47pm)Noted
  3. Capital Programme - Monitor 1 2026/27 (4:46pm)Noted
  4. Capital Programme Outturn 2025/26 and Revisions to the 2026/27 - 2029/30 ProgrammeApproved
  5. Recommendations of Executive in relation to the Capital Programme - Monitor 3 2025/26Approved
  6. Capital Programme - Monitor 3 2025/26Approved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies