City and Environmental Services Capital Programme - 2016/17 Budget Report
ApprovedExecutive3 papers
Decision Session - Executive Member for Transport - Expired approved this item on Thursday 14 April 2016. Below is the council's own wording, with the papers it was decided on.
That the Executive Member approves the proposed 2016/17 City and Environmental Services Transport Capital Programme as set out in the report and Annexes 1 and 2. Reason: To implement the Council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities and deliver schemes identified in the Council’s Transport Programme. That the Executive Member approves the proposed 2016/17 City and Environmental Services Transport Capital Programme as set out in the report and Annexes 1 and 2. Reason: To implement the Council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities and deliver schemes identified in the Council’s Transport Programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired, 9 pages
Recommendations
2. The Executive Member is asked to:
Approve the proposed 2016/17 City and Environmental Services Transport Capital Programme as set out in this report and Annexes 1 and 2. Reason: To implement the council’s transport strategy identified in York’s third Local Transport Plan and the Council Priorities, and deliver schemes identified in the council’s Transport Programme
Background 3. Following approval at Full Council on 25 February 2016, the CES Transport Capital Programme budget for 2016/17 has been confirmed as £3,793k. The budget includes £1,920k of Local Transport Plan (LTP) funding, plus other funding from the Better Bus grant, the Department for Transport’s Local Pinch Point Funding (Tranche 3) grant, developer contributions, and council resources. Proposed Transport Capital Programme 4. The proposed programme has been split into a number of blocks (shown in Table 1), which summarise the strategic aims of the third Local Transport Plan (LTP3) and the Council Plan. More details of the proposed allocations are included in the following paragraphs and in Annex 1 to this report.
5. The allocations shown in Table 1 include funding for schemes committed in previous years and an allowance for overprogramming. Overprogramming is used in the capital programme to ensure the funding allocation is fully spent within the year. It allows reserve schemes to be developed and delivered if other schemes are delayed due to unforeseen circumstances.
6. From the start of the LTP3 period, the level of overprogramming has been kept to a much lower proportion than in previous years, due to the reduced Local Transport Plan funding allocation compared to previous years.
Table 1: Proposed 2016/17 Transport Capital Programme Proposed Transport Capital £1,000s Programme Access York Phase 1 150 Public Transport 590 Traffic Management 1,960 Pedestrian & Cycling Schemes 553 Safety Schemes 250 Scheme Development and Design 300 Costs CES Maintenance Schemes 350 Total Transport Programme 4,153 Overprogramming 360 Total Transport Budget 3,793
7. The proposed programme for 2016/17 has been developed to support the five strategic aims of LTP3, and the priorities identified in the Council Plan. It includes some schemes from the 2015/16 capital programme which have carried over into 2016/17, and schemes that were developed in 2015/16 for implementation in 2016/17.
8. Project Initiation Documents (PIDs) have been drafted for all new schemes and the proposed reserve schemes in the 2016/17 capital programme. These summarise the aims of the scheme, the expected outcomes, and the proposed programme of works, and are listed in Annex 2 to this report.
9. Following the completion of the Access York scheme in summer 2014, funding has been allocated for the payment of the final retention for the construction works, and other ongoing issues that may still need to be addressed.
10. Funding has been allocated for the ongoing programme of improvement works at Park & Ride sites across the city, and for work to improve bus stops across the city to address accessibility issues. Funding has been carried forward from the 2015/16 capital programme for the installation of a new bus shelter on Rougier Street, which will be installed once the work on Roman House has been completed by the developer in autumn 2016.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.