City and Environmental Services Capital Programme - 2015/16 Outturn Report
NotedExecutive3 papers
Decision Session - Executive Member for Transport - Expired noted this item on Thursday 9 June 2016. Below is the council's own wording, with the papers it was decided on.
That the progress in delivering schemes be noted and the proposed funding carryovers be approved, as set out in paragraphs 23 to 31 of the Officer’s report. Reason: To enable the effective management and monitoring of the council’s capital programme. That the progress in delivering the capital programme schemes be noted and the proposed funding carryovers be approved, as set out in paragraphs 23 to 31 of the Officer’s report. Reason: To enable the effective management and monitoring of the council’s capital programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired, 9 pages
Summary
1. The purpose of this report is to inform the Executive Member of the outturn position for the 2015/16 CES Transport Capital Programme, any variations between the budget and the outturn, and the progress of schemes in the year.
Recommendations
2. The Executive Member is asked to:
Note the progress in delivering schemes, and approve the proposed funding carryovers set out in paragraphs 23 to 31. Reason: To enable the effective management and monitoring of the council’s capital programme
Background 3. The CES Transport Capital Programme budget for 2015/16 was confirmed as £5,292k at Full Council on 26 February 2015, and details of the programme were presented to the Executive Member at the March Decision Session meeting. The programme was finalised on 10 September 2015 when the Cabinet Member was presented with the Consolidated Capital Programme, which included all schemes and funding that had carried over from 2014/15. 4. A number of amendments to the programme were also made at the Monitor 1 and Monitor 2 reports to Decision Session in November 2015 and February 2016.
5. As a result of these amendments, the approved budget for the 2015/16 Transport Capital Programme at 31 March 2016 was £6,472k, which includes Local Transport Plan (LTP) funding, Better Bus Area Fund grant, Clean Bus Technology grant, developer contributions, council resources, and funding from the Department for Transport for the A19 Pinchpoint scheme. This represents the budget available to spend, and is therefore net of the overprogramming built into the Local Transport Plan element of the programme, which can be used to ensure the available funding is fully spent in each year if required.
6. The CES Transport Capital Programme also includes funding from CYC Resources for the alleygating programme and the maintenance of the city walls.
7. External funding was added to the 2015/16 budget at year-end to deliver several schemes in the programme, which has increased the budget to £6,993k.
8. Table 1 shows the current capital programme:
Table 1: Current Approved 2015/16 Capital Programme Gross External Capital Budget Funding* Receipts £1,000s £1,000s £1,000s Planning & Transport Budget 5,292 3,919 1,373 Variations approved at 2,112 1,991 121 Consolidated Report Variations approved at Monitor - - - 1 Report Variations approved at Monitor -932 -932 2 Report Funding added at year-end 521 521 Current CES Capital 6,993 5,499 1,494 Programme *External funding refers to government grants, non government grants, other contributions, developer contributions and supported capital expenditure. Summary of Key Issues
9. Against the budget of £6,993k in 2015/16, there is an outturn of £3,690k (53%). This is a high level of underspend compared to previous years, and is due to delays in progressing some of the larger schemes in the programme; additional DfT grant funding being received too late in the year to deliver the schemes; and delivery of some schemes under budget.
10. In previous years, additional resources have sometimes been introduced to speed up delivery on other schemes and deliver full spend in the year. This was not considered appropriate for 2015/16, due to the need for funding to be slipped to 2016/17 for delivery of the specific schemes.
11. A substantial amount of work has been progressed in the year, including the following schemes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.