Decision Session - Executive Member for Transport - Expired noted this item on Thursday 9 June 2016. Below is the council's own wording, with the papers it was decided on.
That the findings of the review be noted and the column replacement programme in its present form be approved. Reason: Council Officers and the specialist structural engineer consider that the identified columns represent a credible risk of structural failing or collapse. The manufacturers’ serviceable life of a concrete column is 20 years. The City of York Council has not installed any concrete columns since 1997 and there are no records of installation dates. However from testing information some columns date back to 1970. That the findings of the review be noted and approval given to the column replacement programme as outlined. Reason: Council Officers and the specialist structural engineer consider that the identified columns represent an increased but not immediate risk of structural failing or collapse. The manufacturers’ serviceable life of a concrete column is 20 years. The City of York Council has not installed any concrete columns since 1997 and there are no records of installation dates. However from testing information some columns date back to 1970.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Transport - Expired, 6 pages
Summary
1. This report presents a review of how the current concrete column stock is deteriorating and how the street lighting team are currently managing the risk. The review proposes the implementation of a replacement programme of age expired concrete columns. Recommendations 2. The Executive Member is requested to note the findings of the report, and approve the column replacement programme in its present form. Reasons: 3. Council Officers and the specialist structural engineer consider that the identified columns represent a credible risk of structural failing or collapse. The manufacturers’ serviceable life of a concrete column is 20 years. The City of York Council has not installed any concrete columns since 1997 and there are no records of installation dates. However from testing information some columns date back to 1970.
Background
4. Street lighting columns all have manufacturer’s recommended serviceable life, in years, at the date of manufacture for both concrete (20 years) and steel units (30years). The majority (90%) of York’s concrete street lighting stock has exceeded this date. 5. Columns which have exceeded their serviceable life are being managed on an annual program of structural testing. The testing includes metal fatigue and corrosion for steel and visual inspections for concrete. The authority has approx 19,000 columns / street lights of various heights and construction, of which approx 5778 are concrete. The concrete columns are no longer being installed due to the fragile nature and deterioration over time. The last recorded concrete unit to be installed was in 1997. In 2015 there were 53 concrete failures / collapse which required immediate response to remove the columns.
Assessment of the risk and proposed accelerated replacement programme
6. The objectives of an ongoing concrete column replacement program are various. Concrete columns are deemed to be at a higher risk of collapse than tubular/sheet steel due to the nature of the manufacturing process and the way they have been constructed. City of York Council have been managing their column asset with a regime of structural testing and visual inspections for concrete and steel over a number of years with a specialist structural tester, to adhere with legislation and TR22 managing a vital asset.
7. The table below shows an accelerated replacement programme. If the street lighting team replace the Concrete columns on an average of 289 columns per year, to completely replace all concrete columns it would still take 20 years. Table 1: Proposed replacement Programme 2016 / 2036 Table 1 above explained:
8. The yellow header numbers 1~20 these numbers represent the programme in years. The numbers directly below the highlighted year numbers, represent the total number of columns required to be replaced on an annual basis to complete the programme. Example: Year 10 would require an annual replacement programme of 578 concrete columns. 9. Column year 20 shows this year’s investment in replacing concrete columns, This indicates if we continue to invest at this current rate it will take 20 years to remove all concrete columns from York’s inventory.
10. Funding has been allocated for the replacement of 289 concrete columns. These columns have been identified through structural testing and are the highest risk. The concrete columns will be replaced with tubular steel including PPA coating and a life expectancy of 35 years in northern Europe.
Table 2: Proposed 2016/17 replacement Programme Proposed replacement no Date Programme Column installs 289 June / Aug Lantern installs 289 June / Aug Column removals 289 Aug / Sep Underground transfers 289 Aug / Sep
11. The proposed programme has been split into a number of blocks (shown in Table 2), which summarise the strategic aims of the team
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Transport - Expired at York and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.